Rookery South Energy from Waste Generating Station Examination timetable

The examination timetable shows the dates of events and deadlines for submissions.

If you have registered to have your say, you can do this in the examination stage.

The examination stage

The examination opened on 18 January 2011

The examination closed on 15 July 2011

Upcoming deadlines and events

There are no deadlines and events

Past deadlines and events

17 January 2011 - Deadline 1

Closed

Preliminary Meeting

17 January 2011 - Preliminary Meeting

Closed

Preliminary Meeting

21 January 2011 - Deadline 2

Closed

Notice of procedural decision including confirmation of the examination timetable and first round of written questions from the Examining authority (ExA)

4 February 2011 - Deadline 3

Closed

Accompanied site visit to the Rookery South pit

28 February 2011 - Deadline 4

Closed

Deadline for receipt of:

•Written representations •Responses to written questions •Local impact report(s) •Statements of common ground

28 March 2011 - Deadline 5

Closed

Deadline for comments on:

•Relevant and written representations •Responses to the ExA’s questions •Local Impact Report(s)

11 April 2011 - Deadline 6

Closed

ExA issued its second round of written questions

9 May 2011 - Deadline 7

Closed

Deadline for responses to the ExA’s second round of written questions

13 May 2011 - Deadline 8

Closed

Issue specific hearing to consider the drafting aspects of the draft Development Consent Order and requirements, and the proposed agreement between the applicant and local planning authorities under s106 of the Town and Country Planning Act 1990

13 May 2011 - Deadline 9

Closed

ExA notification of the programme for further issue specific hearings

26 May 2011 - Deadline 10

Closed

Letter from ExA setting out further details of the issue specific hearings including areas for discussion and parties asked to attend

6 June 2011 - Deadline 11

Closed

Deadline for the receipt of comments on responses to the ExA’s second round of written questions

6 June 2011 - Deadline 12

Closed

Deadline for i) interested parties to notify the ExA of their intention to be heard at an open floor hearing and ii) affected persons to notify the ExA of their wish to be heard at a compulsory acquisition hearing

7 June 2011 - Deadline 13

Closed

Letter from the ExA confirming dates and arrangements for the open floor hearing

7 June 2011 - Deadline 14

Closed

Letter from ExA confirming dates and arrangements for the compulsory acquisition hearing

7 June 2011 - Deadline 15

Closed

Letter (Rule 1754) from ExA to the Applicant requesting further information regarding parent company guarantee and Statement of Reasons

13 June 2011 - Deadline 16

Closed

Issues specific hearing on drafting of DCO and requirements and proposed s106 agreement

17 June 2011 - Deadline 17

Closed

Letter (Rule 17) from ExA confirming their request (made at the issue specific hearing on 13 June) for a final version of the draft DCO and a completed s106 Agreement by 8 July 2011, together with statements from the Councils and 25TPCs setting out any parts of the DCO and requirements with which they disagree

17 June 2011 - Deadline 18

Closed

Issue specific hearing on the effect of the proposed development on the waste hierarchy (am)

17 June 2011 - Deadline 19

Closed

Issue specific hearing on the noise impact of early morning operations on the living conditions of residents (including campers at the Stewartby Water Sports Club) living near to the access routes proposed for HGVs between the A421 and the site (pm)

21 June 2011 - Deadline 20

Closed

Issue specific hearing on landscape, visual impact and design matters, including specifically whether the viewpoints considered in the Environmental Statement are representative and the identification of any additional viewpoints that interested parties want the ExA to include in their site visit

22 June 2011 - Deadline 21

Closed

Issue specific hearing on the impact of the development on the setting of the heritage assets.

23 June 2011 - Deadline 22

Closed

Letter (Rule 17) from ExA inviting written representations in relation to the finalised NPSs (deadline of 6 July 2011).

27 June 2011 - Deadline 23

Closed

Compulsory acquisition hearing (four sessions held on the 27, 28, 29 June and 1 July)

5 July 2011 - Deadline 24

Closed

Open floor hearing (four sessions held over two days)

6 July 2011 - Deadline 25

Closed

Open floor hearing (four sessions held over two days)

8 July 2011 - Deadline 26

Closed

Letter (Rule 17) from ExA inviting comments received in response to the ExA’s previous letter of 23 June (deadline of 14 July 2011)

8 July 2011 - Deadline 27

Closed

Deadline for the submission of the final draft of the DCO and proposed s106 agreement

12 July 2011 - Deadline 28

Closed

Accompanied site visit to the application site and surrounding area.

15 July 2011 - Deadline 29

Closed

Notification from the ExA of the completion of the examination.