Progress Power Station Examination timetable

The examination timetable shows the dates of events and deadlines for submissions.

If you have registered to have your say, you can do this in the examination stage.

The examination stage

The examination opened on 24 July 2014

The examination closed on 24 January 2015

Upcoming deadlines and events

There are no deadlines and events

Past deadlines and events

24 July 2014 - Preliminary Meeting

Closed

A procedural meeting to discuss the draft examination timetable for the proposed Progress Power Station application. Registration begins at 0930, the Preliminary Meeting commences at 1000.

4 August 2014 - Deadline 1

Closed

Issue by ExA of: • Examination timetable • ExA first written questions and requests for Statements of Common Ground

14 August 2014 - Deadline 2

Closed

Deadline 1 Deadline for statutory parties to inform the Examining Authority of a wish to be considered as an interested party. Request or receipt of notification (using the prescribed form) by persons within certain categories of interests in the land of a wish to become an interested party

4 September 2014 - Deadline 3

Closed

Deadline 2 Deadline for receipt by the ExA of: • Comments on relevant representations (RRs) • Summaries of all RRs exceeding 1500 words • Written representations (WRs) by all interested parties • Summaries of all WRs exceeding 1500 words • LIR from any local authorities • Statements of Common Ground requested by ExA • Responses to ExA’s first written questions • Notification of wish to speak at a compulsory acquisition hearing • Notification of wish to make oral representations at the first issue specific hearing on the local impact of the project • Notification by interested parties of wish to be heard at an open floor hearing • Notification by interested parties of wish to attend any accompanied site visits and any representations relating to locations to view at or near the site and in the surrounding area • Comments on any other / additional submissions received prior to the preliminary meeting • Submissions from interested parties recommending itinerary items for the accompanied site visit • Any further information requested by the ExA for this deadline

15 September 2014 - Deadline 4

Closed

Notification by ExA of date, time and place for: • First issue specific hearing to be held on the local impact of the project • Any accompanied site visit(s) • Any open-floor hearing

2 October 2014 - Deadline 5

Closed

Deadline 3 Deadline for receipt by the ExA of: • Comments on WRs and responses to comments on RRs • Comments on LIRs • Comments on Statements of Common Ground • Comments on responses to ExA’s first written questions • Revised DCO from the applicant • Any further information requested by the ExA for this deadline

14 October 2014 - Site Visit (Accompanied)

Closed

Date reserved for ExA’s inspection of site(s) in the company of interested parties (am)

15 October 2014 - Open Floor Hearing 1

Closed

Date reserved for a the first open floor hearing (pm)

15 October 2014 - Open Floor Hearing 2

Closed

?

16 October 2014 - Issue Specific Hearing 1

Closed

Dates reserved for issue specific hearing on the local impact of the project, including the first draft DCO hearing

16 October 2014 - Issue Specific Hearing 2

Closed

?

17 October 2014 - Issue Specific Hearing 3

Closed

Dates reserved for issue specific hearing on the local impact of the project, including the first draft DCO hearing

17 October 2014 - Issue Specific Hearing 4

Closed

?

24 October 2014 - Deadline 6

Closed

Deadline 4 Deadline for receipt by ExA of: • All post hearing documents (including any revised DCO from the applicant) • Any updated Statements of Common Ground • All written summaries of oral cases made at the open-floor and issue specific hearings • Notification by interested parties of wish to make oral representations at the second issue specific hearing on the draft Development Consent Order (DCO) and any related LIR matters • Any further information requested by the ExA for this deadline

27 October 2014 - Deadline 7

Closed

Issue by ExA of: • ExA’s second round of written questions and any further request for Statements of Common Ground • Notification by the ExA of the time and place for the second issue specific hearing relating to the draft DCO and any related LIR matters • Notification by the ExA of the time and place for compulsory acquisition hearings

17 November 2014 - Deadline 8

Closed

Deadline 5 Deadline for receipt of: • Responses to ExA’s second written questions and any further requests for Statements of Common Ground • Comments on written summaries of case put at the first issue specific and open floor hearings

2 December 2014 - Deadline 9

Closed

Deadline 6 Deadline for receipt of: • Comments on responses to ExA’s second round of written questions and any further Statements of Common Ground

9 December 2014 - Compulsory Acquisition Hearing

Closed

Date reserved for compulsory acquisition hearings and any other issue specific hearing

10 December 2014 - Issue Specific Hearing 5

Closed

Dates reserved for issue specific hearing(s) including second DCO hearing and LIR issues

11 December 2014 - Issue Specific Hearing 6

Closed

Dates reserved for issue specific hearing(s) including second DCO hearing and LIR issues

15 December 2014 - Deadline 10

Closed

Issue by ExA of: The Report on the Implications for European Sites (RIES)

19 December 2014 - Deadline 11

Closed

Deadline 7 Deadline for the receipt of: • Optional written summary of the case put orally at the issue specific hearing on draft DCO and any related LIR matters • Optional written summary of the case put orally at compulsory acquisition and any other hearings held • Any proposed amendments to the draft DCO

13 January 2015 - Deadline 12

Closed

Deadline 8 Deadline for receipt of: • Comments on written summaries of case put at the second issue specific hearing, compulsory acquisition and any other hearings held • Comments on any proposed amendments to the draft DCO • Comments on the RIES