Cleve Hill Solar Park Examination timetable

The examination timetable shows the dates of events and deadlines for submissions.

If you have registered to have your say, you can do this in the examination stage.

The examination stage

The examination opened on 30 May 2019

The examination closed on 30 November 2019

Upcoming deadlines and events

There are no deadlines and events

Past deadlines and events

30 May 2019 - Preliminary Meeting

Closed

Preliminary Meeting

7 June 2019 - Issue by the Examining Authority

Closed

Examination Timetable

7 June 2019 - Publication of

Closed

The Examining Authority's Written Questions

12 June 2019 - Deadline 1

Closed

Deadline 1 Deadline for receipt by the Examining Authority of: • Notification of wish to speak at a Compulsory Acquisition Hearing (CAH); • Notification of wish to speak at an Open Floor Hearing (OFH); • Notification of wish to attend the Accompanied Site Inspection (ASI); • Submission of suggested locations / sites for the Panel to include as part of the ASI including the issues to be observed there, information on whether the site can be accessed on public land and reasoning for each nominated site; • Applicant’s draft itinerary for the ASI to be held on Wednesday 24 July 2019; • Local Impact Reports (LIR) from Local Authorities.

26 June 2019 - Deadline 2

Closed

Deadline 2 Deadline for receipt by the ExA of: • Responses to the ExA’s Written Questions; • Written Representations (WRs); • Summaries of all WRs exceeding 1500 words; • Notification of wish to participate in Issue Specific Hearings; • Initial Statements of Common Ground requested by the ExA; • Comments on Relevant Representations (RRs); • Comments on the Applicant’s response to the Planning Inspectorate’s s51 advice [AS-001 to AS-010]; • An updated Guide to the Application; • The Compulsory Acquisition Schedule; • An updated version of the draft Development Consent Order (dDCO) in clean, tracked and word versions; • Comments on responses submitted for Deadline 1; • Any further information requested by the ExA under Rule 17 of the Examination Rules2.

16 July 2019 - Open Floor Hearing 1 (Morning)

Closed

For any Interested Parties to make representations on the merits of the Proposed Development.

16 July 2019 - Compulsory Acquisition Hearing 1

Closed

This hearing will take place on the afternoon of 16 Jul 2019.

17 July 2019 - Issue Specific Hearing 1

Closed

An Issue Specific Hearing dealing with matters relating on Need.

18 July 2019 - Issue Specific Hearing 2

Closed

An Issue Specific Hearing dealing with matters relating to the draft Development Consent Order

22 July 2019 - Open Floor Hearing 2 (Evening)

Closed

For any Interested Parties to make representations on the merits of the Proposed Development.

23 July 2019 - Issue Specific Hearing 3

Closed

An Issue Specific Hearing dealing with matters relating to Landscape and Visual Amenity Matters.

24 July 2019 - Accompanied Site Inspection 1

Closed

Accompanied Site Inspections (ASI) 1

25 July 2019 - Issue Specific Hearing 4

Closed

An Issue Specific Hearing dealing with matters relating to Biodiversity/Nature Conservation Matters.

1 August 2019 - Deadline 3

Closed

Deadline 3 Deadline for receipt by the ExA of: • Written summaries of oral submissions put at any hearings held between 16 and 25 July 2019; • Comments on LIR(s); • An updated Guide to the Application; • An updated version of the dDCO in clean, tracked and word versions; • An updated Compulsory Acquisition Schedule; • Comments on responses to the ExA’s Written Questions; • Comments on responses submitted for Deadline 2; • Progressed Statements of Common Ground; • Any further information requested by the ExA under Rule 17 of the Examination Rules.

9 August 2019 - Publication of

Closed

• The ExA’s Further Written Questions (FWQ) (if required)

30 August 2019 - Deadline 4

Closed

Deadline 4 Deadline for receipt by the ExA of: • Responses to the ExA’s FWQ (if published); • An updated Guide to the Application; • An updated version of the dDCO in clean, tracked and word versions; • An updated Compulsory Acquisition Schedule; • Comments on responses submitted for Deadline 3; • Progressed Statements of Common Ground; • Any further information requested by the ExA under Rule 17 of the Examination Rules.

10 September 2019 - Open Floor Hearing 3

Closed

For any Interested Parties to make representations on the merits of the Proposed Development.

10 September 2019 - Issue Specific Hearing 5

Closed

Issue Specific Hearing 5 on the draft Development Consent Order (dDCO)

11 September 2019 - Issue Specific Hearing 6

Closed

Issue Specific Hearing 6 on Environmental Matters

12 September 2019 - Compulsory Acquisition Hearing 2

Closed

Compulsory Acquisition Hearing 2

20 September 2019 - Deadline 5

Closed

Deadline 5 Deadline for receipt by the ExA of: • Written summaries of oral submissions put at any hearings held during the week commencing 9 September 2019; • Comments on responses to the ExA’s FWQ (if published); • An updated Guide to the Application; • An updated version of the dDCO in clean, tracked and word versions; • An updated Compulsory Acquisition Schedule; • Comments on responses submitted for Deadline 4; • Progressed Statements of Common Ground; • Any further information requested by the ExA under Rule 17 of the Examination Rules.

4 October 2019 - Deadline 6

Closed

Deadline 6 Deadline for receipt by the ExA of: • An updated Guide to the Application; • An updated version of the dDCO in clean, tracked and word versions; • An updated Compulsory Acquisition Schedule; • Comments on responses submitted for Deadline 5; • Progressed Statements of Common Ground; • Any further information requested by the ExA under Rule 17 of the Examination Rules.

23 October 2019 - Issue by the ExA of

Closed

• The Report on the Implications for European Sites (RIES) (if required); • The ExA’s dDCO (if required); • Any requests for information under Rule 17 of the Examination Rules (if required).

13 November 2019 - Deadline 7

Closed

Deadline 7 Deadline for receipt by the ExA of: • Comments on the RIES (if required); • Comments on the ExA’s dDCO (if required); • Any further information requested by the ExA under Rule 17 of the Examination Rules (if required); • An updated Guide to the Application; • An updated version of the dDCO in clean, tracked and word versions; • An updated Compulsory Acquisition Schedule; • Comments on responses submitted for Deadline 6; • Finalised Statements of Common Ground and S106 Agreements.

29 November 2019 - Rule 17 Deadline

Closed

Deadline for receipt by the ExA of: • Responses to the Request of Further Information(R17) requested by the Examining Authority

30 November 2019 - Close of Examination

Closed

The ExA is under a duty to complete the Examination of the application by the end of the period of 6 months