M54 to M6 Link Road Amserlen yr archwiliad

Mae amserlen yr archwiliad yn dangos dyddiadau digwyddiadau a therfynau amser ar gyfer cyflwyniadau.

Os ydych wedi cofrestru i leisio'ch barn, gallwch wneud hyn yn ystod y cam archwilio.

Y cam archwilio

Agorodd yr archwiliad ar 21 October 2020

Caeodd yr archwiliad ar 21 April 2021

Terfynau amser a digwyddiadau i ddod

Nid oes unrhyw derfynau amser neu ddigwyddiadau

Terfynau amser a digwyddiadau blaenorol

1 Hydref 2020 - Preliminary Meeting part 1

Caeedig

Preliminary Meeting part 1

20 Hydref 2020 - Preliminary Meeting part 2

Caeedig

Preliminary Meeting part 2

21 Hydref 2020 - Open Floor Hearing 1

Caeedig

Open Floor Hearing 1

21 Hydref 2020 - Start of Examination

Caeedig

Examination Begins

3 Tachwedd 2020 - Deadline (D1)

Caeedig

Deadline 1 (D1)

Deadline for receipt by the ExA of:

• Responses to Written Questions, issued on 20 July 2020 [PD-010] • Comments on Applicant’s change application of 29 May 2020 [AS-004], accepted on 20 July 2020 [PD-005] • Comments on Additional Documents submitted by the Applicant and other parties since the application was accepted [AS-001] to [AS-059] • Comments on Relevant Representations (RRs) • Summaries of all RRs exceeding 1500 words • Written Representations (WRs) • Summaries of all WRs exceeding 1500 words • Applicant’s submission of Integrity matrices as to effects on European sites • Post Hearing submissions including written summaries following PM and OFH1 • Interested Party comments on Applicant’s suggested ASI itinerary • Local Impact Reports (LIRs) (Annex B) • Statements of Common Ground (SoCG) requested by the ExA (Annex B) • Responses to any further information requested by the ExA for this deadline

3 Tachwedd 2020 - Procedural Deadline C

Caeedig

Procedural Deadline C

Deadline for receipt by the ExA of:

• Notification by Statutory Parties of their wish to be considered as an IP by the ExA • Notification of wish to speak at an Open Floor Hearing (OFH2) • Notification of wish to make oral representations at an Issue Specific Hearings (ISH) together with indication of specific topics that the party wishes the ExA to discuss • Notification of wish to speak at a Compulsory Acquisition Hearing (CAHs) • Notification of wish to have future correspondence received electronically

17 Tachwedd 2020 - Deadline 2 (D2)

Caeedig

Deadline 2 (D2)

Deadline for receipt by the ExA of:

• Comments on responses to the ExA’s Written Questions • Applicant’s first revised draft DCO • Responses to comments on RRs • Comments on any additional information/submissions received by D1 • Responses to any further information requested by the ExA for this deadline including the question relating to publicity

17 Tachwedd 2020 - Procedural Deadline D

Caeedig

Procedural Deadline D

Deadline for receipt by the ExA of:

• Confirmation as to wish to participate or observe at Hearings scheduled for December 2020 • Notification of wish to attend, or part attend, an ASI should this be possible

24 Tachwedd 2020 - Deadline 3 (D3)

Caeedig

Deadline 3 (D3)

Deadline for receipt by the ExA of:

• Comments on WRs • Comments on SoCGs • Comments on LIRs • Comments on Applicant’s first revised draft DCO • Comments on Integrity matrices as to effects on European sites • Submission by the Applicant of low resolution documents (see Annex F) • Comments on any additional information/submissions received by D2 • Responses to any further information requested by the ExA for this deadline

1 Rhagfyr 2020 - Deadline 3A (D3A)

Caeedig

Deadline 3A (D3A)

Deadline for the receipt by the ExA of:

• Comments on the Changes accepted on 29 October 2020

4 Rhagfyr 2020 - Issue by the ExA of

Caeedig

Issue by the ExA of Further Written Questions (if necessary)

8 Rhagfyr 2020 - Hearings

Caeedig

Dates reserved for:

• Open Floor Hearing (OFH2) (if required) • Issue Specific Hearings (ISH 1 to 3) (if required)

Possible topics: o Air Quality o Biodiversity o Cultural Heritage o Green Belt o Geology and Soils o Landscape and visual o Noise and Vibration o Socio-Economics o Traffic and Transport o Water issues o Draft DCO

• Compulsory Acquisition Hearing (CAH1) (if required)

Tuesday 8 - Thursday 10 December 2020

15 Rhagfyr 2020 - Hearing Reserve Dates

Caeedig

Dates reserved for hearings (if necessary due to overrun or technical issues) Tuesday 15 - Thursday 17 December 2020

18 Rhagfyr 2020 - Procedural Deadline EA

Caeedig

Procedural Deadline EA

• Confirmation as to wish to participate or observe at Hearings scheduled for January 2021 (should they take place)

8 Ionawr 2021 - Deadline 4

Caeedig

Deadline 4 (D4)

Deadline for receipt by the ExA of:

• Post December 2020 Hearing submissions including written submissions of oral case • Any revised/updated SoCG • Responses to the ExA’s Further Written Questions (if issued) • Applicant’s revised draft DCO (if required) • Comments on any additional information/submissions received by D3 and D3A • Responses to any further information requested by the ExA for this deadline

18 Ionawr 2021 - Publication of ExA's Site Inspection Timetable

Caeedig

Publication of ExA’s Site Inspection Timetable for Site Inspections identified for 9 and 10 February 2021

20 Ionawr 2021 - Deadline 5 (D5)

Caeedig

Deadline 5 (D5)

Deadline for receipt by the ExA of:

• Comments on any revised/updated SoCG (if any) • Comments on Applicant’s revised draft DCO (if any) • Comments on responses to ExA’s further written questions (if issued) • Comments on any additional information/submissions received by D4 • Responses to any further information requested by the ExA for this deadline

27 Ionawr 2021 - Deadline 5A

Caeedig

Deadline 5A - Deadline for receipt by the ExA of comments on the suitability of virtual site inspection methods and necessary lead-in

29 Ionawr 2021 - Publication of ExA's Third Set of Written Questions (if required)

Caeedig

Publication of the ExA’s Third set of Written Questions (if required)

12 Chwefror 2021 - Deadline 6

Caeedig

Deadline 6 (D6)

Deadline for receipt by the ExA of:

• Responses to the ExA’s Third set of Written Questions (if required) • Comments on any additional information/submissions received by D5 • Responses to any further information requested by the ExA for this deadline

26 Chwefror 2021 - Publication of the RIES and ExA's proposed schedule of changes to the draft DCO (if required)

Caeedig

Publication of: • Report on the Implications for European Sites (RIES) (if required) • The ExA’s proposed schedule of changes to the draft DCO (if required)

12 Mawrth 2021 - Deadline 6A

Caeedig

Deadline 6A - Submission by the Applicant of the 360° photography and video footage requested by the ExA on 29 January 2021.

16 Mawrth 2021 - Site Inspection

Caeedig

The Examining Authority's Site Inspection

Tuesday 16 and Wednesday 17 March 2021

26 Mawrth 2021 - Deadline 7 (D7)

Caeedig

Deadline 7 (D7)

Deadline for receipt by the ExA of:

• Comments on responses to the ExA’s further Written Questions (if required) • Comments on the RIES (if issued) • Comments on the ExA’s proposed schedule of changes to the draft DCO (if issued) • Comments on any additional information/ submissions received by D6 •Comments on the 360° photography and video footage received by D6A • Responses to any further information requested by the ExA for this deadline

7 Ebrill 2021 - Deadline 8 (D8)

Caeedig

Deadline 8 (D8)

Deadline for receipt by the ExA of:

• Responses to comments on the RIES (if issued) Responses to comments on the ExA’s proposed schedule of changes to the draft DCO (if issued) • Final DCO to be submitted by the Applicant in the SI template with the SI template validation report (MS Word) • Final updated Book of Reference • Final SoCGs • Final Statement of Commonality of SoCG • Final Compulsory Acquisition Schedule • Final updated Guide to the Application • Comments on any additional information/ submissions received by D7 • Responses to any further information requested by the ExA for this deadline

16 Ebrill 2021 - Deadline 9 (D9)

Caeedig

Deadline 9 (D9)

Deadline for receipt by the ExA of: • Comments on any additional information/submissions received • Responses to any further information requested by the ExA for this deadline • Statements of Final Position in respect of matters examined

21 Ebrill 2021 - Deadline for close of the Examination

Caeedig

The ExA is under a duty to complete the Examination of the application by the end of the period of 6 months beginning with the day after the close of the Preliminary Meeting.