Examination timetable
The examination timetable shows the dates of events and deadlines for submissions.
If you have registered to have your say, you can do this in the examination stage.
The examination stage
The examination opened on 22 April 2015
The examination closed on 15 October 2015
22 April 2015 - Preliminary Meeting
ClosedPreliminary Meeting
29 April 2015 - Deadline 1
ClosedIssue by ExA of: • Examination timetable • ExA first written questions
20 May 2015 - Deadline 2
ClosedDeadline I
Deadline for receipt of: • Comments on relevant representations (RRs) • Summaries of all RRs exceeding 1500 words • Written representations (WRs) by all interested parties • Summaries of all WRs exceeding 1500 words • Local Impact Report from any local authorities • Statements of Common Ground requested by ExA – see Annex G • Responses to ExA’s first written questions • Comments on any additional submissions (non-material change of application documents dated 13 April 2015 by applicant) • Comments on, and suggested changes to, the draft Development Consent Order
Notifications: • Notification by Statutory Parties to inform the ExA of a wish to be considered an interested party • Notification of wish to speak at a compulsory acquisition hearing • Notification of wish to speak at the issue specific hearing on the draft Development Consent Order (DCO) • Notification of wish to speak at issue specific hearing on environmental issues • Notification of wish to speak at an open floor hearing • Notification of wish to attend accompanied site inspection
3 June 2015 - Deadline 3
ClosedIssue by the ExA of: • Confirmation by the ExA of date, time and place for a accompanied site inspection (ASI) • Confirmation by ExA of date, time and place for an issue specific hearing • Confirmation by ExA of date, time and place for compulsory acquisition hearing • Confirmation by ExA of date, time and place for an open floor hearing, if required • Any further request for information if required
10 June 2015 - Deadline 4
ClosedDeadline II
Deadline for receipt by the ExA of: • Comments on WRs and responses to comments on RRs • Comments on Local Impact Reports • Comments on responses to ExA’s first written questions • Comments on SoCGs • Revised draft DCO from applicant • Applicant’s response to comments received by Deadline I on non-material change to application documents, dated 13 April 2015 • Response to any further information requested by the ExA for this deadline
19 June 2015 - Deadline 5
ClosedDeadline III
• Report compiled from responses to the Applicant’s notification of the non-material amendments to the DCO application and updates to the application documents dated 13 April 2015
1 July 2015 - Issue Specific Hearing 1
ClosedEnvironmental Issues
1 July 2015 - Open Floor Hearing
Closed?
2 July 2015 - Compulsory Acquisition Hearing
Closed?
2 July 2015 - Issue Specific Hearing 2
Closeddraft Development Consent Order
3 July 2015 - Deadline 6
ClosedDay reserved for accompanied site inspection
3 July 2015 - Site Visit (Accompanied)
Closed?
8 July 2015 - Deadline 7
ClosedDeadline IV
• Post-Hearing documents including any written summary of an oral case put at any hearing • Comments on any further information received by the ExA for Deadline II
22 July 2015 - Deadline 8
ClosedIssue by ExA of:
• Second written questions
5 August 2015 - Deadline 9
ClosedDeadline V
Deadline for receipt of:
• Responses to ExA’s second written questions • Applicants revised draft DCO taking account of issues raised and comments to date
21 August 2015 - Deadline 10
ClosedDeadline VI
Deadline for receipt of: • Comments on applicant’s revised draft DCO • Comments on responses to ExA’s second written questions (if required) • Response to any further information requested by the ExA for this deadline
7 September 2015 - Deadline 11
ClosedIssue by the ExA of:
• ExA’s revised dDCO taking issues raised and comments into account • ExA’s Report on the Implications for European Sites (RIES) for consultation • Any further request for information, if required
23 September 2015 - Deadline 12
ClosedDEADLINE VII
Deadline for receipt by ExA of:
• Any updated SoCGs, • Any written comments on the ExA’s revised dDCO • Any written comments on the ExA’s RIES • Response to any further information requested by the ExA for this deadline (if required)
7 October 2015 - Deadline 13
ClosedDEADLINE VIII
Deadline for receipt by ExA of:
• Responses on the additional submission (Project and Funding Update) received by the applicant • Comments on any information received by the ExA for Deadline VII • Any further requests for information, if required
13 October 2015 - Deadline 14
ClosedDEADLINE IX
Deadline for receipt by ExA of:
• Comments, on responses to the additional submission (Project and Funding Update) received by the applicant • Comments on any information and/responses received by the ExA for Deadline VIII • Any further requests for information, if required
15 October 2015 - Deadline 15
ClosedClose of the Examination.
The ExA is under a duty to complete the examination of the application by the end of the period of 6 months beginning with the day after the close of the Preliminary Meeting.