The examination opened on 18 July 2013

The examination closed on 18 January 2014

Upcoming deadlines and events

There are no deadlines and events

Past deadlines and events

18 July 2013 - Preliminary Meeting

Closed

Preliminary Meeting at The Brighton Centre, Kings Road, Brighton BN1 2GR

25 July 2013 - Deadline 1

Closed

Issue by the Examining Authority:

  • Examination timetable
  • Examining Authority’s first Questions6 (EAQs)
  • Requests for Statements of Common Ground (SoCG)
  • Submission by the applicant of any documents relating to the applicant’s proposed corrections and omissions to the application
  • Submission by any other party of corrections and omissions in relation to a relevant representation

7 August 2013 - Deadline 2

Closed

Issue by the Examining Authority: Notification by ExA of date, time and place for hearings relating to the Development Consent Order and Deemed Marine Licence

9 August 2013 - Deadline 3

Closed

DEADLINE I for receipt by the Examining Authority: Local Impact Reports

15 August 2013 - Deadline 4

Closed

DEADLINE II for receipt by the Examining Authority:

  • Written Representations (WRs)including any summaries of Written Representations of more than 1500 words
  • Any summaries of Relevant Representations (RRs) exceeding 1500 words
  • Responses to ExA’s first written questions (EAQs)
  • Updated matrices prepared by the applicant to inform the Report on Implications for European Sites
  • Statements of Common Ground (SoCGs)
  • Comments on Relevant Representations (RRs)
  • Notification of wish to be heard at Open Floor (OF) Hearing by Interested Parties
  • Notification of wish to make oral representation at the Issue Specific Hearing
  • Notification of wish to make oral representation at Compulsory Acquisition (CA) Hearing
  • Notification of wish to attend site visit in the company of interested parties and any representations relating to proposed locations to visit
  • Deadline for Statutory Parties and persons in certain categories with interest in land to inform the ExA of a wish to be considered as an Interested Party

21 August 2013 - Deadline 5

Closed

Issue by the Examining Authority:

  • Notification by ExA of date, time and place for Open Floor Hearing
  • Notification of time and place of ExA’s inspection of a site to which the application/specific matters relate in the company of Interested Parties

28 August 2013 - Issue Specific Hearing 1

Closed

Development Consent Order and Deemed Marine Licence

29 August 2013 - Issue Specific Hearing 2

Closed

Development Consent Order and Deemed Marine Licence

5 September 2013 - Deadline 6

Closed

DEADLINE III for receipt by the Examining Authority:

  • Post-Hearing documents including any written summary of an oral case put at any Development Consent Order and Deemed Marine Licence Hearings and any documents/amendments requested by the ExA
  • Comments on Local Impact Reports

11 September 2013 - Open Floor Hearing 1

Closed

Open Floor Hearing

12 September 2013 - Deadline 7

Closed

DEADLINE IV for receipt by the Examining Authority:

  • Comments on Written Representations (WRs)
  • Comments on responses to ExA’s first written questions
  • Comments on applicant’s matrices to inform the Report on the Implications for European Sites
  • Comments on Statements of Common Ground

12 September 2013 - Open Floor Hearing 2

Closed

Open Floor Hearing

19 September 2013 - Deadline 8

Closed

DEADLINE V for receipt by the Examining Authority:

  • Post-Hearing documents including any written summary of an oral case put at any Open Floor Hearings and any documents/amendments requested by the ExA

24 September 2013 - Deadline 9

Closed

Issue by the Examining Authority:

  • Examining Authority’s second written questions (EAQs)

25 September 2013 - Site Visit (Accompanied) 1

Closed

ExA's inspection of onshore and offshore sites in the company of Interested Parties

26 September 2013 - Site Visit (Accompanied) 2

Closed

ExA's inspection of onshore and offshore sites in the company of Interested Parties

9 October 2013 - Deadline 10

Closed

DEADLINE VI for receipt by the Examining Authority:

  • Responses to comments on matrices prepared by the applicant to inform the Report on Implications for European Sites

15 October 2013 - Deadline 11

Closed

DEADLINE VII for receipt by the Examining Authority:

  • Responses to ExA’s second written questions (EAQs)

29 October 2013 - Deadline 12

Closed

DEADLINE for receipt by the Examining Authority:

  • Further information requested under Rule 17 relating to outstanding Habitats Regulation assessment work and final completed matrices

30 October 2013 - Issue Specific Hearing 3

Closed

Issue Specific Hearing

31 October 2013 - Issue Specific Hearing 4

Closed

Issue Specific Hearing

1 November 2013 - Issue Specific Hearing 5

Closed

Issue Specific Hearing

6 November 2013 - Issue Specific Hearing 6

Closed

Development Consent Order and Deemed Marine Licence

7 November 2013 - Issue Specific Hearing 7

Closed

Development Consent Order and Deemed Marine Licence

12 November 2013 - Deadline 13

Closed

DEADLINE VIII for receipt by the Examining Authority:

  • Post-Hearing documents including any written summary of an oral case put at any Issue Specific Hearings and any documents/amendments requested by the ExA Submission of protective provisions and updated Book of Reference requested under Rule 17

12 November 2013 - Issue Specific Hearing 8

Closed

Deadline VIII

27 November 2013 - Issue Specific Hearing 9

Closed

Compulsory Acquisition Hearing

28 November 2013 - Deadline 14

Closed

DEADLINE IX for receipt by the Examining Authority:

  • Comments on responses to ExA’s second written questions (EAQ)

28 November 2013 - Compulsory Acquisition Hearing 1

Closed

Compulsory Acquisition Hearing

29 November 2013 - Compulsory Acquisition Hearing 2

Closed

Compulsory Acquisition Hearing

3 December 2013 - Issue Specific Hearing 10

Closed

Issue Specific Hearing

4 December 2013 - Issue Specific Hearing 11

Closed

Issue Specific Hearing

5 December 2013 - Deadline 15

Closed

DEADLINE X for receipt by the Examining Authority:

  • Final Statements of Common Ground (SoCGs)
  • Post-Hearing documents including any written summary of an oral case put at any Compulsory Acquisition Hearings and any documents/amendments requested by the ExA

5 December 2013 - Issue Specific Hearing 12

Closed

Development Consent Order and Deemed Marine Licence

6 December 2013 - Issue Specific Hearing 13

Closed

Development Consent Order and Deemed Marine Licence

10 December 2013 - Deadline 16

Closed

DEADLINE XI for receipt by the Examining Authority:

  • Post-Hearing documents including any written summary of an oral case put at any Development Consent Order and Deemed Marine Licence Hearings and any documents/amendments requested by the ExA

13 December 2013 - Deadline 17

Closed

including the matrices prepared by the ExA for consultation"

8 January 2014 - Deadline 18

Closed

DEADLINE XII for receipt by the Examining Authority:

  • Any written comments on the ExA’s draft Development Consent Order.