Ferrybridge Multifuel 2 (FM2) Power Station Examination timetable

The examination timetable shows the dates of events and deadlines for submissions.

If you have registered to have your say, you can do this in the examination stage.

The examination stage

The examination opened on 4 December 2014

The examination closed on 29 April 2015

Upcoming deadlines and events

There are no deadlines and events

Past deadlines and events

4 December 2014 - Preliminary Meeting

Closed

Ferrybridge preliminary meeting

18 December 2014 - Deadline 1

Closed

Issue by ExA of: • ExA’s first written questions

22 January 2015 - Deadline 2

Closed

Deadline 1 Deadline for receipt by the ExA of: • Comments on relevant representations (RRs) • Summaries of all RRs exceeding 1500 words • Written representations (WRs) by all interested parties • Summaries of all WRs exceeding 1500 words • Local Impact Report from any local authorities • Updated Statements of Common Ground (SoCG) and SoCG requested by ExA – see Annex C • Responses to ExA’s first written questions • Submissions from interested parties recommending items for the itinerary for the accompanied site visit

Notifications • Notification by interested parties of wish to speak Open floor hearing. • Notification by interested parties of their intention to attend the accompanied site visit.

17 February 2015 - Deadline 3

Closed

Deadline 2 Deadline for receipt by the ExA of: • Comments on WRs • Responses to comments on RRs • Comments on Local Impact Reports • Comments on responses to ExA’s first written questions • Any revised draft DCO from applicant • Any other information requested by the ExA

20 February 2015 - Deadline 4

Closed

Issue by ExA of: • Notification of dates for hearings and accompanied site visit

Agendas for each hearing will be published on the project page of the National Infrastructure pages of the Planning Portal website five calendar days before the hearing is due to take place but will not otherwise be published or circulated.

12 March 2015 - Deadline 5

Closed

Deadline 3 Deadline for receipt by the ExA of: • Responses to comments on WRs • Responses to comments on Local Impact Reports • Comments on any revised draft DCO from applicant • Comments on any other information submitted at Deadline 2 • Request to be heard at any issue specific hearing • Any other information requested by the ExA

17 March 2015 - Deadline 6

Closed

Date reserved for accompanied site visit Date reserved for open floor hearing

17 March 2015 - Site Visit (Accompanied)

Closed

Accompanied site visit 09.00 Knottingley Town Hall

17 March 2015 - Open Floor Hearing

Closed

Open Floor Hearing - 17 March 2015 - 15.00 - Knottingley Town Hall

18 March 2015 - Deadline 7

Closed

Date reserved for hearing on draft DCO/ any other issue-specific hearing

18 March 2015 - Issue Specific Hearing

Closed

ISH DCO Hearing

19 March 2015 - Deadline 8

Closed

Date reserved for issue-specific hearings

2 April 2015 - Deadline 9

Closed

Deadline 4 Deadline for receipt of: • Applicant’s revised draft DCO • Written summaries of oral cases put at hearings • Any information requested by the ExA at hearings • Any other information requested by the ExA • Comments on any other information submitted at Deadline 3

17 April 2015 - Deadline 10

Closed

Deadline 5 Deadline for receipt of: • Comments on applicant’s revised draft DCO • Any other information requested by the ExA for this deadline • Comments on any other information submitted at Deadline 4

4 June 2015 - Deadline 11

Closed

The ExA is under a duty to complete the examination of the application by the end of the period of 6 months beginning with the day after the close of the Preliminary Meeting.