The list below includes a record of advice we have provided for this project.
There is a statutory duty, under section 51 of the Planning Act 2008, around an application or potential application. This includes recording the name of the person who requested advice and the advice given. This information has to be made publicly available.
Search by key words or the name of person the advice was given to.
Showing 1 to 21 of 21 documents, newest first.
Results per page 25 | View 50 results per page | View 100 results per page
Meeting regarding (Non-Material) Change request.
Meeting with DONG Energy concerning a potential change application.
Natural England asked for clarification of the Examining Authority's Second Question No. EO18 e which asked: "What possible contingent or other mitigation or compensation measures would Natural Englan... Read more
Seeking clarification to one of the questions posed within the ExA's second round of written questions. The relevant question is EO 18(c) which is as follows: ?What further work on the derivation of a... Read more
Further to our earlier conversations, I set out below an overview of the position: ? The Ex. A notified through its letter of 18 December 2013 (the Rule 8 Letter) the procedural timetable for the exa... Read more
Request at a hearing on how to submit representations to the Hornsea examination
Post-Acceptance s51 advice to the applicant.
Project update meeting on Hornsea Offshore Wind Farm (Zone 4) ? Projects 1 and 2
To discuss the emerging applications for the proposed Hornsea Offshore Wind Farm (Zone 4) ? projects One and Two
Does the requirement under APFP Reg 6(1)(b)(i) to provide 'details of the proposed route and method of installation for any cable' mean that applicants have to submit a separate 'Cable Statement' docu... Read more
Further to the meeting between SmartWind and the Planning Inspectorate on 12 December 2012, some updated drafting in relation to transfer of the DCO and the effect on deemed Marine Licences was provid... Read more
Meeting at Temple Quay House for SMart Wind Ltd to provide project updates and for The Planning Inspectorate to provide advice on draft documentation.
Dear Mike, I?m writing to you just to follow up my telephone message. We?ve noticed that there is a difference in the advice given in the original Project One scoping opinion (Dec 2010) and the updat... Read more
Planning Inspectorate meeting with developer for a project update and draft Development Consent Order review.
General Project Update
A project update meeting was held to allow the promoter to advise the IPC of recent pre-application work.
The promoter wrote to the IPC seeking advice on a draft letter, proposed to be issued to section 42 consultees, detailing a proposed change in the maximum rotor diameter (from 150m to 178m). The lett... Read more
Project update meeting with promoter
a) Projects with on and offshore elements - approach to consultation, application and determination b) IPC view on implications of OFTO for applications c) Approach to internationa... Read more
Introductory meeting with SMart Wind regarding Hornsea Zone 4 offshore wind farm