Amserlen yr archwiliad
Mae amserlen yr archwiliad yn dangos dyddiadau digwyddiadau a therfynau amser ar gyfer cyflwyniadau.
Os ydych wedi cofrestru i leisio'ch barn, gallwch wneud hyn yn ystod y cam archwilio.
Y cam archwilio
Agorodd yr archwiliad ar 22 March 2012
Caeodd yr archwiliad ar 21 September 2012
21 Mawrth 2012 - Deadline 1
Caeedig-Preliminary meeting held at the Sedgemoor Auction Centre, North Petherton. -Start of examination. -Request by District Councils to extend the deadline to complete the examination. -Request made by the Applicant for the Panel to consider amendments to the application.
21 Mawrth 2012 - Preliminary Meeting
CaeedigThe purpose of the preliminary meeting is to enable views to be expressed about matters set out in the rule 6 letter, and in particular to hear representations about the way in which the application is to be examined.
23 Mawrth 2012 - Deadline 2
CaeedigPanel make a request for further information under Rule 17 to SDC and WSC in respect of their request for the Chair of the IPC to extend the deadline to complete the examination.
27 Mawrth 2012 - Deadline 3
CaeedigProcedural decision issued (Rule 8 of the Infrastructure Planning (Examination Procedure) Rules 2010 and the Panel’s first written questions.
30 Mawrth 2012 - Deadline 4
Caeedig-Chair of the IPC writes to SDC and WSC to inform them of his decision not to extend the deadline for completing the examination. -Applicant submits proposed changes to the application, addenda, errata and additional information.
1 Ebrill 2012 - Deadline 5
CaeedigFunctions of the IPC are transferred to the Planning Inspectorate (National Infrastructure Directorate) as a result of the amendments to the Planning Act 2008 made by the Localism Act 2011.
4 Ebrill 2012 - Deadline 6
CaeedigRequest for further information made by the Panel under Rule 17 to WSC for a copy of the Preliminary Works Planning Permission, including conditions and any related s106 Planning Agreement.
11 Ebrill 2012 - Deadline 7
Caeedig-Michael Hurley appointed to the Panel by the Secretary of State. -Accompanied (familiarisation) site inspections by the Panel to the main site.
11 Ebrill 2012 - Site Visit (Accompanied) 1
CaeedigInitial (familiarisation) site inspections
12 Ebrill 2012 - Deadline 8
CaeedigAccompanied (familiarisation) site inspections by the Panel to the associated development sites.
12 Ebrill 2012 - Site Visit (Accompanied) 2
CaeedigInitial (familiarisation) site inspections
24 Ebrill 2012 - Deadline 9
Caeedig-Deadline for responses to the Panel’s first written questions.
-Panel issues a procedural decision informing interested parties that they intend to accept the proposed changes to the application, addenda, errata and additional information submitted by the Applicant.
-Panel issues a correction to the procedural decision issued on 27 March.
30 Ebrill 2012 - Deadline 10
CaeedigRule 17 request to SDC for a copy of the planning permissions granted by Sedgemoor District Council and any related s106 Planning Agreements in respect of:
North East Bridgwater, former Innovia/British Cellophane site.
The Steart Peninsula Project.
3 Mai 2012 - Deadline 11
CaeedigDeadline for receipt of: -Local Impact Reports -Statements of Common Ground -Written Representations.
9 Mai 2012 - Deadline 12
CaeedigFirst open-floor hearing held at Bridgwater College Cannington Campus, Cannington.
9 Mai 2012 - Open Floor Hearing 1
CaeedigFirst open floor hearings
10 Mai 2012 - Deadline 13
CaeedigSecond open-floor hearing at Otterhampton Village Hall, Combwich.
10 Mai 2012 - Open Floor Hearing 2
CaeedigFirst open floor hearings
16 Mai 2012 - Deadline 14
CaeedigThird open-floor hearing at Bridgwater Town Hall, Bridgwater.
16 Mai 2012 - Open Floor Hearing 3
CaeedigFirst open floor hearings
17 Mai 2012 - Deadline 15
CaeedigFourth open-floor hearing at Victory Hall, Stogursey.
17 Mai 2012 - Open Floor Hearing 4
CaeedigFirst open floor hearings
18 Mai 2012 - Deadline 16
CaeedigRule 17 request to Applicant to provide answers to questions about Compulsory Acquisition, draft DCO Article 33A and draft Article 33B.
31 Mai 2012 - Deadline 17
CaeedigDeadline for comments on:
- Local Impact Reports
- Relevant Representations
- Written Representations
- Responses to Panel’s first questions.
8 Mehefin 2012 - Deadline 18
CaeedigPanel issue a procedural decision inviting interested parties to comment on the following documents: -Revised joint Councils’ Local Impact Report -Updated draft DCO (including requirements), the Mitigation Route Map and Code of Construction Practice -Applicant’s response to Panel’s letter dated 18 May 2012 in which the Panel asked several questions relating to compulsory acquisition and other matters.
14 Mehefin 2012 - Deadline 19
CaeedigPanel issues further written questions to interested parties.
26 Mehefin 2012 - Deadline 20
CaeedigFirst issue-specific hearing on the DCO and mitigation measures (as secured by requirements/s106 etc) at The Exchange, Express Park, Bridgwater.
26 Mehefin 2012 - Issue Specific Hearing 1
CaeedigFirst issue-specific (IS) hearing on the DCO and mitigation measures (as secured by requirements/s106 etc)
9 Gorffennaf 2012 - Deadline 21
CaeedigDeadline for receipt of:
-Responses to Panel’s further written questions from interested parties.
Requests by interested parties for further open-floor hearings.
Requests by Affected Persons for a compulsory acquisition hearing.
16 Gorffennaf 2012 - Deadline 22
CaeedigNotification by the Panel of dates for additional issue-specific hearings.
17 Gorffennaf 2012 - Deadline 23
CaeedigSecond issue-specific hearing on the DCO and mitigation measures (as secured by requirements/s106 etc) at The Exchange, Express Park, Bridgwater.
17 Gorffennaf 2012 - Issue Specific Hearing 2
CaeedigSecond IS hearing on the DCO and mitigation measures (as secured by requirements/s106 etc)
23 Gorffennaf 2012 - Deadline 24
CaeedigPanel issue a procedural decision setting out a timetable for the submission and finalisation of a s106 Planning Obligation.
26 Gorffennaf 2012 - Deadline 25
CaeedigPanel issue a request for further information, asking for comments from interested parties by 17 August on various MMO documents and on the Report on the Implications for European Sites (RIES) compiled by the Planning Inspectorate secretariat. Interested parties were also notified of an open-floor hearing to be held on 6 September.
6 Awst 2012 - Deadline 26
CaeedigDeadline for comments on responses to Panel’s further written questions from interested parties.
14 Awst 2012 - Deadline 27
CaeedigThird issue-specific hearing on the DCO and mitigation measures (as secured by requirements/s106 etc) at Bridgwater and Albion Rugby Club, Bridgwater.
14 Awst 2012 - Issue Specific Hearing 3
CaeedigDCO
21 Awst 2012 - Deadline 28
Caeedig-Issue-specific hearing on socio-economic matters at Bridgwater and Albion Rugby Club, Bridgwater.
-Interested parties notified about a forthcoming opportunity to comment on the Final Form Development Consent Order (DCO) and signed Planning Obligation.
-Interested parties notified of the date, time and departure point of the accompanied site inspection on 12 September.
-Deadline for the Applicant to provide a consolidated final form obligation with technical revisions.
21 Awst 2012 - Issue Specific Hearing 4
CaeedigSocio-economic factors
22 Awst 2012 - Deadline 29
CaeedigIssue-specific hearing on transport and transportation matters at Bridgwater and Albion Rugby Club, Bridgwater.
22 Awst 2012 - Issue Specific Hearing 5
CaeedigTraffic and Transportation
23 Awst 2012 - Deadline 30
CaeedigIssue-specific hearing on Habitats Regulations Assessment (HRA) matters and ecology at Bridgwater and Albion Rugby Club, Bridgwater.
23 Awst 2012 - Issue Specific Hearing 6
CaeedigHRA matters and Ecology
24 Awst 2012 - Deadline 31
CaeedigIssue-specific hearing on Combwich at Bridgwater and Albion Rugby Club, Bridgwater.
24 Awst 2012 - Issue Specific Hearing 7
CaeedigCombwich
29 Awst 2012 - Deadline 32
CaeedigCompulsory acquisition hearing at The Exchange, Express Park, Bridgwater.
29 Awst 2012 - Compulsory Acquisition Hearing
Caeedig2 days
30 Awst 2012 - Deadline 33
CaeedigRule 17 request to Applicant to respond to questions about the temporary jetty.
31 Awst 2012 - Deadline 34
CaeedigProcedural decision issued by the Panel inviting interested parties to comment on:
the Final Form DCO (as proposed by the Applicant).
Planning Agreement (engrossed version), annexes and plans.
Response by the Applicant to issues raised at the issue-specific hearings 21 to 24 August.
3 Medi 2012 - Deadline 35
CaeedigRule 17 request to Applicant to respond to questions about Article 45 of the draft DCO.
6 Medi 2012 - Deadline 36
CaeedigFifth open-floor hearing at The Exchange, Express Park, Bridgwater.
6 Medi 2012 - Open Floor Hearing 5
CaeedigFinal Open Floor Hearing
7 Medi 2012 - Deadline 37
CaeedigDeadline for the receipt of comments from interested parties to the Final Form DCO and Planning Agreement (engrossed version).
10 Medi 2012 - Deadline 38
CaeedigRule 17 request to WSC, SCC, Stogursey Parish Council, Fairfield Estate, the MMO, the EA and NE inviting them to comment on the Applicant’s responses to the Rule 17 requests made on 30 August and 3 September.
12 Medi 2012 - Deadline 39
CaeedigAccompanied site inspection by the Panel.
Rule 17 request to Applicant to provide a copy of the Combined Heat and Power Study, referred to in the Sustainability Statement.
12 Medi 2012 - Site Visit (Accompanied) 3
CaeedigDetails of site visit
12 Medi 2012 - Site Visit (Accompanied) 4
Caeedigtwo day site visit
14 Medi 2012 - Deadline 40
CaeedigDeadline for the Applicant to respond to the comments from interested parties on the final form DCO and Planning Agreement (engrossed version).
Rule 17 request to the Applicant, the EA and NE in relation to Article 33(c) of the draft DCO.
21 Medi 2012 - Deadline 41
CaeedigNotification from the Panel to interested parties of the completion of the examination (Planning Act 2008,s99).