There are no deadlines and events
Examination timetable
The examination timetable shows the dates of events and deadlines for submissions.
If you have registered to have your say, you can do this in the examination stage.
The examination stage
The examination opened on 11 September 2013
The examination closed on 11 March 2014
11 September 2013 - Preliminary Meeting
ClosedThe purpose of the preliminary meeting is to enable views to be put to the Examining Authority about the way in which the application is to be examined. It is important to appreciate that this meeting deals only with procedure and not with the merits of the application.
20 September 2013 - Deadline 1
ClosedIssue by the Examining Authority (ExA) of: • Examination timetable • ExA’s first written questions
27 September 2013 - Deadline 2
ClosedDeadline for receipt by the ExA of comments on the applicant’s proposed change to the Order limits (see Annex E of the Rule 8 Letter for further information).
30 September 2013 - Deadline 3
ClosedDeadline for publication of comments received on the applicant’s proposed change to the Order limits, on the North Killingholme Power Project section of the National Infrastructure pages of the Planning Portal’s website.
2 October 2013 - Deadline 4
ClosedDeadline for receipt by the ExA of the applicant’s response to any comments received in regards to the proposed change to the Order limits
4 October 2013 - Deadline 5
ClosedIssue by the ExA of its Procedural Decision in regards to the applicant’s proposed change to the Order limits.
4 October 2013 - Deadline 6
ClosedDeadline for Statutory Parties and persons in certain categories with interest in land to inform the ExA of a wish to be considered as an Interested Party
14 October 2013 - Deadline 7
ClosedDeadline for receipt by the ExA of: • Comments on relevant representations (RRs) already received • Summaries of all RRs exceeding 1500 words • Written representations (WRs) by all interested parties • Summaries of all WRs exceeding 1500 words • Local Impact Report(s) (LIR) from local authorities • Applicant’s matrices summarising effects on European sites • Photomontages as required • Responses to ExA’s first written questions • Draft Statements of Common Ground • Requests for any issue specific, compulsory acquisition and open floor hearing • Notification by interested parties of wish to make oral representations at a specific issue hearing • Notification by interested parties of wish to speak at an open floor hearing • Notification by affected persons of wish to speak at a compulsory acquisition hearing
22 October 2013 - Deadline 8
ClosedNotification by ExA of date, time and place for: • Issue specific hearing on the draft DCO • Issue specific hearings • Open floor hearing (if required) • Compulsory acquisition hearing (if required) • Accompanied site visit
11 November 2013 - Deadline 9
ClosedDeadline for receipt by the ExA of: • Comments on WRs and responses to comments on RRs • Comments on LIRs • Comments on applicant’s matrices summarising effects on European sites • Comments on responses to ExA’s first written questions • Any proposed amendments to the draft DCO by the applicant
19 November 2013 - Site Visit (Accompanied)
ClosedAccompanied site visit.
The site visit will begin on the application site, accessed through Entrance ‘D’, first turning left off Haven Road, DN40 3JS.
8:30 am registration 9:00 am start
20 November 2013 - Issue Specific Hearing 1
ClosedIssue specific hearing on the draft DCO, including protective provisions. Ashbourne Hotel, Vicarage Lane, North Killingholme, DN40 3JL 8:30 am registration 9:00 am start
20 November 2013 - Open Floor Hearing
ClosedOpen Floor Hearing Ashbourne Hotel, Vicarage Lane, North Killingholme, DN40 3JL 6:00 pm registration 6:30 pm start
21 November 2013 - Compulsory Acquisition Hearing 1
ClosedCompulsory acquisition hearing. Ashbourne Hotel, Vicarage Lane, North Killingholme, DN40 3JL 8:30 am registration 9:00 am start
22 November 2013 - Compulsory Acquisition Hearing 2
ClosedCompulsory acquisition hearing. Ashbourne Hotel, Vicarage Lane, North Killingholme, DN40 3JL 8:30 am registration 9:00 am start
26 November 2013 - Issue Specific Hearing 2
ClosedIssue specific hearing on Transport and Traffic. Ashbourne Hotel, Vicarage Lane, North Killingholme, DN40 3JL 8:30 am registration 9:00 am start
27 November 2013 - Issue Specific Hearing 3
ClosedIssue specific hearing on Habitats, Ecology and Nature Conservation. Ashbourne Hotel, Vicarage Lane, North Killingholme, DN40 3JL 8:30 am registration 9:00 am start
28 November 2013 - Issue Specific Hearing 4
ClosedIssue specific hearing on other Environmental Matters. Ashbourne Hotel, Vicarage Lane, North Killingholme, DN40 3JL 8:30 am registration 9:00 am start
29 November 2013 - Issue Specific Hearing 5
ClosedIssue specific hearing on the Historic and Archaeological Environment. Ashbourne Hotel, Vicarage Lane, North Killingholme, DN40 3JL 8:30 am registration 9:00 am start
29 November 2013 - Issue Specific Hearing 6
ClosedIssue specific hearing on Design, Layout and Visibility. Ashbourne Hotel, Vicarage Lane, North Killingholme, DN40 3JL 1:30 pm registration 2:00 pm start
2 December 2013 - Deadline 10
ClosedDeadline for receipt by the ExA of: Comments on late submissions accepted by the ExA by letter dated 18 November 2013
9 December 2013 - Deadline 11
ClosedDeadline for receipt by the ExA of: Written summaries of the cases put orally at the hearings held between Wednesday 20 and Friday 22 November 2013, and hearings held on and between Tuesday 26 and Thursday 28 November 2013
13 December 2013 - Deadline 12
ClosedIssue by the ExA of: • Second written questions
16 December 2013 - Deadline 13
ClosedDeadline for receipt by the ExA of: Comments on any responses received by the deadline of 2 December 2013
7 January 2014 - Deadline 14
ClosedNotification by ExA of date, time and place for: • Any further compulsory acquisition hearings in the event that the ExA decides during the progress of the examination that they are needed • Any further issue specific hearings in the event that the ExA decides during the progress of the examination that they are needed • Any further open floor hearing (if requested) • Any further issue specific hearing on the draft DCO
7 January 2014 - Deadline 15
ClosedDeadline for receipt by the ExA of: • Responses to ExA’s second written questions
24 January 2014 - Deadline 16
ClosedDeadline for receipt by the ExA of: • Comments on responses to ExA’s second written questions • Any proposed amendments by the applicant to the draft DCO • Final Statements of Common Ground • Draft s.106 agreements • Any proposed changes to the order limit by applicant
4 February 2014 - Issue Specific Hearing 7
ClosedIssue specific hearing on the development consent order including protective provisions. Ashbourne Hotel, Vicarage Lane, North Killingholme, DN40 3JL 8:30 am registration 9:00 am start
5 February 2014 - Issue Specific Hearing 8
ClosedIssue specific hearing on the Habitats, Ecology and Nature Conservation Ashbourne Hotel, Vicarage Lane, North Killingholme, DN40 3JL
6 February 2014 - Issue Specific Hearing 9
ClosedIssue specific hearing on Transport and Traffic Ashbourne Hotel, Vicarage Lane, North Killingholme, DN40 3JL
14 February 2014 - Deadline 17
ClosedIssue by the ExA of: • The Report on the Implications for European Sites (RIES)
19 February 2014 - Deadline 18
ClosedDeadline for receipt by the ExA of: • Written summaries of the cases put orally at the hearings held between Tuesday 4 and Friday 7 February 2014, and Tuesday 11 and Thursday 13 February 2014 • The applicants final version of the draft DCO • Completed s.106 agreements
28 February 2014 - Deadline 19
ClosedDeadline for receipt by the ExA of: • Comments on the Report on the Implications for European Sites (RIES) • Any further comments on the final version of the draft DCO • Comments on any submitted proposal for changes to the order limit by the applicant