Tees CCPP Examination timetable

The examination timetable shows the dates of events and deadlines for submissions.

If you have registered to have your say, you can do this in the examination stage.

The examination stage

The examination opened on 10 April 2018

The examination closed on 10 October 2018

Upcoming deadlines and events

There are no deadlines and events

Past deadlines and events

10 April 2018 - Preliminary Meeting

Closed

Preliminary Meeting

10 April 2018 - Issue Specific Hearing on the Scope of the Application

Closed

Issue Specific Hearing on the Scope of the Application

24 April 2018 - Deadline 1

Closed

Deadline 1

Deadline for the receipt of:  Notification of wish to speak at a subsequent Issue Specific Hearing  Notification of wish to speak at an Open Floor Hearing  Notification of wish to attend an Accompanied Site Inspection(ASI)suggested locations and justifications  Notification by statutory parties of wish to be considered an Interested Party  Notification of wish to have future correspondence electronically  Comments on any updates to Application Documents submitted by the Applicant before or at the Preliminary Meeting(PM)  Submission by the Applicant of revised Habitats Regulation Assessment (HRA) Matrices

14 May 2018 - Any notifications of hearings

Closed

Any notification of hearing

16 May 2018 - Deadline 2

Closed

Deadline 2

Deadline for receipt of:  Comments on Relevant Representations (RRs)  Summaries of all RRs exceeding 1500 words  Written Representations (WRs)  Summaries of all WRs exceeding 1500 words  Local Impact Reports from any local authorities  Statements of Common Ground (SoCG) requested by the ExA – see Annex B  Statement of Commonality for SoCG  Responses to the ExA’s Written Questions  Post hearing submissions including written submissions of oral case  Responses to any additional information requested by the ExA

29 May 2018 - Deadline 3

Closed

Deadline 3

Deadline for receipt by the ExA of:  Comments on WRs and responses to comments on RRs  Comments on Local Impact Reports  Comments on responses to the ExA’s Written Questions  Responses to any additional information requested by the ExA

12 June 2018 - Accompanied Site Inspection

Closed

Accompanied Site Inspection

13 June 2018 - Issue Specific Hearing on Environmental Matters

Closed

Issue Specific Hearing on Environmental Matters Air Quality  Landscape and Visual Impacts  Construction and Traffic and Transport Impacts

13 June 2018 - Open Floor Hearing

Closed

Open Floor Hearing (if requested)

14 June 2018 - Issue Specific Hearing on the draft Development Consent Order (DCO)

Closed

Issue Specific Hearing on the draft Development Consent Order (DCO)

6 July 2018 - Deadline 4

Closed

Deadline 4

Deadline for receipt of: Responses to any additional information requested by the ExA Comments on Post hearing submissions including written submissions of oral case Revised draft DCO from Applicant

10 July 2018 - Any notifications of hearings

Closed

Any notifications of hearings

24 July 2018 - The ExA’s Further Written Questions (if required)

Closed

The ExA’s Further Written Questions (ifrequired)

7 August 2018 - Deadline 5

Closed

Deadline 5

Deadline for receipt of: Responses to the ExA’s Further Written Questions (if required) Responses to any additional information requested by the ExA Comments on Applicant’s revised draft DCO (if required)

22 August 2018 - Deadline 6

Closed

Deadline 6

Deadline for receipt of: Post hearing submissions including written submissions of oral case Applicant’s revised DCO Responses to any additional information requested by ExA Comments on responses to further Written Questions, if required.

5 September 2018 - Report on the Implications for European Sites(RIES) (if required)

Closed

Report on the Implications for European Sites(RIES) (if required)

26 September 2018 - Deadline 7

Closed

Deadline 7

Deadline for receipt of: Comments on the RIES (if one was prepared) Responses to any additional information requested by ExA

3 October 2018 - Deadline 8

Closed

Deadline 8

Deadline for receipt of: Responses to comments on the RIES (if one was prepared) Responses to additional information requested by the ExA Final draft DCO to be submitted by the Applicant in the SI template with the SI template validation report Resubmission of final versions of updated application documents

10 October 2018 - Examination closed

Closed

Examination closed