The examination stage

The examination opened on 11 September 2014

The examination closed on 11 March 2015

Upcoming deadlines and events

There are no deadlines and events

Past deadlines and events

23 July 2014 - Site Visit (Unaccompanied)

Closed

Unaccompanied site Visits taking place 23, 24 July and 13 and 14 August

11 September 2014 - Preliminary Meeting

Closed

?

6 October 2014 - Deadline 1

Closed

DEADLINE I Deadline for receipt of: • Local Impact Reports • Completed Statements of Common Ground (SoCG) as requested by ExA and any drafts of Statements of Common Ground not completed • Receipt of the technical annexes of Chapter 16 (Shipping and Navigation), Volume B of the Environmental Statement Annex A – Consequences Assessment Report Annex B – Hazard Log Annex C – Navitus Bay MGN Checklist • Receipt of errata to: Sections 12.3.36 to 38 and Table 12.7 of the Environmental Statement, Volume C, Chapter 12 Landscape and Visual. Table 4.3 in Appendix 12.4 of the Environmental Statement.

14 October 2014 - Open Floor Hearing 1

Closed

Open floor hearing (mainland)

20 October 2014 - Deadline 2

Closed

DEADLINE II Deadline for receipt of: • Statements of Common Ground not submitted at deadline I • Comments on relevant representations (RRs) • Summaries of RRs and comments that exceed 1500 words • Written representations (WRs) by all interested parties • Summaries of all WRs exceeding 1500 words • Responses to ExA’s first written questions • Notice of wish to be heard at an open floor hearing (Isle of Wight) • Notice of wish to be heard at an issue-specific hearing • Notice of wish to be heard at a compulsory acquisition hearing • Nominations of additional locations to be inspected by the ExA and the features to be observed there, with reasons for each nomination and whether an accompanied site visit is necessary.

24 October 2014 - Deadline 3

Closed

Issue by ExA of: • Notification of date, time and place for all issue specific and compulsory acquisition hearings including any open floor hearings in the Isle of Wight

5 November 2014 - Deadline 4

Closed

DEADLINE III Deadline for receipt by the ExA of: • Responses to comments on RRs • Comments on written representations • Comments on responses to ExA’s written questions • Comments on Local Impact Reports

10 November 2014 - Deadline 5

Closed

Issue by ExA of: • Notification of date, time and place of accompanied site visits

18 November 2014 - Issue Specific Hearing 1

Closed

Dates reserved for issue-specific hearing

19 November 2014 - Issue Specific Hearing 2

Closed

Dates reserved for issue-specific hearing

20 November 2014 - Issue Specific Hearing 3

Closed

Dates reserved for issue-specific hearing

21 November 2014 - Issue Specific Hearing 4

Closed

Dates reserved for issue-specific hearing

25 November 2014 - Issue Specific Hearing 5

Closed

Dates reserved for issue-specific hearing

26 November 2014 - Issue Specific Hearing 6

Closed

Dates reserved for issue-specific hearing

27 November 2014 - Issue Specific Hearing 7

Closed

Dates reserved for issue-specific hearing

28 November 2014 - Issue Specific Hearing 8

Closed

Dates reserved for issue-specific hearing

2 December 2014 - Site Visit (Accompanied) 1

Closed

Isle Of Wight

2 December 2014 - Open Floor Hearing 2

Closed

Isle of Wight

3 December 2014 - Site Visit (Accompanied) 2

Closed

Accompanied site visit - Mainland

4 December 2014 - Site Visit (Accompanied) 3

Closed

Accompanied site visit - Mainland

11 December 2014 - Deadline 6

Closed

DEADLINE IV Deadline for receipt by the ExA of: • Post hearing documents including any written summary of an oral case put at hearings held on Tuesday 18, Wednesday 19,Thursday 20 and Friday 21 November 2014 and Tuesday 25, Wednesday 26, Thursday 27 and Friday 28 November 2014 and any documents/amendments requested by the ExA From the Applicant, in relation to the mitigation option set out at Appendix 43: • Documents referred to in paragraph 1.5.1 of Appendix 43 • A Statement of all impacts • Details of the consideration and identification as to whether any new (un-assessed) impacts would arise from the proposed option. • Details of the process by which the Appendix 43 option was developed. • A statement to address issues raised by the submissions made in writing and orally with regard to the status of Appendix 43. • A statement on how HRA matters will be dealt with in relation to appendix 43.

7 January 2015 - Deadline 7

Closed

DEADLINE V Deadline for receipt by the ExA of: • Applicant’s revised draft DCO/DMLs taking account of issues raised in hearings and WRs • Submissions on whether the mitigation option set out in Appendix 43 amounts to a material change or whether the change is of such a degree that it constitutes a new project or whether it can still be considered under the existing application. • Responses to documents submitted at deadline IV

14 January 2015 - Deadline 8

Closed

Issue by ExA of: • Possible second written questions if required

21 January 2015 - Issue Specific Hearing 9

Closed

Date reserved for issue-specific hearings relating to : • Development Consent Order and Deemed Marine Licences

22 January 2015 - Compulsory Acquisition Hearing

Closed

Date reserved for compulsory acquisition hearing

22 January 2015 - Issue Specific Hearing 10

Closed

Date reserved for hearing regarding mitigation option put forward in Appendix 43

29 January 2015 - Deadline 9

Closed

DEADLINE VI Deadline for receipt by the ExA of: • Responses to ExA’s second written questions • Post hearing documents including any written summary of an oral case put at hearings held on 21 and 22 January and any documents/amendments requested by the ExA • Comments on the applicant’s revised DCO

5 February 2015 - Deadline 10

Closed

Deadline VIa Deadline for receipt by the Examining Authority of: • Additional representations on the merits of the Turbine Area Mitigation Option

20 February 2015 - Deadline 11

Closed

Publication by ExA of: • A Report on the Implications for European Sites (RIES) taking issues raised and comments into account • Revised draft DCO taking issues raised and comments into account • Any further requests for information

5 March 2015 - Deadline 12

Closed

DEADLINE VII Deadline for receipt by the Examining Authority of: • Comments on ExA’s revised draft DCO • Comments on responses to ExA’s second written questions • Comments on ExA’s RIES • Receipt of further information as requested on 26 February 2015 • Comments on additional representations on the merits of the Turbine Area Mitigation Option

10 March 2015 - Deadline 13

Closed

DEADLINE VIII Deadline for receipt by the ExA of: • Comments on responses to the further information request dated 26 February 2015