Hornsea Offshore Wind Farm (Zone 4) - Project Two Examination timetable

The examination timetable shows the dates of events and deadlines for submissions.

If you have registered to have your say, you can do this in the examination stage.

The examination stage

The examination opened on 16 June 2015

The examination closed on 16 December 2015

Upcoming deadlines and events

There are no deadlines and events

Past deadlines and events

16 June 2015 - Preliminary Meeting

Closed

Preliminary Meeting

22 June 2015 - Deadline 1

Closed

Issue by Examining Authority (ExA) of:

• Examination timetable

• ExA’s first written questions

15 July 2015 - Deadline 2

Closed

Deadline 1 Deadline for receipt of:

• Comments on Relevant Representations (RRs)

• Summaries of all RRs exceeding 1500 words

• Written representations (WRs)

• Summaries of all WRs exceeding 1500 words

• Local Impact Report from any local authorities

• Statements of Common Ground (SoCG) requested by ExA

• Schedule of Mitigation Requirements

• Responses to ExA’s first written questions

• Notification of wish to speak at a compulsory acquisition (CA) hearing

• Notification of wish to make oral representations at the issue specific hearing on the draft Development Consent Order (DCO)

• Notification of wish to speak at the open floor hearing (OFH)

• Notification of wish to attend Accompanied Site Inspection (ASI)

• Notification of suggested locations for the ASI to cover

• Notification of any statutory party who wishes to participate in the examination.

28 July 2015 - Deadline 3

Closed

Date reserved for open floor hearing (OFH) if any requests are received by the 15 July 2015. If there are no requests, the hearing will be cancelled and interested parties will be notified through the banner on the project webpage.

29 July 2015 - Site Visit (Accompanied)

Closed

ASI starting at the Humber Royal Hotel

30 July 2015 - Issue Specific Hearing 1

Closed

First ISH

10 August 2015 - Deadline 4

Closed

Deadline 2 Deadline for receipt of:

• Comments on WRs and responses to comments on RRs

• Comments on Local Impact Reports (LIRs)

• Comments on responses to ExA’s first written questions

• Revised draft DCO from Applicant

• Updated HRA matrices

• All post hearing documents including written proofs of oral cases made at hearings

• Documents post Accompanied Site Inspection

• Any other information requested by the ExA

25 August 2015 - Deadline 5

Closed

Deadline 2a deadline for reciept of: Responses to Rule 17 letter issued 4 August 2015.

15 September 2015 - Issue Specific Hearing 2

Closed

ISH scheduled for 2 days

17 September 2015 - Compulsory Acquisition Hearing 1

Closed

2 day CAH

24 September 2015 - Deadline 6

Closed

Deadline 3 Deadline for receipt of:

All post-hearing documents including written proofs of oral cases made at hearings and any other information requested by the ExA.

29 September 2015 - Deadline 7

Closed

Date for issue of ExA’s second written questions (if there are still matters to explore after the hearings)

20 October 2015 - Deadline 8

Closed

Deadline 4 Deadline for receipt of:

• Responses to ExA’s second written questions

• Any other information requested by the ExA

27 October 2015 - Issue Specific Hearing 3

Closed

Start of ISH hearing

28 October 2015 - Issue Specific Hearing 4

Closed

?

29 October 2015 - Compulsory Acquisition Hearing 2

Closed

?

12 November 2015 - Deadline 9

Closed

Deadline 5 Deadline for receipt of:

• Comments on responses to ExA’s second written questions

• Receipt and publication of applicant’s final DCO • Documents post all hearings

• Written proofs of oral cases made at hearings

• Any other information requested by the ExA

26 November 2015 - Deadline 10

Closed

Deadline 6 Deadline for receipt of:

• Any final versions of SoCGs

• Any other information requested by the ExA and

• Issue of ExA’s consultation DCO

• Issue of Report on the Implications for European Sites (RIES)

10 December 2015 - Deadline 11

Closed

Deadline 7 Deadline for receipt of:

• Comments on Applicant’s DCO (REP5-006) • Comments on RIES

• Responses to Rule 17 issued 26 November 2015

• Any other information requested by the ExA

13 December 2015 - Deadline 12

Closed

Deadline 8 Deadline for receipt of:

• Response to Rule 17 issued 7 December 2015

16 December 2015 - Deadline 13

Closed

The ExA is under a duty to complete the examination of the application by the end of the period of 6 months beginning with the day after the close of the Preliminary Meeting.