Nid oes unrhyw derfynau amser neu ddigwyddiadau
Amserlen yr archwiliad
Mae amserlen yr archwiliad yn dangos dyddiadau digwyddiadau a therfynau amser ar gyfer cyflwyniadau.
Os ydych wedi cofrestru i leisio'ch barn, gallwch wneud hyn yn ystod y cam archwilio.
Y cam archwilio
Agorodd yr archwiliad ar 12 January 2023
Caeodd yr archwiliad ar 12 July 2023
3 Ionawr 2023 - Procedural Deadline A
CaeedigProcedural Deadline A
Deadline for receipt by the Examining Authority of:
- Written submissions on the Examination Procedure, including any submissions about the use of virtual methods
- Requests to be heard orally at the Preliminary Meeting and the Open Floor Hearings
- Suggested locations for site inspections (Accompanied or Unaccompanied), including justifications
- The Applicant’s responses to as many of the Relevant Representations as practical
12 Ionawr 2023 - Preliminary Meeting (PM)
CaeedigPreliminary Meeting (PM)
12 Ionawr 2023 - Open Floor Hearing 1 (OFH1)
CaeedigOpen Floor Hearing 1 (OFH1)(if requested)
12 Ionawr 2023 - Open Floor Hearing 2 (OFH2)
CaeedigOpen Floor Hearing 2 (OFH2)(if requested)
20 Ionawr 2023 - Issue by the ExA of the Examination Timetable
CaeedigIssue by the ExA of:
- Examination Timetable
Publication of:
- The ExA’s Written Questions (ExQ1)
30 Ionawr 2023 - Deadline 1
CaeedigDeadline 1
For receipt by the ExA of documents from the Applicant only:
- Applicant’s draft itinerary for ASI
- Application Document Tracker
- Status of negotiations CA schedule
- Status of negotiations with Statutory Undertakers
- Additional plans requested by the ExA
- Response to submissions made by IPs at OFHs
For receipt by the ExA of:
- Comments on Relevant Representations (RR)
- Summaries of all RR exceeding 1500 words
- Requests by Interested Parties to be heard at an Open Floor Hearing (OFH)
- Written submissions of oral representations made at OFHs
- Notification of wish to be an IP from Statutory Parties or Local Authorities
- Comments on any submissions accepted by the ExA prior to the Preliminary Meeting
- Requests by Interested Parties to be heard at a subsequent Open Floor Hearing (OFH)
- Requests to be heard at a CAH Requests by Affected Persons (defined in section 59(4) of the Planning Act 2008) to be heard at a Compulsory Acquisition Hearing (CAH)
- Any further information requested by ExA Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010
- Comments on any further information/submissions accepted by the ExA
13 Chwefror 2023 - Deadline 2
CaeedigDeadline 2 For receipt by the ExA of documents from the Applicant only:
- Draft Statements of Common Ground (SoCG)
- Statement of Commonality
For receipt by the ExA of:
- Written Representations (WR) and summaries
- Responses to ExQ1
- Local Impact Report (LIR)
- Comments on the Applicant’s draft itinerary for the ASI
- Any further information requested by ExA Any further information requested by the ExA under Rule 17 of the Examination Rules
- Comments on any further information received Comments on any further information requested by the ExA and received by Deadline 1
20 Chwefror 2023 - Publication by the ExA of final itinerary for the ASI
CaeedigPublication by the ExA of:
- ExA’s final itinerary for the ASI
28 Chwefror 2023 - Issue Specific Hearing (ISH1) (Part1)
CaeedigIssue Specific Hearing (ISH1)(Part 1) on Environmental Matters
1 Mawrth 2023 - Issue Specific Hearing (ISH1) (Part 2)
CaeedigIssue Specific Hearing (ISH1) (Part 2) on Environmental Matters
1 Mawrth 2023 - Issue Specific Hearing (ISH2)
CaeedigIssue Specific Hearing (ISH2) on the Draft Development Consent Order (dDCO)
1 Mawrth 2023 - Compulsory Acquisition Hearing (CAH1)
CaeedigCompulsory Acquisition Hearing (CAH1)
2 Mawrth 2023 - Accompanied Site Inspection (ASI)
CaeedigAccompanied Site Inspection (ASI)
9 Mawrth 2023 - Deadline 3
CaeedigDeadline 3 For receipt by the ExA of:
- Written submissions of oral representations made at Hearings
- Comments on WR
- Comments on LIR
- Comments on draft SoCG & statement of commonality
- Comments on responses to ExQ1
- Any further information requested by ExA
- Comments on any further information received by the previous deadline
20 Mawrth 2023 - Publication by the ExA of Second Written Questions (ExQ2)
CaeedigPublication by the ExA of:
- ExA’s Second Written Questions (ExQ2) (if required)
27 Mawrth 2023 - Publication by the ExA of the Rule 13 Letter
CaeedigPublication by the ExA of:
- the Rule 13 Letter - Notification of Hearings
11 Ebrill 2023 - Deadline 4
CaeedigDeadline 4 For receipt by the ExA of documents from the Applicant only:
- Draft SoCG
- Updated Statement of Commonality
- Updated Application Document Tracker
- Updated BoR and schedule of changes to BoR
- Updated Status of negotiations CA schedule
- Updated status of negotiations with Statutory Undertakers
For receipt by the ExA of:
- Responses to ExQ2 (if required)
- Any further information requested by ExA
- Comments on any further information received
26 Ebrill 2023 - Issue Specific Hearing (ISH3)
CaeedigIssue Specific Hearing (ISH3) on Environmental matters
27 Ebrill 2023 - Issue Specific Hearing (ISH4)
CaeedigIssue Specific Hearing (ISH4) on the draft Development Consent Order
27 Ebrill 2023 - Compulsory Acquisition Hearing (CAH2)
CaeedigCompulsory Acquisition Hearing (CAH2)
10 Mai 2023 - Deadline 5
CaeedigDeadline 5
For receipt by the ExA of:
- Written submissions of oral representations made at Hearings
- Comments on draft SoCG and Statement of Commonality
- Comments on responses to ExQ2
- Any further information requested by ExA
- Comments on any further information received
22 Mai 2023 - Publication by the ExA of
CaeedigPublication by the ExA of:
- ExA’s Third Written Questions (ExQ3) (if required)
- ExA’s commentary on, or schedule of changes to, the dDCO
12 Mehefin 2023 - Deadline 6
CaeedigDeadline 6 For receipt by the ExA of documents from the Applicant only:
- Draft SoCG
- Updated Statement of Commonality
- Updated Application Document Tracker
- Updated BoR and schedule of changes to BoR
- Updated Status of negotiations CA schedule
- Updated status of negotiations with Statutory Undertakers
For receipt by the ExA of:
- Responses to ExQ3
- Comments on the dDCO
- Comments on the RIES
- Any further information requested by ExA
- Comments on any further information received
27 Mehefin 2023 - Issue Specific Hearing (ISH5)
CaeedigIssue Specific Hearing (ISH5) on the Draft Development Consent Order and Environmental Matters
27 Mehefin 2023 - Compulsory Acquisition Hearing (CAH3)
CaeedigCompulsory Acquisition Hearing (CAH3)
3 Gorffennaf 2023 - Deadline 7
CaeedigDeadline 7
For receipt by the ExA of documents from the Applicant only:
- Closing submissions
- Final DCO to be submitted by the Applicant in the SI template with the SI template validation report
- Final updated BoR and schedule of changes to BoR
- Final SoCG
- Final Statement of Commonality of SoCG
- List of matters not agreed where SoCG could not be finalised
- Final Application Document Tracker
- Final Status of Negotiations CA Schedule
- Final Status of Negotiations with Statutory Undertakers
For receipt by the ExA of:
- Written submissions of oral representations made at Hearings
- Comments on draft SoCG & statement of commonality
- Comments on responses to ExQ3
- Any further information requested by ExA
- Comments on any further information requested by the ExA and received by the previous deadline
12 Gorffennaf 2023 - Deadline 8
CaeedigDeadline 8
For receipt by the ExA of:
- Any further information requested by ExA
- Comments on any further information received by the previous deadline