Nid oes unrhyw derfynau amser neu ddigwyddiadau
Amserlen yr archwiliad
Mae amserlen yr archwiliad yn dangos dyddiadau digwyddiadau a therfynau amser ar gyfer cyflwyniadau.
Os ydych wedi cofrestru i leisio'ch barn, gallwch wneud hyn yn ystod y cam archwilio.
Y cam archwilio
Agorodd yr archwiliad ar 25 June 2013
Caeodd yr archwiliad ar 23 December 2013
25 Mehefin 2013 - Preliminary Meeting
CaeedigPreliminary Meeting in Ipswich
25 Mehefin 2013 - Site Visit (Unaccompanied) 1
CaeedigUnaccompaied site visit to view the landfall site and other areas
4 Gorffennaf 2013 - Deadline 1
CaeedigIssue of:
- Examination timetable
- Examining Authority’s Questions
- Requests for Statements of Common Ground
- Notice of publication of Note of the Preliminary Meeting
9 Gorffennaf 2013 - Deadline 2
CaeedigDeadline for Statutory Parties to inform the ExA of:
- A wish to be considered an Interested Party
- Submission by the applicant of any further information
23 Gorffennaf 2013 - Site Visit (Unaccompanied) 2
CaeedigSite visit of cable route
24 Gorffennaf 2013 - Site Visit (Unaccompanied) 3
CaeedigSubstation site
30 Gorffennaf 2013 - Deadline 3
CaeedigINTERESTED PARTIES DEADLINE I for receipt of:
- Local Impact Reports
- Written representations
- Responses to ExA’s written questions
- Statements of Common Ground
- Any summaries of Relevant Representations exceeding 1500 words
- Any summaries of WRs exceeding 1500 words
- Notification of wish to be heard at an open floor hearing by Interested Parties
- Notification of wish to make oral representations at the specific issue hearing
- Notification of wish to attend the ExA’s inspection of the sites to which the application/specific matters relate in the company of Interested Parties
- Matrices prepared by the applicant to inform the Report on the Implications for European Sites
6 Awst 2013 - Deadline 4
CaeedigIssue of:
- Details of date time and place of ExA’s inspection of a site to which the application/specific matters relate in the company of Interested Parties
- Final notification by ExA of date, time and place for Open Floor and Issue Specific Hearings
27 Awst 2013 - Deadline 5
CaeedigINTERESTED PARTIES DEADLINE II for the receipt of:
- Comments on Local Impact Reports
- Comments on Relevant Representations
- Comments on Written Representations
- Comments on responses to ExA’s Questions
- Comments on Statements of Common Ground
- Comments on applicant’s matrices to inform the Report on the Implications for European Sites
- Notification of wish to make oral representations at a Compulsory Acquisition hearing
10 Medi 2013 - Site Visit (Accompanied) 1
CaeedigSite Inspection in the Company of Interested Parties
11 Medi 2013 - Site Visit (Accompanied) 2
CaeedigSite Inspection in the Company of Interested Parties
12 Medi 2013 - Open Floor Hearing 1
CaeedigReagistration starts at 0930
17 Medi 2013 - Issue Specific Hearing 1
CaeedigRegistration starts at 0930
18 Medi 2013 - Issue Specific Hearing 2
CaeedigRegistration starts at 0930
19 Medi 2013 - Issue Specific Hearing 3
CaeedigRegistration starts at 0930
24 Medi 2013 - Issue Specific Hearing 4
CaeedigRegistration starts at 0930
25 Medi 2013 - Issue Specific Hearing 5
CaeedigRegistration starts at 0930
26 Medi 2013 - Issue Specific Hearing 6
CaeedigRegistration starts at 0930
27 Medi 2013 - Issue Specific Hearing 7
CaeedigRegistration starts at 0930
8 Hydref 2013 - Compulsory Acquisition Hearing 1
CaeedigRegistration at 0930
9 Hydref 2013 - Compulsory Acquisition Hearing 2
CaeedigRegistration at 0930
Outstanding s127 applications if necessary
10 Hydref 2013 - Compulsory Acquisition Hearing 3
CaeedigRegistration at 0930
11 Hydref 2013 - Compulsory Acquisition Hearing 4
CaeedigRegistration at 0930
21 Hydref 2013 - Deadline 6
CaeedigINTERESTED PARTIES DEADLINE III for receipt of: Post-Hearing documents including any written summary of an oral case put at any Hearing and any documents/amendments requested by the ExA
21 Hydref 2013 - Open Floor Hearing 2
CaeedigDeadline III
5 Tachwedd 2013 - Deadline 7
CaeedigIssue of:
- ExA’s draft Development Consent Order, if any, for consultation
- Matrices prepared by the ExA to inform Report on the implications for European Sites, for consultation
19 Tachwedd 2013 - Site Visit (Unaccompanied) 4
CaeedigSite Visit to visit the area at night
26 Tachwedd 2013 - Deadline 8
CaeedigINTERESTED PARTIES DEADLINE IV for receipt of:
- Any written comments on the ExA’s draft Development Consent Order.
- Any written comments on the matrices to inform Report on the Implications for European Sites