Port Blyth New Biomass Plant Amserlen yr archwiliad

Mae amserlen yr archwiliad yn dangos dyddiadau digwyddiadau a therfynau amser ar gyfer cyflwyniadau.

Os ydych wedi cofrestru i leisio'ch barn, gallwch wneud hyn yn ystod y cam archwilio.

Y cam archwilio

Agorodd yr archwiliad ar 2 August 2012

Caeodd yr archwiliad ar 2 February 2013

Terfynau amser a digwyddiadau i ddod

Nid oes unrhyw derfynau amser neu ddigwyddiadau

Terfynau amser a digwyddiadau blaenorol

2 Awst 2012 - Deadline 1

Caeedig

Preliminary Meeting

2 Awst 2012 - Preliminary Meeting

Caeedig

Preliminary meeting at the Civic Centre, Blyth

15 Awst 2012 - Deadline 2

Caeedig

Issuing by the ExA of procedural decision including confirmation of the examination timetable, first written questions under Rule 8 of the Infrastructure Planning (Examination Procedure) Rules 2010 and note of the Preliminary Meeting held on 2 August 2012

29 Awst 2012 - Deadline 3

Caeedig

Date by which Statutory Parties were requested to notify the ExA of their wish to be considered as an interested party

17 Medi 2012 - Deadline 4

Caeedig

Notification by the ExA of Issue Specific Hearing on the draft Development Consent Order including the Deemed Marine Licence on 11 October 2012 under Rule 13 of the Infrastructure Planning (Examination Procedure) Rules 2010

21 Medi 2012 - Deadline 5

Caeedig

Notification by the ExA of procedural decision to vary the examination timetable under Rule 8 (3) of the Infrastructure Planning (Examination Procedure) Rules 2010.

26 Medi 2012 - Deadline 6

Caeedig

Deadline for receipt by the ExA of: •Comments on Relevant Representations •Responses to ExA’s first written questions •Any summaries of Relevant Representations exceeding 1500 words •Written Representations by all interested parties •Any summaries of Written Representations exceeding 1500 words •Local Impact Report from any local authorities •Notification by an Interested Party of their wish to be heard at an Open Floor hearing •Notification by an Affected Person of their wish to be heard at a Compulsory Acquisition hearing •Notification of wish to make oral representations at the Specific Issue Hearingon the draft Development Consent Order including the draft Deemed Marine Licence

11 Hydref 2012 - Deadline 7

Caeedig

Issue Specific Hearing on the draft Development Consent Order including Deemed Marine Licence

11 Hydref 2012 - Issue Specific Hearing 1

Caeedig

Issue Specific Hearing in the draft Development Consent Order and Deemed Marine Licence

24 Hydref 2012 - Deadline 8

Caeedig

Deadline for receipt by the ExA of: •Comments on Written Representations and responses to comments on Relevant Representations •Comments on Local Impact Reports •Comments on responses to ExA’s first written questions •Statements of Common Ground •Notification of wish to cross examine at a Specific Issue or Compulsory Acquisition Hearing

25 Hydref 2012 - Deadline 9

Caeedig

Notice of ExA’s request for further information under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010 inviting comments on Northumberland County Council’s response to the ExA’s first round of questions which was received on 12 October 2012.

25 Hydref 2012 - Deadline 10

Caeedig

Deadline for receipt by the ExA of: •Any written summary of the oral case put at the Specific Issue Hearing held on 11 October 2012

2 Tachwedd 2012 - Deadline 11

Caeedig

Issuing by the ExA of second written questions

6 Tachwedd 2012 - Deadline 12

Caeedig

Notification by the ExA of procedural decision to vary the examination timetable under Rule 8 (3) of the Infrastructure Planning (Examination Procedure) Rules 2010 and notification of a Compulsory Acquisition Hearing under Rule 13 of the Infrastructure Planning (Examination Procedure) Rules 2010

6 Tachwedd 2012 - Deadline 13

Caeedig

Notification by the ExA of procedural decision to vary the examination timetable under Rule 8 (3) of the Infrastructure Planning (Examination Procedure) Rules 2010 and notification of Hearings and Site Visit under Rules 13 and 16 of the Infrastructure Planning (Examination Procedure) Rules 2010

9 Tachwedd 2012 - Deadline 14

Caeedig

Deadline for responses to the ExA’s request for further information on 25 October 2012

30 Tachwedd 2012 - Deadline 15

Caeedig

Deadline for receipt by the ExA of: •Responses to ExA’s second written questions •Notification by Interested Parties of wish to speak at any of the Hearings on 4 or 5 December 2012 •Notification by Affected Persons of wish to speak at Compulsory Acquisition Hearing on 6 December 2012 •Notification by Interested Parties of wish to attend the Accompanied Site Visit on 6 December 2012

4 Rhagfyr 2012 - Deadline 16

Caeedig

Specific Issue Hearing on Landscape, Design and Visual Impact (AM)

4 Rhagfyr 2012 - Deadline 17

Caeedig

Specific Issue Hearing on Access and Transport (PM)

4 Rhagfyr 2012 - Issue Specific Hearing 2

Caeedig

Issue Specific Hearing for Access and Transport

4 Rhagfyr 2012 - Issue Specific Hearing 3

Caeedig

Issue Specific Hearing on Landscape, Design and Visual Impact

5 Rhagfyr 2012 - Deadline 18

Caeedig

Specific Issue Hearing on Safety (AM)

5 Rhagfyr 2012 - Deadline 19

Caeedig

Open Floor Hearing (PM)

5 Rhagfyr 2012 - Deadline 20

Caeedig

Open Floor Hearing (Evening)

5 Rhagfyr 2012 - Issue Specific Hearing 4

Caeedig

Issue Specific Hearing on Safety

5 Rhagfyr 2012 - Open Floor Hearing 1

Caeedig

Open Floor Hearing - afternoon session

5 Rhagfyr 2012 - Open Floor Hearing 2

Caeedig

Open Floor Hearing - evening session

6 Rhagfyr 2012 - Deadline 21

Caeedig

Compulsory Acquisition Hearing (AM)

6 Rhagfyr 2012 - Deadline 22

Caeedig

Accompanied Site Visit (PM)

6 Rhagfyr 2012 - Compulsory Acquisition Hearing

Caeedig

Compulsory Acquisition Hearing

14 Rhagfyr 2012 - Deadline 23

Caeedig

Deadline for receipt by the ExA of: •Any revised proposed schedules or requirements for inclusion within the draft Development Consent Order

17 Rhagfyr 2012 - Deadline 24

Caeedig

Notification by the ExA of Specific Issue Hearing on the draft Development Consent Order and Deemed Marine Licence under Rule 13 of the Infrastructure Planning (Examination Procedure) Rules 2010

17 Rhagfyr 2012 - Deadline 25

Caeedig

Notice of ExA’s request for further information under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010 to Northumberland County Council and North Blyth Energy Limited

20 Rhagfyr 2012 - Deadline 26

Caeedig

Deadline for receipt by the ExA of: •Any written summary of the oral case put at any Specific Issue Hearing held on 3 and 4 December 2012

3 Ionawr 2013 - Deadline 27

Caeedig

ExA’s report on the implications for European Sites published

3 Ionawr 2013 - Deadline 28

Caeedig

Notice of ExA’s request for further information under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010 to all Interested Parties regarding the ExA’s report on the implications for European Sites

4 Ionawr 2013 - Deadline 29

Caeedig

Deadline for receipt by the ExA of: •Any written summary of the oral case put at any Open Floor Hearing on 5 December 2012 or Compulsory Acquisition Hearing on 6 December 2012 •Comments on responses to ExA’s second written questions •Notification by Interested Parties of wish to speak at the Specific Issue Hearing on 9 January 2013

9 Ionawr 2013 - Deadline 30

Caeedig

Specific Issue Hearing on the draft Development Consent Order and Deemed Marine Licence

9 Ionawr 2013 - Deadline 31

Caeedig

ExA appointed as Section 127 Examiner

9 Ionawr 2013 - Issue Specific Hearing 5

Caeedig

Specific Issue Hearing on the draft Development Consent Order (DCO) including the draft Deemed Marine Licence (DML) on 9 January 2013 in the Civic Centre, Blyth.

14 Ionawr 2013 - Deadline 32

Caeedig

Notice of ExA’s request for further information under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010 to The Environment Agency

18 Ionawr 2013 - Deadline 33

Caeedig

Deadline for responses to the ExA’s request for further information on 17 December 2012

25 Ionawr 2013 - Deadline 34

Caeedig

Deadline for response from The Environment Agency to the ExA’s request for further information on 14 January 2013 and from all Interested Parties to the ExA’s request for further information on 3 January 2013

2 Chwefror 2013 - Deadline 35

Caeedig

Examination closed at 23:59