Examination timetable
The examination timetable shows the dates of events and deadlines for submissions.
If you have registered to have your say, you can do this in the examination stage.
The examination stage
The examination opened on 17 July 2018
The examination closed on 8 January 2019
17 July 2018 - Preliminary Meeting
ClosedPreliminary Meeting
17 July 2018 - Issue Specific Hearing 1 (ISH1)
ClosedISH1 on the draft Development Consent Order (dDCO)
24 July 2018 - Issue by ExA
ClosedExamination timetable ExA’s Written Questions (ExQ1)
31 July 2018 - Deadline 1
ClosedDEADLINE 1
Deadline for receipt of:
● Comments on any updates to application documents submitted by the Applicant before or at the PM; ● Comments on Relevant Representations (RRs); ● Summaries of all RRs exceeding 1500 words; ● Written Representations (WRs) by all Interested Parties (IPs); ● Summaries of all WRs exceeding 1500 words; ● Statements of Common Ground (SoCG) requested by ExA – see Annex E; ● Response to any further information requested by the ExA for this deadline; ● Post-hearing submissions including written submissions of oral cases; ● Notification by Statutory Parties of their wish to be considered as an IP by the ExA; ● Notification of wish to speak at any subsequent Issue Specific Hearings (ISHs); ● Notification of wish to speak at an Open Floor Hearing (OFH); ● Provision of suggested locations and justifications for site inspections for consideration by the ExA; ● Notification of wish to attend an Accompanied Site Inspection (ASI); and ● Notification of wish to have future correspondence received electronically
21 August 2018 - Deadline 2
ClosedDEADLINE 2
Deadline for receipt of:
● Comments on WRs; ● Comments on any SoCG; ● Local Impact Reports (LIRs) from any Local Authorities; ● Responses to ExQ1; ● Comments on any additional information/ submissions received by D1; and ● Responses to any further information requested by the ExA for this deadline.
12 September 2018 - Accompanied Site Inspection
ClosedAccompanied Site Inspection
12 September 2018 - Open Floor Hearing
ClosedOpen Floor Hearing (evening)
13 September 2018 - Issue Specific Hearing 2 (ISH2)
ClosedISH2 on Environmental matters, Landscape & Visual, Ecology, Air Quality and Other matters
14 September 2018 - Issue Specific Hearing 3 (ISH3)
ClosedISH3 on the draft DCO
20 September 2018 - Deadline 3
ClosedDEADLINE 3
Deadline for receipt by the ExA of:
● Post-hearing submissions including written submissions of oral cases; ● Comments on LIRs; ● Comments on responses to ExQ1; ● Any revised/ updated SoCG (if any); ● The Applicant’s revised dDCO; ● Comments on any additional information/ submissions received by D2; and ● Responses to any further information requested by the ExA for this deadline.
28 September 2018 - Deadline 4
ClosedDEADLINE 4
Deadline for receipt by the ExA of:
● Comments on the Applicant’s revised dDCO; ● Comments on any revised/updated SoCG (if any); ● Comments on any additional information/ submissions received by D3; and ● Responses to any further information requested by the ExA for this deadline.
22 October 2018 - Procedural Decision
ClosedPublication by the ExA of:
● Further Written Questions (ExQ2) (if required); ● Consultation on the ExA’s preferred DCO (if required); and ● Report on the Implications for European Sites (RIES) (if required).
13 November 2018 - Deadline 5
ClosedDEADLINE 5
Deadline for receipt by the ExA of:
● Post-hearing submissions including written submissions of oral cases (if required); ● Any revised/ updated SoCG; ● Response to ExQ2 (if required); ● Comments on the ExA’s preferred DCO (if required); ● Comments on the ExA’s RIES (if required); ● Comments on any additional information/ submissions received by D4; and ● Responses to any further information requested by the ExA for this deadline.
20 November 2018 - Deadline 6
ClosedDEADLINE 6
Deadline for receipt by the ExA of:
● Comments on any revised/updated SoCG; ● Comments on responses to ExQ2 (if required); ● The Applicant’s Final preferred DCO in the Statutory Instrument (SI) template validation report; ● Comments on any additional information/ submissions received by D5; and responses to any further information requested by the ExA for this deadline.
28 November 2018 - Deadline 7
ClosedDEADLINE 7
Deadline for receipt by the ExA of:
● Comments on the Applicant’s Final preferred DCO; ● Comments on any additional information/ submissions received by D6; and ● Responses to any further information requested by the ExA for this deadline.
24 December 2018 - Deadline 8
ClosedDEADLINE 8
Deadline for receipt by the ExA of:
● Comments on the Applicant’s proposed change to Work No.1(c).
3 January 2019 - Deadline 9
ClosedDEADLINE 9
Deadline for receipt by the ExA of:
● Comments on any submissions received by D8.
17 January 2019 - Close of examination
ClosedThe ExA is under a duty to complete the Examination of the application by the end of the period of 6 months beginning with the day after the close of the Preliminary Meeting.