Amserlen yr archwiliad
Mae amserlen yr archwiliad yn dangos dyddiadau digwyddiadau a therfynau amser ar gyfer cyflwyniadau.
Os ydych wedi cofrestru i leisio'ch barn, gallwch wneud hyn yn ystod y cam archwilio.
Y cam archwilio
Agorodd yr archwiliad ar 18 February 2014
Caeodd yr archwiliad ar 18 August 2014
18 Chwefror 2014 - Deadline 1
CaeedigThe Preliminary Meeting
18 Chwefror 2014 - Preliminary Meeting
CaeedigThe preliminary meeting is held in public and concerns procedural matters only. It is not essential to attend the preliminary meeting; interested parties will be sent details of how to take further part in the examination in any event.
25 Chwefror 2014 - Deadline 2
CaeedigIssue by ExA of: Examination timetable and ExA first written questions
4 Mawrth 2014 - Deadline 3
CaeedigDeadline I Deadline for receipt by the ExA of: • Local Impact Report from any local authorities • First version of Statements of Common Ground requested by ExA
18 Mawrth 2014 - Deadline 4
CaeedigDeadline II Deadline for receipt by the ExA of: • Written Representations (WRs) by all interested parties • Comments on Relevant Representations (RRs) • Summaries of all RRs exceeding 1500 words • Summaries of all WRs exceeding 1500 words • Comments on Matrices prepared by the applicant to inform the Report on the implications for European Sites • Comments on consolidated ornithological addendum provided by the applicant • Responses to ExA’s first written questions • Notification of wish to speak at a Compulsory Acquisition hearing • Notification of wish to make oral representations at an issue specific hearing on the draft Development Consent Order (DCO) and Deemed Marine Licence (DML) • Notification of wish to make oral representation at an Issue Specific Hearing • Notification of wish to speak at an open floor hearing • Notification of wish to attend site visit in the company of interested parties and any representations relating to proposed locations to visit
31 Mawrth 2014 - Deadline 5
CaeedigDate reserved for open floor hearing (evening) if required
31 Mawrth 2014 - Open Floor Hearing
CaeedigOpen Floor Hearing
1 Ebrill 2014 - Deadline 6
CaeedigDate for first Issue Specific Hearing – Development Consent Order and Deemed Marine Licence
1 Ebrill 2014 - Issue Specific Hearing 1
CaeedigDevelopment Consent Order and Deemed Marine Licence
2 Ebrill 2014 - Deadline 7
CaeedigDate for first Issue Specific Hearing – Development Consent Order and Deemed Marine Licence
2 Ebrill 2014 - Issue Specific Hearing 2
CaeedigDevelopment Consent Order and Deemed Marine Licence
3 Ebrill 2014 - Deadline 8
CaeedigDate for Accompanied site visit
3 Ebrill 2014 - Site Visit (Accompanied)
CaeedigAccompanied Site Visit
4 Ebrill 2014 - Deadline 9
Caeedig• Date for first Issue Specific Hearing on HRA – methodology and impacts on birds and marine mammals. Also including mitigation measures to avoid, reduce and if possible offset any major adverse transboundary effects
4 Ebrill 2014 - Issue Specific Hearing 3
CaeedigBiodiversity biological environment and ecology and HRA
15 Ebrill 2014 - Deadline 10
CaeedigDeadline III Deadline for receipt by the ExA of: • Comments on WRs • Comments on Responses to ExA’s first written questions • Comments on Local Impact Report • Responses to comments on matrices prepared by the applicant to inform the Report on Implications for European Sites • Responses to comments on the consolidated ornithological addendum In relation to item 6 any written summary of an oral case put at the Open Floor Hearing and any documents/amendments requested Tuesday 15 April 2014 by the ExA • In relation to item 7 any written summary of an oral case put at the Issue Specific Hearings and any documents/amendments requested by the ExA • Draft s106 Agreements
30 Ebrill 2014 - Deadline 11
CaeedigIssue by ExA of: • ExA second written questions
19 Mai 2014 - Deadline 12
CaeedigDeadline IV (2pm) Deadline for receipt by the ExA of: • Responses to ExA’s second written questions
3 Mehefin 2014 - Deadline 13
Caeedig• Date for second Issue Specific Hearing on HRA – methodology and impacts on birds and marine mammals. Also including mitigation measures to avoid, reduce and if possible offset any major adverse transboundary effects
3 Mehefin 2014 - Issue Specific Hearing 4
CaeedigHRA
4 Mehefin 2014 - Deadline 14
Caeedig• Date for second Issue Specific Hearing on HRA – methodology and impacts on birds and marine mammals. Also including mitigation measures to avoid, reduce and if possible offset any major adverse transboundary effects
4 Mehefin 2014 - Issue Specific Hearing 5
CaeedigHRA
5 Mehefin 2014 - Deadline 15
Caeedig• Date for second Issue Specific Hearing – Development Consent Order and Deemed Marine Licence
5 Mehefin 2014 - Issue Specific Hearing 6
CaeedigDCO and DML
6 Mehefin 2014 - Deadline 16
Caeedig• Date for second Issue Specific Hearing – Development Consent Order and Deemed Marine Licence
6 Mehefin 2014 - Issue Specific Hearing 7
CaeedigDCO and DML
16 Mehefin 2014 - Deadline 17
CaeedigDeadline V (2pm) Deadline for receipt by the ExA of: • Comments on responses to ExA’s second written questions • In relation to item 11 any written summary of an oral case put at the HRA Issue Specific Hearing and any documents/amendments requested by the ExA • In relation to item 12 any written summary of an oral case put at the DCO and DML Issue Specific Hearings and any documents/amendments requested by the ExA
23 Mehefin 2014 - Deadline 18
CaeedigDeadline V (A) Submission of applicants revised draft DCO following the issue specific hearing on the DCO and DML in relation to item 13, including one clean and one tracked change copy
1 Gorffennaf 2014 - Deadline 19
CaeedigIssue Specific Hearing on HRA
1 Gorffennaf 2014 - Issue Specific Hearing 8
CaeedigISH on biodiversity, biological environment and ecology, and HRA
2 Gorffennaf 2014 - Deadline 20
CaeedigAccompanied site visit
3 Gorffennaf 2014 - Deadline 21
CaeedigCompulsory Acquisition Hearing
3 Gorffennaf 2014 - Compulsory Acquisition Hearing 1
CaeedigCompulsory Acquisition Hearing
4 Gorffennaf 2014 - Deadline 22
CaeedigCompulsory Acquisition Hearing
4 Gorffennaf 2014 - Compulsory Acquisition Hearing 2
CaeedigCompulsory Acquisition Hearing
7 Gorffennaf 2014 - Deadline 23
CaeedigDeadline VI (2pm) • In relation to item 15 any written summary of an oral case put at the Issue Specific Hearing and any documents/amendments requested by the ExA
- Submission of applicant's final draft DCO
11 Gorffennaf 2014 - Deadline 24
CaeedigDeadline VII • In relation to item 17 any written summary of an oral case put at the compulsory acquisition hearing and any documents/amendments requested by the ExA -Comments on applicant's final draft DCO
14 Gorffennaf 2014 - Deadline 25
CaeedigIssue by the Examining Authority: The Report on the Implications for European Sites, including the Matrices prepared by the ExA to inform Report on the implications for European Sites.
• The ExAs Draft Development ConsentOrder
16 Gorffennaf 2014 - Deadline 26
CaeedigIssue Specific Hearing – Development Consent Order and Deemed Marine Licence
16 Gorffennaf 2014 - Issue Specific Hearing 9
CaeedigISH into the draft DCO and DMLs
17 Gorffennaf 2014 - Deadline 27
CaeedigIssue Specific Hearing – Development Consent Order and Deemed Marine Licence
24 Gorffennaf 2014 - Deadline 28
CaeedigDeadline VIII (2pm) • In relation to item 21 any written summary of an oral case put at the DCO and DML Issue Specific Hearings and any documents / amendments requested by the ExA •Any final s106 agreement •Any written comments on ExA's draft DCO •Applicant’s response to the ExA’s Rule 17 request of 14 July 2014 • Submission of revised DCO from the applicant following matters discussed at the DCO hearing
30 Gorffennaf 2014 - Deadline 29
CaeedigDeadline VIII(a) (2pm) • Responses to the Examining Authority’s Rule 17 request of 24 July 2014
1 Awst 2014 - Deadline 30
CaeedigDeadline VIII(b) (12 noon) • Responses to the ExA’s Rule 17 request of 29 July 2014
5 Awst 2014 - Deadline 31
CaeedigDeadline IX Any written comments on • The Report on the Implications for European Sites, including the Matrices prepared by the ExA to inform Report on the implications for European Sites •Any written comments on the final s106 agreement •Any further comments on the written comments received to the ExA's draft DCO •Any written comments on Statements of Common Ground and / or representations in writing received in response to Deadline VIII • Comments on the applicant’s response to the ExA’s Rule 17 request of 14 July 2014 • Comments in light of any revised DCO from the applicant • Comments on any responses to the ExA’s Rule 17 request of 24 July 2014 • Comments on any responses to the ExA’s Rule 17 request of 29 July 2014
15 Awst 2014 - Deadline 32
CaeedigDeadline X (12 noon) •Responses to the Examining Authority’s Rule 17 request of 12 August 2014
18 Awst 2014 - Deadline 33
CaeedigDeadline X(a) (11.59pm) •Comments on Responses to the ExA’s Rule 17 request of 12 August 2014
18 Awst 2014 - Deadline 34
CaeedigThe ExA is under a duty to complete the examination of the application by the end of the period of 6 months beginning with the day after the close of the Preliminary Meeting.