Examination timetable
The examination timetable shows the dates of events and deadlines for submissions.
If you have registered to have your say, you can do this in the examination stage.
The examination stage
The examination opened on 18 January 2011
The examination closed on 15 July 2011
17 January 2011 - Deadline 1
ClosedPreliminary Meeting
17 January 2011 - Preliminary Meeting
ClosedPreliminary Meeting
21 January 2011 - Deadline 2
ClosedNotice of procedural decision including confirmation of the examination timetable and first round of written questions from the Examining authority (ExA)
4 February 2011 - Deadline 3
ClosedAccompanied site visit to the Rookery South pit
28 February 2011 - Deadline 4
ClosedDeadline for receipt of:
•Written representations •Responses to written questions •Local impact report(s) •Statements of common ground
28 March 2011 - Deadline 5
ClosedDeadline for comments on:
•Relevant and written representations •Responses to the ExA’s questions •Local Impact Report(s)
11 April 2011 - Deadline 6
ClosedExA issued its second round of written questions
9 May 2011 - Deadline 7
ClosedDeadline for responses to the ExA’s second round of written questions
13 May 2011 - Deadline 8
ClosedIssue specific hearing to consider the drafting aspects of the draft Development Consent Order and requirements, and the proposed agreement between the applicant and local planning authorities under s106 of the Town and Country Planning Act 1990
13 May 2011 - Deadline 9
ClosedExA notification of the programme for further issue specific hearings
26 May 2011 - Deadline 10
ClosedLetter from ExA setting out further details of the issue specific hearings including areas for discussion and parties asked to attend
6 June 2011 - Deadline 11
ClosedDeadline for the receipt of comments on responses to the ExA’s second round of written questions
6 June 2011 - Deadline 12
ClosedDeadline for i) interested parties to notify the ExA of their intention to be heard at an open floor hearing and ii) affected persons to notify the ExA of their wish to be heard at a compulsory acquisition hearing
7 June 2011 - Deadline 13
ClosedLetter from the ExA confirming dates and arrangements for the open floor hearing
7 June 2011 - Deadline 14
ClosedLetter from ExA confirming dates and arrangements for the compulsory acquisition hearing
7 June 2011 - Deadline 15
ClosedLetter (Rule 1754) from ExA to the Applicant requesting further information regarding parent company guarantee and Statement of Reasons
13 June 2011 - Deadline 16
ClosedIssues specific hearing on drafting of DCO and requirements and proposed s106 agreement
17 June 2011 - Deadline 17
ClosedLetter (Rule 17) from ExA confirming their request (made at the issue specific hearing on 13 June) for a final version of the draft DCO and a completed s106 Agreement by 8 July 2011, together with statements from the Councils and 25TPCs setting out any parts of the DCO and requirements with which they disagree
17 June 2011 - Deadline 18
ClosedIssue specific hearing on the effect of the proposed development on the waste hierarchy (am)
17 June 2011 - Deadline 19
ClosedIssue specific hearing on the noise impact of early morning operations on the living conditions of residents (including campers at the Stewartby Water Sports Club) living near to the access routes proposed for HGVs between the A421 and the site (pm)
21 June 2011 - Deadline 20
ClosedIssue specific hearing on landscape, visual impact and design matters, including specifically whether the viewpoints considered in the Environmental Statement are representative and the identification of any additional viewpoints that interested parties want the ExA to include in their site visit
22 June 2011 - Deadline 21
ClosedIssue specific hearing on the impact of the development on the setting of the heritage assets.
23 June 2011 - Deadline 22
ClosedLetter (Rule 17) from ExA inviting written representations in relation to the finalised NPSs (deadline of 6 July 2011).
27 June 2011 - Deadline 23
ClosedCompulsory acquisition hearing (four sessions held on the 27, 28, 29 June and 1 July)
5 July 2011 - Deadline 24
ClosedOpen floor hearing (four sessions held over two days)
6 July 2011 - Deadline 25
ClosedOpen floor hearing (four sessions held over two days)
8 July 2011 - Deadline 26
ClosedLetter (Rule 17) from ExA inviting comments received in response to the ExA’s previous letter of 23 June (deadline of 14 July 2011)
8 July 2011 - Deadline 27
ClosedDeadline for the submission of the final draft of the DCO and proposed s106 agreement
12 July 2011 - Deadline 28
ClosedAccompanied site visit to the application site and surrounding area.
15 July 2011 - Deadline 29
ClosedNotification from the ExA of the completion of the examination.