21 Hydref 2020
The Secretary of State for Business, Energy and Industrial Strategy has today granted development consent for the project. For further information please refer to the following documents:
- Secretary of State’s Decision Letter (PDF, 301KB)
- Planning Inspectorate Decision Cover Letter (PDF, 115KB)
- Development Consent Order as Made (PDF, 256KB)
- Examining Authority’s Recommendation Report (PDF, 2MB)
- Regulation 23 Notice (PDF, 111KB)
21 Hydref 2020
Decision made by the Secretary of State
21 Gorffennaf 2020
Recommendations given by the Planning Inspectorate
23 Ebrill 2020
15 Ebrill 2020
The Deadline 7 Submissions have now been published.
3 Ebrill 2020
The Examining Authority has issued a request for information from the Applicant under Rule 17. This has been added to the Examination Library.
2 Ebrill 2020
Deadline 6 submissions have now been published.
9 Mawrth 2020
The Rule 17 – Request for further information has now been Published.
25 Chwefror 2020
Deadline 5 submissions have now been published and the Examination Library has been updated.
10 Chwefror 2020
The Examining Authority has exercised its discretion to accept an Additional Submission from the Canal & Rivers Trust. This has been added to the Examination Library.
5 Chwefror 2020
3 Chwefror 2020
Deadline 4 submissions have now been published and the Examination Library has been updated.
24 Ionawr 2020
The following documents have been published and added to the Examination Library:
21 Ionawr 2020
The Examining Authority has exercised its discretion to accept an Additional Submission from the Applicant in the form of a Statement of Common Ground with Bassetlaw District Council. This has been added to the Examination Library.
13 Ionawr 2020
The Itinerary for the Accompanied Site Inspection and agendas for the Open Floor Hearing and Issue Specific Hearing have been published and added to the Examination Library.
23 Rhagfyr 2019
16 Rhagfyr 2019
The letter from the Examining Authority giving Notification of Hearings and Accompanied Site Inspection in January, has now been published.
The Examination Library has been updated
The Examination Library has been updated
11 Rhagfyr 2019
10 Rhagfyr 2019
The Deadline 2 submissions and the updated Examination Library have now been published.
22 Tachwedd 2019
The Deadline 1 submissions have been published.
6 Tachwedd 2019
The Examination Timetable (Rule 8 letter) has been sent to Interested Parties.
Procedural decision following Preliminary Meeting.
5 Tachwedd 2019
The Examining Authority carried out an Unaccompanied Site Inspection on 29 October 2019. A note of the inspection has been added to the Examination Library.
1 Tachwedd 2019
The Examining Authority has exercised its discretion to accept an Additional Submission from ESP Utilities Group Ltd. This has been added to the Examination Library.
31 Hydref 2019
Recording of the Preliminary Meeting - 30 October 2019 has been published.
30 Hydref 2019
Preliminary Meeting takes place
30 Hydref 2019
Examination begins
30 Medi 2019
The Examining Authority undertook an Unaccompanied Site Inspection on Wednesday 25 September 2019. A note of the visit has been published and added to the Examination Library.
26 Medi 2019
The notification of Preliminary Meeting (Rule 6 letter) has been sent.
The letter also includes the draft Examination Timetable and Initial Assessment of Principal Issues.
25 Medi 2019
The Examining Authority has exercised its discretion to accept an Additional Submission from the Environment Agency. This has been added to the Examination Library.
16 Medi 2019
The Examining Authority has exercised its discretion to accept Additional Submissions from Highways England and Harlaxton Gas Networks Limited. These have been added to the Examination Library.
3 Medi 2019
Relevant representations published on the website
30 Awst 2019
Registration of interested parties closes
26 Mehefin 2019
Registration of interested parties begins
23 Mai 2019
The application has been accepted for examination
1 Mai 2019
This application was received by the Planning Inspectorate on 30 April 2019.
The application documents will be made available if the application is accepted for examination.
It is for the applicant to decide whether or not application documents can be published upon submission (see DCLG pre-application guidance).
The application documents will be made available if the application is accepted for examination.
It is for the applicant to decide whether or not application documents can be published upon submission (see DCLG pre-application guidance).
30 Ebrill 2019
Application received by the Planning Inspectorate