14 April 2020
A Decision Letter from the Department for Business, Energy and Industrial Strategy (BEIS) regarding a Non-Material Change application has been published.
5 November 2019
22 October 2019
The deadline for receipt of representations relating to the application for a non-material change has been extended until 4 November 2019.
If you wish to make a representation, this should be emailed to MillbrookPower@planninginspectorate.gov.uk
or posted to: National Infrastructure, The Planning Inspectorate, Temple Quay House, 2 The Square, Bristol BS1 6PN
If you wish to make a representation, this should be emailed to MillbrookPower@planninginspectorate.gov.uk
or posted to: National Infrastructure, The Planning Inspectorate, Temple Quay House, 2 The Square, Bristol BS1 6PN
26 September 2019
An application for a non-material change to the Millbrook Gas Fired Generating Station Development Consent Order 2019 has been made by Millbrook Power Limited
If you wish to make a representation, this should be emailed to MillbrookPower@planninginspectorate.gov.uk
or posted to: National Infrastructure, The Planning Inspectorate, Temple Quay House, 2 The Square, Bristol BS1 6PN
The deadline for receipt of representations is 28 October 2019.
If you wish to make a representation, this should be emailed to MillbrookPower@planninginspectorate.gov.uk
or posted to: National Infrastructure, The Planning Inspectorate, Temple Quay House, 2 The Square, Bristol BS1 6PN
The deadline for receipt of representations is 28 October 2019.
13 March 2019
The Secretary of State has granted development consent for this application. For further information, please refer to the following decision documentation:
Secretary of State Decision Letter
Development Consent Order as Made by the Secretary of State
Regulation 23 Notice – Notification of Decision Letter
Recommendation Report
Secretary of State Decision Letter
Development Consent Order as Made by the Secretary of State
Regulation 23 Notice – Notification of Decision Letter
Recommendation Report
13 March 2019
Decision made by the Secretary of State
13 December 2018
Recommendations given by the Planning Inspectorate
24 August 2018
The submissions for deadline 7 have now been published.
1 August 2018
The responses received for Deadline 6 (31 July 2018) have now been published.
16 July 2018
The responses received for Deadline 5 (11 July 2018) have now been published.
A Rule 17 Letter inviting Interested Parties to comment on proposed changes to the application has also been published, with a deadline for replies of 31 July 2018.
A Rule 17 Letter inviting Interested Parties to comment on proposed changes to the application has also been published, with a deadline for replies of 31 July 2018.
15 June 2018
The responses received for Deadline 4 (14 June 2018) have now been published.
5 June 2018
The Examining Authority has decided that the Issue Specific Hearings scheduled to take place (if required) on the 4 and 5 July are now not required.
31 May 2018
The ExA’s Second Written Questions have been published. Deadline for responses is Thursday 14 June 2018.
18 May 2018
Submissions for Deadline 3 have been published.
24 April 2018
The Accompanied Site Inspection Itinerary and Agendas for Hearings in May 2018 have been published. Please note that the date reserved for the Open Floor Hearing on the evening of Tuesday 1 May 2018 is not taking place as we have received no requests for one to be held.
19 April 2018
Submissions for Deadline 2 (17 April 2018) have been published.
28 March 2018
Submissions for Deadline 1 (27 March 2018) have been published.
20 March 2018
The Examination Timetable (Rule 8 letter) has been sent to Interested Parties.
Procedural decision following Preliminary Meeting.
14 March 2018
Audio recordings of the Preliminary Meeting and Issue Specific Hearing on draft DCO on 13 March have now been published.
13 March 2018
Preliminary Meeting takes place
13 March 2018
Examination begins
12 February 2018
The notification of Preliminary Meeting (Rule 6 letter) has been sent.
The letter also includes the draft Examination Timetable and Initial Assessment of Principal Issues.
23 January 2018
Relevant representations published on the website
19 January 2018
Registration of interested parties closes
20 December 2017
Notice of the Appointment of Examining Authority has been published.
28 November 2017
Registration of interested parties begins
20 November 2017
The application has been accepted for examination
24 October 2017
This application was received by the Planning Inspectorate on Monday 23 October 2017.
The application documents will be made available if the application is accepted for examination.
It is for the applicant to decide whether or not application documents can be published upon submission (see DCLG guidance on the pre-application process).
The application documents will be made available if the application is accepted for examination.
It is for the applicant to decide whether or not application documents can be published upon submission (see DCLG guidance on the pre-application process).
23 October 2017
Application received by the Planning Inspectorate