The list below includes a record of advice we have provided for this project.
-
Enquiry sent to the Secretary of State
-
Enquiry sent to the Secretary of State
-
Enquiry sent to the Secretary of State
-
Enquiry sent to the Secretary of State.
-
Project Update Meeting
-
A project update meeting to discuss East Anglia ONE, THREE and FOUR wind farms.
-
A project update meeting for East Anglia THREE and FOUR, including an update for East Anglia ONE.
-
Request information on when view on the project can be submitted.
-
In regard to the s127 application, Anglian Water Services take the view that the Written representations provide useful background information for the Examining Panel and would like to maintain this r...
Read more
-
Query in relation to s127 applications for the examination of East Anglia One Offshore Windfarm
Anglian Water Services take the view that the Written Representations provide useful background infor...
Read more
-
Thank you for the information it will help me get started in quest to get up to speed on what is happing.
I appreciate that I may too late to register as an interested party. However, are you a...
Read more
-
Request to register as an Interested Party and submit written representations during the examination of the application
-
Further to the Ministry of Defence representation made on 7 March 2013, please find attached a letter detailing an updated position which the examining authority may wish to consider.
-
On 8 April 2013, East Anglia One brought to the attention of the Planning Inspectorate project team a number of potential amendments that may be considered as part of the examination of the applicatio...
Read more
-
Submission of further comments
-
Submitting additional documents during the pre-examination stage.
-
The query related to whether it was possible to pay one fee for the examination and get a refund of any overspend.
-
How can a Statutory Body become an Interested Party for the purpose of an examination?
-
Update on East Anglia THREE and FOUR applications and logistical discussion on East Anglia ONE examination
-
A project update meeting for the proposed East Anglia Offshore Windfarm project (East Anglia ONE)with the developers, East Anglia One Ltd. and their legal representatives Bond Pearce, to discuss pre-s...
Read more
-
Pre-application tripartite meeting for the proposed East Anglia Offshore Windfarm (Zone 5) project - East Anglia One, between The Planning Inspectorate, representatives from the local authorities of S...
Read more
-
Promoters for the East Anglia Offshore Windfarm (East Anglia ONE), currently at pre-application, sought advice from the Planning Inspectorate on their approach to include cable ducting as part of the ...
Read more
-
Following the meeting on 7 June 2012 held at The Planning Inspectorate offices in Bristol, The Planning Inspectorate issued advice to the promoter on some of their draft plans.
The advice was sent ...
Read more
-
A project update meeting was held on 7 June 2012 with the developer for East Anglia ONE Offshore Wind at the Planning Inspectorate offices in Bristol.
The attendees were: Mike Harris (Case Leader -...
Read more
-
A project update meeting for the proposed East Anglia Offshore Windfarm (Zone 5) - East Anglia ONE, was held on 27 January 2012 at the IPC offices in Bristol and attended by IPC, Scottish Power Renewa...
Read more