Skip to main content
Find a National Infrastructure Project

This is a beta service - your feedback will help us to improve it

Kentish Flats Extension Examination timetable

The examination timetable shows the dates of events and deadlines for submissions.

If you have registered to have your say, you can do this in the examination stage.

The examination stage

The examination opened on 22 February 2012

The examination closed on 20 August 2012

Upcoming deadlines and events

There are no deadlines and events

Past deadlines and events

22 February 2012 - Deadline 1

Closed

Preliminary Meeting

22 February 2012 - Preliminary Meeting

Closed

Preliminary Meeting to enable views to be expressed about matters set out in the agenda (annex B) and in particular to hear representations about the way in which the application is to be examined

5 March 2012 - Deadline 2

Closed

Notification by ExA of procedural decision including confirmation of the examination timetable and first written questions under Rule 8 of the Infrastructure Planning (Examination Procedure) Rules 2010

14 March 2012 - Deadline 3

Closed

Deadline for receipt by the ExA of:

• Data related to the monitoring of the LA offshore wind farm.

1 April 2012 - Deadline 4

Closed

Functions of the IPC are transferred to The Planning Inspectorate (National Infrastructure Directorate) as a result of the amendments to the PA2008 made by the Localism Act 2011.

5 April 2012 - Deadline 5

Closed

Deadline for receipt by the Examining Authority of:

• Responses to the ExA’s Written Questions • Responses to the submitted draft DCO and the Schedule of DCO corrections and amendments issued by the ExA. • Applicant’s revised draft DCO. • Written Representations (including summaries of any Written Representations of more than 1550 words) • LIR from relevant local authorities • SoCGs regarding:#

  • Biological Environment and Ecology, (including data contained in applicant’s HRA report).
  • Fish and Fishing
  • Radar, navigation and search and rescue
  • Other SoCG’s to be submitted by the applicant • Any analysis of information emerging from the monitoring of LA • Notification of wish to be heard at an Openfloor Hearing by Interested Parties • Notification by Interested Parties of wish to make oral representations at any issue specific hearings

18 April 2012 - Deadline 6

Closed

Deadline for receipt by the ExA of:

• Supplementary SoCG regarding interpretation, analysis and assessment of additional information emerging from the monitoring of LA

27 April 2012 - Deadline 7

Closed

Notification of arrangements for offshore site inspection on 29 May 2012 under Rule 16

11 May 2012 - Deadline 8

Closed

Deadline for receipt by the ExA of any written comments regarding:

• Responses to the ExA’s written questions • Relevant Representations • Written representations • SoCGs • LIRs • Any additional information emerging from the monitoring of LA • The applicant’s revised draft DCO and any other contributions regarding the schedule of corrections issued by the ExA

19 May 2012 - Deadline 9

Closed

Deadline for Interested Parties to notify the ExA of:

• Which hearing session(s) they wish to attend • If they wish to speak at the hearing. And provide:

• Written summaries of the matters they wish to raise

29 May 2012 - Deadline 10

Closed

ExA’s offshore site inspection in the company of interested parties

29 May 2012 - Site Visit (Accompanied)

Closed

Examining Authority's site inspection in the company of Interested Parties

30 May 2012 - Deadline 11

Closed

Hearing regarding DCO requirements, related LIR matters and DML (am)

30 May 2012 - Deadline 12

Closed

Hearing regarding biological environment, ecology and fishing (pm)

30 May 2012 - Issue Specific Hearing 1

Closed

First Hearing regarding DCO requirements, related LIR matters & deemed Marine Licence

30 May 2012 - Issue Specific Hearing 2

Closed

Hearing regarding biological environment, ecology & Fishing

31 May 2012 - Deadline 13

Closed

Hearing regarding Habitats Regulations aspects and information to support the appropriate assessment (am)

31 May 2012 - Deadline 14

Closed

Hearing regarding identified specific issues including visual effects, radar effects, marine archaeology, and damage to property around cable landfall and transition pit (pm)

31 May 2012 - Issue Specific Hearing 3

Closed

Hearing regarding Habitats Regulations aspects & information to support the Appropriate Assessment

31 May 2012 - Issue Specific Hearing 4

Closed

Hearing regarding identified specific issues inc. visual effects, radar effects, marine archaeology & damage to property around, cable landfall & transition pit

1 June 2012 - Deadline 15

Closed

Notification of revision to Examination Timetable under Rule 8 (3)

6 June 2012 - Deadline 16

Closed

ExA’s requests for further information and comments under Rule 17

7 June 2012 - Deadline 17

Closed

Deadline for receipt by the ExA of:

• Written summaries of any case put at any preceding hearing • Applicant’s final draft DCO

12 June 2012 - Open Floor Hearing 1

Closed

Open Floor Hearing.

12 June 2012 - Open Floor Hearing 2

Closed

Open Floor Hearing.

Reserve session for any additional hearing required

13 June 2012 - Deadline 18

Closed

Deadline for:

• Written summaries of any case put at the hearings on 30 and 31 May 2012 • Applicant’s final draft DCO

13 June 2012 - Issue Specific Hearing 5

Closed

Second Hearing on Development Consent Order, requirements and related Local Report matters.

19 June 2012 - Deadline 19

Closed

Deadline for receipt by the ExA of:

• Comments on CCC’s submission due by 8 June 2012 • Responses to ExA’s questions under Rule 17 issued by letter on 6 June 2012

28 June 2012 - Deadline 20

Closed

Notification of:

• ExA’s Draft DCO and Report on the Implications for European Sites issued for comment • Requests for further information under Rule 17 • Revised timetable

16 July 2012 - Deadline 21

Closed

Deadline for receipt by the ExA of:

• Any written comments on the draft appropriate assessment

23 July 2012 - Deadline 22

Closed

Deadline for receipt by the ExA of:

• Any written comments on the ExA’s draft DCO • Any written comments on the Report on the Implications for European Sites • Responses to questions issued under Rule 17 by the letter of 28 June 2012

7 August 2012 - Deadline 23

Closed

Request for further information under Rule 17

14 August 2012 - Deadline 24

Closed

Deadline for responses to the letter of 7 August

20 August 2012 - Deadline 25

Closed

Examination closes at 15:00