1. Section 51 advice
  2. Advice in detail

Advice to H Phoenix

Back to list

Enquiry

From
H Phoenix
Date advice given
5 December 2017
Enquiry type
Email

Please find attached my letter outlining my objections to Vattenfall's flawed proposal to put two huge substation at Necton/Ivy Todd in Norfolk. Please also find attached Necton Substation Action Group's objection document, which goes into wider detail. I look forward to hearing from you, thank you.

Advice given

Thank you for your email. As the project has not yet been submitted to the Planning Inspectorate (the Inspectorate) all responses to the Applicant’s consultation should be sent directly to them. We have no formal powers to intervene on consultees behalf therefore I would encourage you to contact the developer directly to make your concerns heard as the Applicant has a statutory duty to take your views into account. However, if you feel your comments are not being taken into account, I would advise you to write to your local authority and set out why you think the Applicant is failing to conduct its consultation properly. Your comments should be taken into account when the local authority sends the Inspectorate its comments on whether the Applicant has fulfilled its consultation duties. The local authority’s comments on the Applicant’s consultation will be taken into account when the Acceptance Inspector makes their decision whether to accept the application for Examination.

A copy of your correspondence has been placed on our records and will be presented to the Inspector at Acceptance, together with the application documents and local authorities’ comments on the Applicant’s consultation.

After the decision has been made regarding whether to accept the application for Examination all documents used to inform the decision will be published on our website. If the application for development consent is formally accepted you will be able to submit your views in relation to the project which will be considered by the Examining Authority during the Examination. The Inspectorate has published a series of advice notes which explain the Examination process, including information on how to get involved; of particular interest are advice notes 8.1 to 8.5. These are available at: https://infrastructure.planninginspectorate.gov.uk/legislation-and-advice/advice-notes

We have also published a Frequently Asked Questions document regarding Pre-application consultation and this can be viewed on our website here: https://infrastructure.planninginspectorate.gov.uk/wp-content/ipc/uploads/projects/General/General-Advice-00632-1-170702%20s47%20Community%20Consultation%20FAQ.pdf.

Attachments

View advice (PDF)

View advice (PDF)