Skip to main content
Dod o hyd i Brosiect Seilwaith Cenedlaethol

Gwasanaeth beta yw hwn - bydd eich adborth yn ein helpu i'w wella.

Norfolk Vanguard Amserlen yr archwiliad

Mae amserlen yr archwiliad yn dangos dyddiadau digwyddiadau a therfynau amser ar gyfer cyflwyniadau.

Os ydych wedi cofrestru i leisio'ch barn, gallwch wneud hyn yn ystod y cam archwilio.

Y cam archwilio

Agorodd yr archwiliad ar 10 December 2018

Caeodd yr archwiliad ar 10 June 2019

Terfynau amser a digwyddiadau i ddod

Nid oes unrhyw derfynau amser neu ddigwyddiadau

Terfynau amser a digwyddiadau blaenorol

10 Rhagfyr 2018 - Preliminary Meeting

Caeedig

Preliminary Meeting

10 Rhagfyr 2018 - Open Floor Hearing 1

Caeedig

Open Floor Hearing

16 Ionawr 2019 - Deadline 1

Caeedig

Deadline 1 Deadline for receipt of: • Comments on Relevant Representations (RRs) • Summaries of all RRs exceeding 1500 words • Written Representations (WRs) • Summaries of all WRs exceeding 1500 words • Local Impact Reports from any local authorities • Statements of Common Ground (SoCG) requested by the ExA • Statement of Commonality of SoGCs • Applicant’s Guide to the Application • The Compulsory Acquisition (CA) schedule • Responses to the ExA’s Written Questions • Comments on updated application documents including specific comments upon drafting of the DCO • Comments on any additional submissions • Responses to further information requested by the ExA • Notification by Statutory Parties and certain Local Authorities who wish to be considered as an Interested Party • Notification of wish to speak at a Compulsory Acquisition Hearing (CAH) • Notification of wish to speak at Open Floor Hearing (OFH) • Notification of wish to make oral representations at the Issue Specific Hearing on the draft Development Consent Order (DCO) • Notification of wish to make oral representations at the Issue Specific Hearing on Environmental matters • Notification of wish to attend an Accompanied Site Inspection (ASI), suggested locations and justifications • Notification of wish to have future correspondence electronically

30 Ionawr 2019 - Deadline 2

Caeedig

Deadline 2 Deadline for receipt by the ExA of: • Comments on WRs and responses to comments on RRs • Comments on Local Impact Reports • Comments on responses to the ExA’s Written Questions • Revised draft DCO from Applicant • Responses to further information requested by the ExA

5 Chwefror 2019 - Issue Specific Hearing 1

Caeedig

Issue Specific Hearing into onshore environmental matters: to include all environmental and amenity matters

6 Chwefror 2019 - Issue Specific Hearing 2

Caeedig

Issue Specific Hearing into offshore environmental matters: to include offshore ecology and processes

6 Chwefror 2019 - Open Floor Hearing 2

Caeedig

Open Floor Hearing

7 Chwefror 2019 - Issue Specific Hearing 3

Caeedig

Issue Specific Hearing into the draft DCO

14 Chwefror 2019 - Deadline 3

Caeedig

Deadline 3 • Post hearing submissions including written submissions of oral cases • Responses to further information requested by the ExA

27 Chwefror 2019 - Publication by the ExA

Caeedig

Publication by the ExA of: • The ExA's Further Written Questions (if required)

13 Mawrth 2019 - Deadline 4

Caeedig

Deadline 4 Deadline for receipt of: • Responses to the ExA’s Further Written Questions (if required) • Applicant’s revised draft DCO • Updated SoCGs • Updated Statement of Commonality of SoCGs • Applicant’s updated Guide to the Application • Responses to further information requested by the ExA

20 Mawrth 2019 - Deadline 5

Caeedig

Deadline 5 • Comments on responses to ExA’s Further Written Questions (if required) • Responses to further information requested by the ExA

25 Mawrth 2019 - Accompanied Site Inspection

Caeedig

Accompanied Site Inspection to be held on Monday 25 March & Tuesday 26 March

26 Mawrth 2019 - Accompanied Site Inspection

Caeedig

Accompanied Site Inspection to be held on Monday 25 March & Tuesday 26 March

27 Mawrth 2019 - Issue Specific Hearing 4

Caeedig

Date reserved to hold an Issue Specific Hearing into environmental matters

28 Mawrth 2019 - Issue Specific Hearing 5

Caeedig

Issue Specific Hearing into the draft DCO

28 Mawrth 2019 - Compulsory Acquisition Hearing

Caeedig

Compulsory Acquisition Hearing

29 Mawrth 2019 - Compulsory Acquisition Hearing 2

Caeedig

Compulsory Acquisition Hearing NB - if matters are concluded on the afternoon of Thursday 28 March then the hearing on Friday 29 March will not be required. Therefore any party that wishes to attend the Compulsory Acquisition Hearing should attend by 3:00pm on Thursday 28 March 2019.

5 Ebrill 2019 - Deadline 6

Caeedig

Deadline 6 Deadline for receipt of: • Responses to further information requested by the ExA • Post hearing submissions including written submissions of oral case

24 Ebrill 2019 - Issue Specific Hearing 6

Caeedig

Issue Specific Hearing into Environmental Matters - to conclude no later than 5pm

24 Ebrill 2019 - Open Floor Hearing 3

Caeedig

Open Floor Hearing - to conclude no later than 9pm

25 Ebrill 2019 - Issue Specific Hearing 7

Caeedig

Issue Specific Hearing on the draft Development Consent Order

2 Mai 2019 - Deadline 7

Caeedig

Deadline 7 Deadline for receipt of: • Updated SoCGs • Updated Statement of Commonality of SoCGs • Applicant’s updated Guide to the Application • Responses to further information requested by the ExA • Post hearing submissions (if required)

9 Mai 2019 - Publication by the ExA of

Caeedig

Publication by the ExA of: • The Report on the Implications of European Sites (RIES) • The ExA's draft DCO schedule of changes (if required)

21 Mai 2019 - Issue by the ExA of

Caeedig

Time reserved by the ExA of: • Any further information requests under Rule 17 (if required)

30 Mai 2019 - Deadline 8

Caeedig

Deadline 8 Deadline for receipt of: • Comments on the RIES • Comments on the ExA’s draft DCO schedule of changes (if required) • Final updated version of the Book of Reference • Applicant’s final guide to application document • Final CA Schedule • Final SoCGs • Final Statement of Commonality of SoCGs • Responses to further information requested by the ExA • Applicant’s final updated Guide to the Application • Final DCO to be submitted by the Applicant in the SI template with the SI template validation report

6 Mehefin 2019 - Deadline 9

Caeedig

Deadline 9 Deadline for the receipt of: • Responses to comments on the RIES • Responses to comments on ExA’s draft DCO schedule of changes