Hornsea Project Three Offshore Wind Farm Examination timetable

The examination timetable shows the dates of events and deadlines for submissions.

If you have registered to have your say, you can do this in the examination stage.

The examination stage

The examination closed on 2 April 2019

Upcoming deadlines and events

There are no deadlines and events

Past deadlines and events

2 October 2018 - Preliminary Meeting

Closed

Preliminary Meeting

9 October 2018 - Procedural Decision 1

Closed

Issue by the ExA of: • Examination Timetable • The ExA’s Written Questions

7 November 2018 - Deadline 1

Closed

Deadline 1 Deadline for receipt of: • Applicant’s revised draft Development Consent Order (DCO) • Applicant’s Guide to the Application • Applicant’s Statement of Commonality of Statements of Common Ground (SoCG) • Applicant’s Compulsory Acquisition (CA) schedule • Comments on Relevant Representations (RRs) • Summaries of all RRs exceeding 1500 words • Written Representations (WRs) • Summaries of all WRs exceeding 1500 words • Local Impact Reports from any local authorities • Statements of Common Ground (SoCG) requested by the ExA • Responses to the ExA’s Written Questions • Comments on updated application documents • Comments on any additional submissions • Responses to further information requested by the ExA • Notification by Statutory Parties and certain Local Authorities who wish to be considered as an Interested Party • Notification of wish to speak at a Compulsory Acquisition Hearing (CAH) • Notification of wish to speak at an Open Floor Hearing (OFH) • Notification of wish to make oral representations at an Issue Specific Hearing • Notification of wish to attend an Accompanied Site Inspection (ASI), suggested locations and justifications • Notification of wish to have future correspondence electronically

21 November 2018 - Deadline 2

Closed

Deadline 2 Deadline for receipt by the ExA of: • Comments on WRs and responses to comments on RRs • Comments on Local Impact Reports • Comments on responses to the ExA’s Written Questions • Responses to further information requested by the ExA

3 December 2018 - Open Floor Hearing 1

Closed

Open Floor Hearing Date reserved to hold an OFH (if required) in Norwich

4 December 2018 - Issue Specific Hearing 1

Closed

Issue Specific Hearing (ISH1) ISH1 into alternatives/design flexibility (offshore and onshore); onshore ecology; navigation/other offshore operations

5 December 2018 - Issue Specific Hearing 2

Closed

Issue Specific Hearing (ISH2) ISH2 into offshore ecology

6 December 2018 - Issue Specific Hearing 3

Closed

Issue Specific Hearing (ISH3) ISH3 into the draft DCO

7 December 2018 - Issue Specific Hearing 4

Closed

Issue Specific Hearing (ISH4) ISH4 into other onshore matters

14 December 2018 - Deadline 3

Closed

Deadline 3 • Post hearing submissions including written submissions of oral cases • Comments on revised draft DCO • Responses to further information requested by the ExA

20 December 2018 - Procedural Decision 2

Closed

Publication by ExA of: • The ExA’s Further Written Questions (if required)

15 January 2019 - Deadline 4

Closed

Deadline 4 Deadline for receipt of: • Applicant’s revised draft DCO • Applicant’s updated Guide to the Application • Applicant’s updated Statement of Commonality of SoCG • Responses to the ExA’s Further Written Questions (if required) • Updated SoCG • Responses to further information requested by the ExA

23 January 2019 - Deadline 5

Closed

Deadline 5 • Comments on responses to ExA’s Further Written Questions (if required) • Responses to further information requested by the ExA

28 January 2019 - Accopmanied Site Inspection

Closed

Accompanied Site Inspection (ASI1) Date reserved to hold an ASI

28 January 2019 - Open Floor Hearing 2

Closed

Open Floor Hearing Date reserved to hold an OFH (if required) at location convenient to the northern part of the onshore cable route.

29 January 2019 - Issue Specific Hearing 5

Closed

Issue Specific Hearing (ISH5) Date reserved to hold an ISH into environmental matters (if required)

30 January 2019 - Issue Speciifc Hearing 6

Closed

Issue Specific Hearing (ISH6) Date reserved to hold an ISH into the draft DCO

31 January 2019 - Compulsory Acquisition Hearing 1

Closed

Compulsory Acquisition Hearing (CAH1) Date reserved to hold a CAH

1 February 2019 - Compulsory Acquisition Hearing 2

Closed

Compulsory Acquisition Hearing (if required)(CAH2) Date reserved to hold a CAH (if required)

8 February 2019 - Deadline 6

Closed

Deadline 6 Deadline for receipt of: • Post hearing submissions including written submissions of oral cases • Responses

21 February 2019 - Procedural Decision 3

Closed

Publication by the ExA of: • Report on the Implications for European Sites (RIES)

26 February 2019 - Procedural Decision 4

Closed

Publication by the ExA of: • The ExA’s draft DCO schedule of changes (if required)

5 March 2019 - Accompanied Site Inspection 2

Closed

Reserved for Accompanied Site Inspection (ASI2)

6 March 2019 - Issue Specific Hearing 7

Closed

ISH7 into offshore ecology

7 March 2019 - Issue Specific Hearing 8

Closed

ISH 8 into aviation, shipping and effects on oil and gas operations

8 March 2019 - Issue Specific Hearing 9

Closed

ISH9 - Part 1 into cumulative traffic impacts and related mitigation measures; Part 2 into the draft DCO

14 March 2019 - Deadline 7

Closed

Deadline 7 Deadline for receipt of: • Applicant’s updated Guide to the Application • Applicant’s updated Statement of Commonality of SoCGs • Comments on the ExA’s draft DCO schedule of changes (if required) • Comments on the RIES • Updated SoCGs • Responses to further information requested by the ExA • Post hearing submissions (if required)

19 March 2019 - Procedural Decision 5

Closed

Time reserved for issue by the ExA of: • Any further information requests under Rule 17 (if required)

22 March 2019 - Deadline 8

Closed

Deadline 8 Deadline for receipt of: • Written Representations • Comments on responses to written questions (if required) • Notification of wish to be heard at a Compulsory Acquisition Hearing or Open Floor Hearing

25 March 2019 - Open Floor Hearing 3

Closed

Open Floor Hearing (evening)

26 March 2019 - Deadline 9

Closed

Deadline 9 Deadline for receipt of: • Applicant’s final updated Guide to the Application • Final DCO to be submitted by the Applicant in the SI template with the SI template validation report • Applicant’s final CA Schedule • Applicant’s final updated version of the Book of Reference • Applicant’s final Statement of Commonality of SoCGs • Responses to comments on the ExA’s draft DCO schedule of changes (if required) • Responses to comments on the RIES • Final SoCGs • Responses to further information requested by the ExA

26 March 2019 - Issue Specific Hearing

Closed

Further Issue Specific Hearing and further Compulsory Acquisition Hearing

1 April 2019 - Deadline 10

Closed

Deadline 10 Deadline for receipt of: • Comments on Written Representations • Comments on responses to Written Questions (if required) • Summary of Oral Submissions at Hearings

2 April 2019 - Close of Examination

Closed

The ExA is under a duty to complete the examination of the application by the end of the period of 6 months beginning with the day after the close of the Preliminary Meeting.