East Anglia ONE Offshore Windfarm Amserlen yr archwiliad

Mae amserlen yr archwiliad yn dangos dyddiadau digwyddiadau a therfynau amser ar gyfer cyflwyniadau.

Os ydych wedi cofrestru i leisio'ch barn, gallwch wneud hyn yn ystod y cam archwilio.

Y cam archwilio

Agorodd yr archwiliad ar 25 June 2013

Caeodd yr archwiliad ar 23 December 2013

Terfynau amser a digwyddiadau i ddod

Nid oes unrhyw derfynau amser neu ddigwyddiadau

Terfynau amser a digwyddiadau blaenorol

25 Mehefin 2013 - Preliminary Meeting

Caeedig

Preliminary Meeting in Ipswich

25 Mehefin 2013 - Site Visit (Unaccompanied) 1

Caeedig

Unaccompaied site visit to view the landfall site and other areas

4 Gorffennaf 2013 - Deadline 1

Caeedig

Issue of:

  • Examination timetable
  • Examining Authority’s Questions
  • Requests for Statements of Common Ground
  • Notice of publication of Note of the Preliminary Meeting

9 Gorffennaf 2013 - Deadline 2

Caeedig

Deadline for Statutory Parties to inform the ExA of:

  • A wish to be considered an Interested Party
  • Submission by the applicant of any further information

23 Gorffennaf 2013 - Site Visit (Unaccompanied) 2

Caeedig

Site visit of cable route

24 Gorffennaf 2013 - Site Visit (Unaccompanied) 3

Caeedig

Substation site

30 Gorffennaf 2013 - Deadline 3

Caeedig

INTERESTED PARTIES DEADLINE I for receipt of:

  • Local Impact Reports
  • Written representations
  • Responses to ExA’s written questions
  • Statements of Common Ground
  • Any summaries of Relevant Representations exceeding 1500 words
  • Any summaries of WRs exceeding 1500 words
  • Notification of wish to be heard at an open floor hearing by Interested Parties
  • Notification of wish to make oral representations at the specific issue hearing
  • Notification of wish to attend the ExA’s inspection of the sites to which the application/specific matters relate in the company of Interested Parties
  • Matrices prepared by the applicant to inform the Report on the Implications for European Sites

6 Awst 2013 - Deadline 4

Caeedig

Issue of:

  • Details of date time and place of ExA’s inspection of a site to which the application/specific matters relate in the company of Interested Parties
  • Final notification by ExA of date, time and place for Open Floor and Issue Specific Hearings

27 Awst 2013 - Deadline 5

Caeedig

INTERESTED PARTIES DEADLINE II for the receipt of:

  • Comments on Local Impact Reports
  • Comments on Relevant Representations
  • Comments on Written Representations
  • Comments on responses to ExA’s Questions
  • Comments on Statements of Common Ground
  • Comments on applicant’s matrices to inform the Report on the Implications for European Sites
  • Notification of wish to make oral representations at a Compulsory Acquisition hearing

10 Medi 2013 - Site Visit (Accompanied) 1

Caeedig

Site Inspection in the Company of Interested Parties

11 Medi 2013 - Site Visit (Accompanied) 2

Caeedig

Site Inspection in the Company of Interested Parties

12 Medi 2013 - Open Floor Hearing 1

Caeedig

Reagistration starts at 0930

17 Medi 2013 - Issue Specific Hearing 1

Caeedig

Registration starts at 0930

18 Medi 2013 - Issue Specific Hearing 2

Caeedig

Registration starts at 0930

19 Medi 2013 - Issue Specific Hearing 3

Caeedig

Registration starts at 0930

24 Medi 2013 - Issue Specific Hearing 4

Caeedig

Registration starts at 0930

25 Medi 2013 - Issue Specific Hearing 5

Caeedig

Registration starts at 0930

26 Medi 2013 - Issue Specific Hearing 6

Caeedig

Registration starts at 0930

27 Medi 2013 - Issue Specific Hearing 7

Caeedig

Registration starts at 0930

8 Hydref 2013 - Compulsory Acquisition Hearing 1

Caeedig

Registration at 0930

9 Hydref 2013 - Compulsory Acquisition Hearing 2

Caeedig

Registration at 0930

Outstanding s127 applications if necessary

10 Hydref 2013 - Compulsory Acquisition Hearing 3

Caeedig

Registration at 0930

11 Hydref 2013 - Compulsory Acquisition Hearing 4

Caeedig

Registration at 0930

21 Hydref 2013 - Deadline 6

Caeedig

INTERESTED PARTIES DEADLINE III for receipt of: Post-Hearing documents including any written summary of an oral case put at any Hearing and any documents/amendments requested by the ExA

21 Hydref 2013 - Open Floor Hearing 2

Caeedig

Deadline III

5 Tachwedd 2013 - Deadline 7

Caeedig

Issue of:

  • ExA’s draft Development Consent Order, if any, for consultation
  • Matrices prepared by the ExA to inform Report on the implications for European Sites, for consultation

19 Tachwedd 2013 - Site Visit (Unaccompanied) 4

Caeedig

Site Visit to visit the area at night

26 Tachwedd 2013 - Deadline 8

Caeedig

INTERESTED PARTIES DEADLINE IV for receipt of:

  • Any written comments on the ExA’s draft Development Consent Order.
  • Any written comments on the matrices to inform Report on the Implications for European Sites