Skip to main content
Find a National Infrastructure Project

This is a beta service - your feedback will help us to improve it

Back

All project updates

17 July 2024

The Secretary of State for Energy Security and Net Zero has made a decision (PDF, 118KB) to approve the Version 2 Benthic Implementation and Management Plan, as required by Part 3 of Schedule 17 of the Development Consent Order (PDF, 3MB).

29 April 2024

The Marine Management Organisation (PDF, 391MB) and Natural England (PDF, 104KB) responses to the Benthic Implementation and Monitoring Plan (PDF, 8MB) and associated documents have now been published

28 March 2024

The Applicant has submitted the Benthic Implementation and Monitoring Plan (PDF, 8MB) and associated documents to the Secretary of State for Energy Security and Net Zero for her consideration. The Secretary of State has invited the Marine Management Organisation and Natural England to comment on the Plan, in accordance with the Norfolk Boreas and Norfolk Vanguard Offshore Wind Farm Orders. The deadline for response is 23:59 on Friday 19 April 2024.

16 January 2024

On 13 June 2022 the Marine Management Organisation (MMO) received a request from Norfolk Vanguard Offshore Wind Farm limited, to vary the Deemed Marine Licences (DML) contained within Schedules 9 and 10 of Norfolk Vanguard Offshore Wind Farm Order 2022 (PDF, 3MB).

The MMO has now completed its consideration of the request and, in exercise of the powers conferred by section 72(3)(d) of the Marine and Coastal Access Act 2009, has determined to make the variations as detailed in the documentation published on the MMO website: Norfolk Vanguard Offshore Wind Farm Order 2022 - GOV.UK (www.gov.uk)

13 December 2023

A Decision Letter (PDF,183KB) and Amendment Order (PDF, 76KB) have been issued by the Department of Energy Security and Net Zero to make a change that is not material to the Norfolk Vanguard Offshore Wind Farm Order 2022

30 November 2023

Further Representations received in response to the application for a non-material change to the Norfolk Vanguard Offshore Wind Farm Development Consent Order 2022 have been published.

1 August 2023

The responses to the Secretary of State's letter of 21 July 2023 have been published.(PDF, 1 MB)


The Secretary of State continues to invite representations on all the information provided (PDF, 150 KB), including the latest responses (PDF, 1 MB).


The deadline for receipt of representations remains 11:59pm on Tuesday 29 August 2023.

21 July 2023

The Secretary of State for Energy Security and Net Zero has today written to the Applicant regarding several points of clarification (PDF, 150 KB). The deadline for response is 23:59 on 28 July 2023.

6 July 2023

An application for a non-material change to Norfolk Vanguard Offshore Wind Farm Development Consent Order 2022 has been made by Norfolk Vanguard Ltd. and Norfolk Vanguard East Ltd.

If you wish to make a representation, this should be emailed to NorfolkVanguard@planninginspectorate.gov.uk or posted to:

National Infrastructure
The Planning Inspectorate
Temple Quay House
2 The Square
Bristol BS1 6PN

The deadline for receipt of representations is 11:59pm on Tuesday 29 August 2023.

21 June 2023

The Secretary of State for Energy Security and Net Zero has issued a letter (PDF 139KB) confirming those parties that the Applicant should consult regarding a proposed non-material change (PDF 436KB) relating to the Norfolk Vanguard Offshore Wind Farm Order 2022.

6 June 2023

The responses to the Secretary of State’s consultation in relation to the Benthic Implementation and Monitoring Plan and associated documents have been published.

19 May 2023

The Applicant has submitted the Benthic Implementation and Monitoring Plan and associated documents to the Secretary of State for Energy Security and Net Zero for his consideration. The Secretary of State has invited the Marine Management Organisation and Natural England to comment on the Plans, in accordance with the Norfolk Boreas and Norfolk Vanguard Offshore Windfarm Orders.

Following a request for an extension by Natural England (PDF, 119KB), the deadline for response is 23:59 on Friday 26 May 2023.

4 May 2023

The Applicant has submitted the Benthic Implementation and Monitoring Plan and associated documents to the Secretary of State for Energy Security and Net Zero for his consideration. The Secretary of State has invited the Marine Management Organisation and Natural England to comment on the Plans, in accordance with the Norfolk Boreas and Norfolk Vanguard Offshore Windfarm Orders. The deadline for response is 23.59 on Wednesday 17 May 2023.

6 February 2023

The Secretary of State has issued Approval Letters on 26 January 2023 for the Kittiwake Implementation and Monitoring Plan (PDF, 125 KB) and the Lesser Black-Backed Gull Implementation and Monitoring Plan (PDF, 126 KB), pursuant to Schedule 17, Parts 1 and 2 of the Norfolk Vanguard Offshore Wind Farm Order 2021.

2 December 2022

Responses to the Applicant’s Lesser Black-Backed Gull Implementation and Monitoring Plan (PDF, 104 KB) (PDF, 129 KB) and the Kittiwake Implementation and Monitoring Plan (PDF, 145 KB) (PDF, 130 KB) have been published.

18 November 2022

The Applicant has submitted the Kittiwake Implementation and Monitoring Plan and associated documents  to the Secretary of State for Business, Energy and Industrial Strategy for his consideration. The Secretary of State has invited East Suffolk Council, Great Yarmouth Borough Council and Natural England to comment on the Plans, in accordance with the Norfolk Boreas and Norfolk Vanguard Offshore Windfarm Orders. The deadline for response is 23.59 on Wednesday 30 November 2022.

10 November 2022

The Applicant has submitted the Lesser Black-Backed Gull Implementation and Monitoring Plan and associated documents to the Secretary of State for Business, Energy and Industrial Strategy for his consideration. The Secretary of State has invited East Suffolk Council, Great Yarmouth Borough Council and Natural England to comment on the Plans, in accordance with the Norfolk Boreas and Norfolk Vanguard Offshore Windfarm Orders. The deadline for response is 23.59 on Thursday 24th November 2022.

30 September 2022

A Decision Letter (PDF, 183KB) and Amendment Order (PDF, 45KB) have been issued by the Department for Business, Energy and Industrial Strategy to make a change that is not material to the Norfolk Vanguard Offshore Wind Farm Order 2022.

The Secretary of State has issued an Approval Letter (PDF, 117 KB) on 27 September 2022 for the Plans of Work for the Kittiwake Steering Group, the Lesser-Black Backed Gull Steering Group, and the Benthic Steering Group, pursuant to Schedule 19, Parts 1 to 3 of the Norfolk Vanguard Offshore Wind Farm Order 2021.

8 September 2022

Representations received in response to the application for a non-material change to the Norfolk Vanguard Development Consent Order have been published.

A Correction Order (PDF, 43 KB) and a Correction Notice (PDF, 124 KB) for the Norfolk Vanguard Offshore Wind Farm Order 2022 have been published. The Correction Order came into force on 7 September 2022

29 July 2022

Representations received in response to the application for a non-material change to the Norfolk Vanguard Development Consent Order have been published.

14 June 2022

An application for a non-material change to the Norfolk Vanguard Development Consent Order has been made by Norfolk Vanguard Limited.

If you wish to make a representation, this should be emailed to NorfolkVanguard@planninginspectorate.gov.uk or posted to:

National Infrastructure
The Planning Inspectorate
Temple Quay House
2 The Square
Bristol BS1 6PN

The deadline for receipt of representations is 24 July 2022.

11 February 2022

The Secretary of State has today granted development consent for this application. For further information please refer to the following documentation:

Planning Inspectorate Notification of Decision Letter (PDF, 110 KB)
Secretary of State Decision Letter (PDF, 569 KB)
Development Consent Order as made by the Secretary of State (PDF, 3MB)
Examining Authority's Recommendation Report (PDF, 7MB)
Regulation 31 Notice (PDF, 64 KB)
Habitats Regulations Assessment (PDF, 2MB)

11 February 2022

Decision made by the Secretary of State

8 December 2021

The Applicant has made a further submission to the Secretary of State (PDF, 1 MB) in light of comments submitted by Interested Parties.

26 October 2021

Further to the Secretary of State’s letter of 11 October 2021 (PDF, 178KB) requesting information, and in response to a request from an Interested Party, the Secretary of State has agreed to extend the date for responses (PDF, 114KB) to 23.59 on Friday 19 November 2021.

 

11 October 2021

The Secretary of State has issued a further letter requesting information from the Applicant, Natural England and Interested Parties. Responses are requested by 23:59 on 8 November 2021

26 August 2021

The Applicant's response to the Secretary of State's letter of 11 August 2021 (PDF, 154 KB) has been published. The Secretary of State is reviewing the response.

11 August 2021

Responses to the Secretary of State's consultation letter of 5 July 2021 have been published.

The Secretary of State has issued a further letter requesting information from the Applicant (PDF, 154 KB). Responses are requested by 23.59 on Wednesday 25 August 2021.

5 July 2021

The Secretary of State has requested additional information from the Applicant following the responses received to the Secretary of State’s letter inviting comments from all Interested Parties.

The deadline for the Applicant to comment is 23.59 on 2 August 2021.

30 April 2021

Following the High Court’s decision to quash the Norfolk Vanguard Offshore Wind Farm Order 2020, a letter inviting comments (PDF, 207 KB) from all Interested Parties has been published. The deadline for comments is 23.59 on 20 May 2021.

11 March 2021

Following an Order of the High Court made on 18 February 2021, the decision of the Secretary of State dated 1 July 2020 to grant the application by Norfolk Vanguard Limited for development consent for the proposed Norfolk Vanguard Offshore Wind Farm has been quashed. The Secretary of State will now re-determine that application. Further details on the re-determination process will be published here in due course.

24 February 2021

Following an Order of the High Court made on 18 February 2021, the decision of the Secretary of State dated 1 July 2020 to grant the application by Norfolk Vanguard Limited for development consent for the proposed Norfolk Vanguard Offshore Wind Farm has been quashed. The Secretary of State is considering the judgment and will decide on the next steps in due course.

18 February 2021

Following an Order of the High Court made on 18 February 2021 the decision of the Secretary of State dated 1 July 2020 to grant the application by Norfolk Vanguard Limited for development consent for the proposed Norfolk Vanguard Offshore Wind Farm has been quashed. The Secretary of State must now re-determine that application. Further details on the re-determination process will be published here in due course.

1 July 2020

The Secretary of State has granted development consent for this application. For further information please refer to the following decision documentation:

Planning Inspectorate Notification of Decision Letter
Secretary of State Decision Letter
Examining Authority Recommendation Report
Development Consent Order as made by the Secretary of State
Habitats Regulation Assessment
Regulation 31 Notice

NB Following an Order of the High Court made on 18 February 2021, the decision of the Secretary of State dated 1 July 2020 to grant the application by Norfolk Vanguard Limited for development consent for the proposed Norfolk Vanguard Offshore Wind Farm has been quashed. Consequently, only the link to the Examining Authority’s Report will still function.

1 June 2020

The Secretary of State has decided to re-set the statutory deadline for this application to 1 July 2020. A statement confirming the new deadline for a decision will be made to the House of Commons and House of Lords in accordance with section 107(7) of the Planning Act 2008 as soon as possible.

1 May 2020

Comments from Interested Parties on the responses to the Secretary of State’s consultation letter of 6 December 2019 have now been published.

27 March 2020

The Secretary of State has received responses from the Applicant and other Interested Parties to his consultation letter dated 6 December 2019 by the 28 February 2020 deadline. The Secretary of State considers the information provided by the Applicant in response to those letters to contain new environmental information and invites comments from Interested Parties on the representations received. The new deadline for this is 27 April 2020.

10 March 2020

The Secretary of State has received responses from the Applicant and other Interested Parties to his consultation letter dated 6 December 2019 by the 28 February 2020 deadline. The Secretary of State considers the information provided by the Applicant in response to those letters to contain new environmental information and invites comments from Interested Parties on the representations received by 9 April 2020.

6 February 2020

A Written Ministerial Statement has been made announcing that the decision by the Secretary of State for Business, Energy and Industrial Strategy has been delayed until 1 June 2020.

11 December 2019

The Secretary of state for Business, Energy and Industrial Strategy has requested information and comments from Norfolk Vanguard Limited, Interested Parties and Other Parties on the Norfolk Vanguard Offshore Wind Farm.

The Secretary of State will be setting a new deadline for a decision. A statement confirming the new deadline for a decision will be made to the House of Commons and House of Lords in accordance with section 107(7) of the Planning Act 2008 as soon as possible once Parliament is in session.

10 September 2019

Recommendations given by the Planning Inspectorate

17 June 2019

The Examination closed at 11.59pm on 10 June 2019.

10 June 2019

The Submissions for Deadline 9 have now been published.

10 June 2019

The Examination closes at 23.59 on Monday 10 June 2019.

3 June 2019

The Submissions for Deadline 8 have now been published.

28 May 2019

A request for further information under Rule 17 has been sent to the Applicant.

22 May 2019

The Examining Authority's request for further information under Rule 17 has been published.

15 May 2019

The Applicant has submitted Additional Submissions which have been accepted at the discretion of the Examining Authority.

7 May 2019

The Submissions for Deadline 7 have now been published.

24 April 2019

A revised version of the draft Development Consent Order (Version 4) has been published. This was accepted at the discretion of the Examining Authority as an additional submission on 17 April 2019.

9 April 2019

The Submissions for Deadline 6 have now been published.

21 March 2019

The Submissions for Deadline 5 have now been published.

21 March 2019

The itinerary for the Accompanied Site Inspection scheduled for 25 & 26 March 2019 has now been published.

15 March 2019

The Submissions for Deadline 4 have been published.

 

27 February 2019

19 February 2019

The Submissions for Deadline 3 have now been published.

31 January 2019

28 January 2019

22 January 2019

Documents for Deadline 1 have been published.

19 December 2018

The Examination Timetable (Rule 8 letter) has been sent to Interested Parties.

Procedural decision following Preliminary Meeting.

13 December 2018

Audio recordings of the Preliminary Meeting and the Open Floor Hearing have been published.

10 December 2018

Preliminary Meeting takes place

10 December 2018

Examination begins

9 November 2018

The notification of Preliminary Meeting (Rule 6 letter) has been sent.

The letter also includes the draft Examination Timetable and Initial Assessment of Principal Issues.

21 September 2018

Relevant representations published on the website

16 September 2018

Registration of interested parties closes

3 August 2018

Registration of interested parties begins

24 July 2018

The application has been accepted for examination

28 June 2018

This application was received by the Planning Inspectorate on Tuesday 26 June 2018.

The applicant has agreed that all application documents can be published as soon as practicable to help everyone become familiar with the detail of what is being proposed in this application. The Planning Inspectorate will therefore make the application documents available as soon as practicable.

This provision is solely for the purpose of allowing more time to all those who wish to become familiar with the detail of what is being proposed ahead of the relevant representation period without lengthening the overall time required for the application process. There will be no opportunity at this stage to make comments on the application. However, if the application is accepted anyone interested in the application will be able to register and express their views during the relevant representation stage and the subsequent examination.

26 June 2018

Application received by the Planning Inspectorate