11 November 2024
A Decision Letter (227,KB) and Amendment Order (PDF, 75KB) have been issued by the Department of Energy Security and Net Zero to make a change that is not material to the Dogger Bank Teesside A and B Offshore Wind Farm Order 2015.
7 November 2024
The Applicant has provided their Consultation and Publicity Statement.
14 October 2024
Representations received in response to the application for a non-material change to the Made Dogger Bank Teeside A and B Offshore Wind Farm Order 2015 (As Amended) Development Consent Order have been published.
7 October 2024
On 19 August 2024, the Marine Management Organisation (MMO) received a request from Dogger Bank C Offshore Wind Farms Limited to vary the Deemed Marine Licences (DML) contained within Schedule 8 of The Dogger Bank C Offshore Wind Farm Order 2015 (As Amended).
Following consultation with relevant stakeholders the MMO has now completed its consideration of the request and, in exercise of the powers conferred by section 72(3)(d) of the Marine and Coastal Access Act 2009, has determined to make the variations as detailed in the attached documents.
Please see attached documents:
15 August 2024
An application for a non-material change to the made Dogger Bank Teeside A and B Offshore Wind Farm Order 2015 (As Amended) has been made by Doggerbank Offshore Wind Farm Project 3 Projco Limited.
The deadline for receipt of representations is 6th October 2024.
If you wish to make a representation, this should be emailed to DBTeesideAB@planninginspectorate.gov.uk or posted to:
National Infrastructure
The Planning Inspectorate
Temple Quay House
2 The Square
Bristol
BS1 6PN
16 July 2024
The Secretary of State for Energy Security and Net Zero has issued a letter (PDF,130KB) confirming those parties that the Applicant should consult regarding a proposed non-material change application relating to The Dogger Bank Teesside A and B Offshore Wind Farm (PDF, 452KB) Made Order.
4 July 2024
On 06 November 2023 the Marine Management Organisation (MMO) received a request from Dogger Bank A&B Offshore Wind Farms Limited to vary the Deemed Marine Licences (DML) contained within Schedule 9 of The Dogger Bank Creyke Beck Offshore Wind Farm Order 2015 (As Amended).
The MMO has now completed its consideration of the request and, in exercise of the powers conferred by section 72(3)(d) of the Marine and Coastal Access Act 2009, has determined to make the variations as detailed in the following documents:
Cover Letter (PDF, 175KB)
Notice of Variation for Schedule 9 (PDF, 81KB)
Variation 7 – DML Schedules of The Dogger Bank B Creyke Beck Offshore Wind Farm Order 2015 (As Amended) (PDF, 449KB)
4 November 2021
Following consultation with relevant stakeholders the MMO has now completed its consideration of the request and, in exercise of the powers conferred by section 72(3)(d) of the Marine and Coastal Access Act 2009, has determined to make the variations as detailed in the attached documents:
- Cover Letter (PDF,927KB)
- Notice of Variation for Schedule 8 (PDF,31KB)
- Notice of Variation for Schedule 10 (PDF,31KB)
- Variation 5 – DML Schedule 8 of the Dogger Bank Teesside A and B Offshore Wind Farm Order 2015 (PDF, 158KB)
- Variation 5 – DML Schedule 10 of the Dogger Bank Teesside A and B Offshore Wind Farm Order 2015 (PDF,154KB)
9 August 2021
The Examination documents relating to this project have been archived and are no longer available on this site. The Secretary of State’s decision and Development Consent Order can be viewed on the Documents tab.
To find out where to view the Certified Documents please refer to the contact details set out in the Explanatory Note of the Development Consent Order.
18 February 2021
To find out where to view the Certified Documents please refer to the contact details set out in the Explanatory Note of the Development Consent Order.