Knottingley Power Project Amserlen yr archwiliad

Mae amserlen yr archwiliad yn dangos dyddiadau digwyddiadau a therfynau amser ar gyfer cyflwyniadau.

Os ydych wedi cofrestru i leisio'ch barn, gallwch wneud hyn yn ystod y cam archwilio.

Y cam archwilio

Agorodd yr archwiliad ar 13 March 2014

Caeodd yr archwiliad ar 13 September 2014

Terfynau amser a digwyddiadau i ddod

Nid oes unrhyw derfynau amser neu ddigwyddiadau

Terfynau amser a digwyddiadau blaenorol

13 Mawrth 2014 - Preliminary Meeting

Caeedig

Preliminary Meeting

27 Mawrth 2014 - Deadline 1

Caeedig

Receipt of written notification of:

• Request for receipt of written notification by statutory parties of a wish to be considered as an interested party

• Request for receipt of notification (using the prescribed form) by persons with certain categories of interest in the land of a wish to become an interested party

11 Ebrill 2014 - Deadline 2

Caeedig

Deadline 1

Deadline for receipt by the ExA of:

• Comments on additional documents provided and listed as accepted in Annex D of this letter and published on the Knottingley Power Project webpage on Thursday 20 March 2014

• Comments by interested parties on relevant representations (RRs) already received

• Summaries of all RRs by interested parties whose RRs exceeded 1500 words

• Written representations (WRs) by interested parties

• Summaries of WRs by interested parties whose WRs exceeded 1500 words

• Responses to ExA’s first written questions

• Statements of Common Ground requested by the ExA

• Local Impact Report(s) (LIR) from local authorities defined under s56A of the Planning Act 2008 (as amended)

• Any documents/amendments requested by the ExA at the Preliminary Meeting

14 Ebrill 2014 - Deadline 3

Caeedig

Deadline 2

Deadline for notification by interested parties of their wish:

• to be heard at an open floor hearing (OFH)

• to make oral representations at any issue specific hearing (ISH), including compulsory acquisition, DCO and local environmental impact matters

• to attend any accompanied site visit and any representations to view at or near the site or the surrounding area

17 Ebrill 2014 - Deadline 4

Caeedig

Notification by the ExA of date, time and place for:

• Compulsory acquisition hearing (CAH) • Local environmental impact matters hearing • Any accompanied site visit(s) (ASV) • Any other issue specific hearing(s) • Any open floor hearing

6 Mai 2014 - Deadline 5

Caeedig

Deadline 3

Deadline for the receipt of:

• Comments on the written representations and responses to comments on relevant representations

• Comments on Statements of Common Grounds

• Comments on Local Impact Reports

• Comments on responses to ExA’s first written questions

9 Mai 2014 - Deadline 6

Caeedig

Deadline for receipt of comments regarding the Examining Authority's procedural decision in relation to changes to the application and comments on the closure of Kellingley Colleriery, made on 1 May 2014.

13 Mai 2014 - Deadline 7

Caeedig

Date reserved for any accompanied site visit

13 Mai 2014 - Site Visit (Accompanied)

Caeedig

Accompanied Site Visit

14 Mai 2014 - Deadline 8

Caeedig

Date reserved for environmental impacts hearing and evening open floor hearing

14 Mai 2014 - Issue Specific Hearing 1

Caeedig

Issue Specific Hearing relating to Environmental Impacts

14 Mai 2014 - Open Floor Hearing

Caeedig

Open Floor Hearing

15 Mai 2014 - Deadline 9

Caeedig

Date reserved for compulsory acqusition hearing

15 Mai 2014 - Compulsory Acquisition Hearing

Caeedig

Compulsory Acquisition Hearing

23 Mai 2014 - Deadline 10

Caeedig

Deadline 4

Deadline for the receipt of:

• Written summary of the oral case put at the environmental impacts hearing, compulsory acquisition and open floor hearing

• Any documents/amendments requested by the ExA including

• Any revised DCO

28 Mai 2014 - Deadline 11

Caeedig

Issue by the ExA of:

• Second round of written questions (if a second round is required)

• Any further request for SoCGs

20 Mehefin 2014 - Deadline 12

Caeedig

Deadline 5

Deadline for the receipt of:

• Responses to the ExA’s second round of questions and any further SoCGs

• Comments on written summaries of cases put at any issue specific or open floor hearings

• Comments on any submitted revised DCO

23 Mehefin 2014 - Deadline 13

Caeedig

Notification by ExA of the time, date and place for:

• DCO hearing

• Any other hearings deemed necessary by the ExA

11 Gorffennaf 2014 - Deadline 14

Caeedig

Deadline 6

Deadline for the receipt of:

• Comments on the responses to the ExA’s second round of questions and any further SoCGs

• Any documents/amendments requested by the ExA

16 Gorffennaf 2014 - Deadline 15

Caeedig

Issue Specific Hearing on the draft Development Consent Order and Water Resource issues

16 Gorffennaf 2014 - Issue Specific Hearing 2

Caeedig

Issue Specific Hearing on the draft Development Consent Order and Water Resource issues

24 Gorffennaf 2014 - Deadline 16

Caeedig

Deadline 7

Deadline for the receipt of:

• Written summaries of cases put orally at DCO/or other issue specific hearing on 16 and 17 July 2014 and;

• Any documents/amendments requested by the ExA at the hearings

• Final revised DCO

15 Awst 2014 - Deadline 17

Caeedig

Deadline 8

Deadline for the receipt of:

• Comments on the written summaries of cases put orally at DCO/and any issue specific hearing on 16 and 17 July 2014

• Comments on final revised DCO