East Anglia THREE Offshore Wind Farm Examination timetable

The examination timetable shows the dates of events and deadlines for submissions.

If you have registered to have your say, you can do this in the examination stage.

The examination stage

The examination closed on 28 December 2016

Upcoming deadlines and events

There are no deadlines and events

Past deadlines and events

28 June 2016 - Preliminary Meeting

Closed

Preliminary Meeting

28 June 2016 - Unaccompanied Site Visit

Closed

Unaccompanied Site Visit

29 June 2016 - Issue Specific Hearing

Closed

Issue Specific Hearing (ISH) relating to the definition of the project and draft Development Consent Order (DCO) matters

6 July 2016 - Publication by the ExA of First Written Questions and Timetable

Closed

Issue by Examining Authority (ExA) of:

• Examination timetable

• ExA first written questions

13 July 2016 - Deadline 1

Closed

Deadline 1

• Post-hearing documents including any written summary of an oral case put at the DCO ISH and any documents/amendments requested by the ExA

• Applicant’s revised draft DCO

27 July 2016 - Deadline 2

Closed

Deadline 2

Deadline for receipt of:

• Comments on relevant representations (RRs)

• Summaries of all RRs exceeding 1,500 words

• Written representations (WRs) by all interested parties

• Summaries of all WRs exceeding 1,500 words

• Comments on any additional representations and submissions received as outlined in Annex D

• Responses to Applicant’s revised draft DCO

• Local Impact Reports (LIRs) from any local authorities

• Statements of Common Ground (SoCG) requested by the ExA

• Responses to the ExA’s first written questions

• Notification of wish to speak at a Compulsory Acquisition Hearing (CAH)

• Notification of wish to make oral representations at any further ISHs

• Notification of wish to speak at an Open Floor Hearing (OFH)

• Notification of wish to attend an Accompanied Site Inspection (ASI)

• Representations relating to locations to view at the site or in the surrounding area which are considered to be relevant for the ExA during unaccompanied site inspections

• Representations relating to locations to view at the site or in the surrounding area which are considered to be relevant for the ExA during an accompanied site inspection to better understand representations made or to see land and interests where there is no opportunity to gain public access

• Notification from statutory parties, or local authorities without direct responsibility in the proposed development area, of a wish to be considered as an interested party

• Any other information requested by the ExA under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010 (the EPR)

3 August 2016 - Notification by the ExA

Closed

Issue by the ExA of:

Notification of the date, time and place for further ISHs, an OFH (if required) and CAHs (if required)

10 August 2016 - Deadline 3

Closed

Deadline 3

Deadline for receipt by the ExA of:

• Comments on WRs and responses to comments on RRs

• Comments on LIRs

• Comments on responses to the ExA’s first written questions

• Comments on responses to the Applicant’s revised draft DCO

• Responses to comments on any additional representations and submissions received

• Information to inform the HRA for the Southern North Sea pSAC report to be submitted by Applicant

• Statements of Common Ground (SoCG) requested by the ExA

6 September 2016 - Accompanied site inspection

Closed

accompanied site inspection, starting and ending at the Novotel Hotel, Ipswich. Commencing at 8.30am.

7 September 2016 - ISH on environmental or other matters

Closed

ISH on environmental or other matters to be held at the Town Hall, Ipswich.

8 September 2016 - ISH on the draft DCO

Closed

ISH on the draft DCO to be held at the Town Hall, Ipswich

15 September 2016 - Deadline 4

Closed

Deadline 4

Deadline for receipt by the ExA of:

• Post-hearing documents including any written summary of an oral case put at any hearing and any documents/amendments requested by the ExA

• Applicant’s revised draft DCO

• Any other information requested by the ExA under Rule 17 of the EPR

22 September 2016 - Publication by the ExA of Second written questions

Closed

Publication by the ExA of:

• Second written questions

6 October 2016 - Deadline 5

Closed

Deadline 5

Deadline for receipt of:

• Responses to the ExA’s second written questions

• Comments on the Applicant’s revised draft DCO

• Any other information requested by the ExA under Rule 17 of the EPR

25 October 2016 - ISH on environmental matters

Closed

ISH on environmental matters

25 October 2016 - Compulsory Acquisition Hearing

Closed

Compulsory Acquisition Hearing

26 October 2016 - ISH on the draft DCO

Closed

ISH on the draft DCO

8 November 2016 - Deadline 6

Closed

Deadline 6

Deadline for receipt of:

• Post-hearing documents including any written summary of an oral case put at any hearing and any documents/amendments requested by the ExA

• Applicant’s revised draft DCO

• Comments on responses to the ExA’s second written questions

• Any other information requested by the ExA under Rule 17 of the EPR

17 November 2016 - Publication by the ExA of The ExA’s draft DCO and RIES

Closed

Publication by the ExA of:

• The ExA’s draft DCO (if required to facilitate examination)

• Report on the Implications for European Sites (RIES)

8 December 2016 - Deadline 7

Closed

Deadline 7

Deadline for receipt of:

• Comments on the RIES

• Comments on the ExA’s draft DCO

• Any other information requested by the ExA under Rule 17 of the EPR

15 December 2016 - Deadline 8

Closed

Deadline 8

Deadline for receipt of:

• Responses to comments on the ExA’s draft DCO

• Responses to comments on the RIES

• Any other information requested by the ExA under Rule 17 of the EPR

• Comments on any information submitted at deadline 7

28 December 2016 - Close of Examination

Closed

The ExA is under a duty to complete the examination of the application by the end of the period of 6 months beginning with the day after the close of the Preliminary Meeting.