Nid oes unrhyw derfynau amser neu ddigwyddiadau
Amserlen yr archwiliad
Mae amserlen yr archwiliad yn dangos dyddiadau digwyddiadau a therfynau amser ar gyfer cyflwyniadau.
Os ydych wedi cofrestru i leisio'ch barn, gallwch wneud hyn yn ystod y cam archwilio.
Y cam archwilio
Agorodd yr archwiliad ar 4 October 2018
Caeodd yr archwiliad ar 4 April 2019
4 Hydref 2018 - Preliminary Meeting
CaeedigPreliminary Meeting
4 Hydref 2018 - Open Floor Hearing
CaeedigOpen Floor Hearing
11 Hydref 2018 - Issue by ExA of
Caeedig• Examination Timetable • ExA’ Written Questions
18 Hydref 2018 - Deadline 1
CaeedigDEADLINE 1
Deadline for receipt of: • Comments on updated application documents • Comments on Relevant Representations (RR) • Summaries of all RRs exceeding 1500 words • Statements of Common Ground (SoCG) requested by the ExA • Post hearing submissions including written submissions of oral case • Notification by Statutory Parties of their wish to be considered as an IP by the ExA • Notification of wish to make oral representations at an Issue Specific Hearing (ISH) • Notification of wish to speak at any Open Floor Hearing (OFH) • Notification of wish to speak at any Compulsory Acquisition Hearing (CAH) • Notification of wish to attend an Accompanied Site Inspection (ASI) including suggested locations and justifications • Notification of wish to have future correspondence received electronically • Comments on any additional information/submissions received • Responses to any further information requested by the ExA for this Deadline
8 Tachwedd 2018 - Deadline 2
CaeedigDEADLINE 2
Deadline for receipt of: • Written Representations (WR’s) • Summaries of all WR’s exceeding 1500 words • Comments on SoCG’s • Local Impact Reports (LIR) from any local authorities • Responses to ExA’s Written Questions • Updated Compulsory Acquisition Schedule (Annex to Written Questions) • Draft itinerary for Accompanied Site Inspection • Comments on any additional information/submissions received by D1 • Responses to any further information requested by the ExA for this Deadline
22 Tachwedd 2018 - Deadline 3
CaeedigDEADLINE 3
Deadline for receipt of: • Comments on WR’s • Comments on LIR’s • Comments on responses to the ExA’s Written Questions • Any revised/updated SoCG (if any) • The Applicant’s revised draft Development Consent Order (dDCO) • Requests to attend Accompanied Site Inspection • Comments on any additional information/submissions received by D2 • Responses to any further information requested by the ExA for this Deadline
4 Rhagfyr 2018 - Accompanied Site Inspection
CaeedigAccompanied Site Inspection
4 Rhagfyr 2018 - Open Floor Hearing 2 (OFH2)
CaeedigDate reserved to hold OFH2
5 Rhagfyr 2018 - Issue Specific Hearing 1 (ISH1)
CaeedigDate reserved to hold ISH1
6 Rhagfyr 2018 - Issue Specific Hearing 2 (ISH2)
CaeedigDate reserved to hold ISH2 on the dDCO (morning)
6 Rhagfyr 2018 - Compulsory Acquisition Hearing 1 (CAH1)
CaeedigDate reserved to hold CAH1(afternoon)
13 Rhagfyr 2018 - Deadline 4
CaeedigDEADLINE 4
Deadline for receipt of: • Post hearing submissions including written submissions of oral case • Comments on any revised/updated SoCG (if any) • Comments on the Applicant’s revised dDCO • Comments on any additional information/submissions received by D3 • Responses to any further information requested by the ExA for this Deadline
9 Ionawr 2019 - Deadline 5
CaeedigDEADLINE 5
Deadline for receipt of: • Any revised/updated SoCG (if any) • The Applicant’s revised dDCO • Comments on any additional information/submissions received by D4 • Responses to any further information requested by the ExA for this Deadline
15 Ionawr 2019 - Publication by ExA of -
Caeedig• The ExA’s further Written Questions (if required)
30 Ionawr 2019 - Deadline 6
CaeedigDEADLINE 6
Deadline for receipt of: • Responses to the ExA’s further Written Quetsions (if required) • Comments on any revised/updated SoCG (if any) • Comments on the Applicant’s revised dDCO • Comments on any additional information/submissions received by D5 • Responses to any further information requested by the ExA for this Deadline
12 Chwefror 2019 - Compulsory Acquisition Hearing (CAH2), Open Floor Hearing (OFH3) & Issue Specific Hearing (ISH3)
CaeedigDate reserved to hold CAH2, OFH3 and ISH3
20 Chwefror 2019 - Deadline 7
CaeedigDEADLINE 7
Deadline for receipt of: • Post hearing submissions including written submissions of oral case (if required) • Comments on the ExA’s further Written Questions (if required) • Any revised/updated SoCG (if any) • The Applicant’s revised dDCO • Comments on any additional information/submissions received by D6 • Responses to any further information requested by the ExA for this Deadline
28 Chwefror 2019 - Publication by ExA of -
Caeedig• Report on the Implications for European Sites (RIES) • ExA’s proposed schedule of changes to the dDCO (if required)
21 Mawrth 2019 - Deadline 8
CaeedigDEADLINE 8
Deadline for receipt of: • Comments on the RIES • Comments on the ExA’s proposed schedule of changes to the dDCO (if required) • Final SoCGs • Applicant’s final Compulsory Acquisition Schedule • Final updated Book of Reference • Comments on any additional information/submissions received by D7 • Responses to any further information requested by the ExA for this Deadline
28 Mawrth 2019 - Deadline 9
CaeedigDEADLINE 9
Deadline for receipt of: • Applicant’s final DCO to be submitted in the SI template with the SI template validation report • Final updated Guide to the Application • Comments on any additional information/submissions received by D8 • Responses to any further information requested by the ExA for this Deadline
4 Ebrill 2019 - Close of the Examination
CaeedigThe ExA is under a duty to complete the examination of the application by the end of the period of 6 months beginning with the day after the close of the Preliminary Meeting