View examination library (PDF, 555KB) containing document reference numbers
-
Deadline 8 Submission - Comments on any additional information/submissions received by the previous deadline
(PDF, 192KB)
From London Borough of Bexley
-
Deadline 8 Submission - 8.02.82 Applicant's response to Mrs Margaret J White Deadline 7 Submission
(PDF, 1MB)
From Cory Riverside Energy
-
Deadline 8 Submission - Response to Deadline 8 – Comments on Applicant’s draft Development Consent Order (DCO)
(PDF, 291KB)
From Eversheds Sutherland LLP on behalf of National Grid
-
Deadline 8 Submission - 8.02.83 Applicant's update on Environmental Permit Determination
(PDF, 920KB)
From Cory Riverside Energy
-
Deadline 8 Submission - Annex A - Agreed Protective provisions
(PDF, 65KB)
From Thames Water Utilities Limited
-
Deadline 8 Submission - 8.01.13 Statement of Common Ground (SoCG) Kent County Council (Rev 2)
(PDF, 434KB)
From Cory Riverside Energy
-
Deadline 8 Submission - 8.02.87 Applicant's response to Friends of Crossness Nature Reserve Submission
(PDF, 815KB)
From Cory Riverside Energy
-
Deadline 8 Submission - Appendix 4 - Planning Permission Conditions
(PDF, 118KB)
From Greater London Authority
-
Deadline 8 Submission - 8.02.78 Applicant's response to Greater London Authority's Deadline 7 and 7A Submissions
(PDF, 1MB)
From Cory Riverside Energy
-
Deadline 8 Submission - 7.6 Outline Biodiversity Landscape Mitigation Strategy (Rev 4) (with track changes)
(PDF, 2MB)
From Cory Riverside Energy
-
Deadline 8 Submission - 8.02.22 Land Negotiations Summary (Rev 3)
(PDF, 814KB)
From Cory Riverside Energy
-
Deadline 8 Submission - 5.3 Grid Connection Statement (Rev 2) (with track changes)
(PDF, 3MB)
From Cory Riverside Energy
-
Deadline 8 Submission - 8.02.86 Supplementary Note to the Temporary Jetty Outage Review
(PDF, 951KB)
From Cory Riverside Energy
-
Deadline 8 Submission - Comments on any additional information/submissions received by previous deadline
(PDF, 140KB)
From Friends of Crossness Nature Reserve
-
Deadline 8 Submission - 6.3 ES Appendix L to B.1 Outline Construction Traffic Management Plan (CTMP (Rev 5) (with track Changes)
(PDF, 3MB)
From Cory Riverside Energy
-
Deadline 8 Submission - 7.5 Outline Code of Construction Practice (Rev 4)
(PDF, 1MB)
From Cory Riverside Energy
-
Deadline 8 Submission - 8.02.77 Oral Summaries for the Issue Specific Hearing on draft DCO ISH3 (19 September 2019)
(PDF, 2MB)
From Cory Riverside Energy
-
Deadline 8 Submission - 5.3 Grid Connection Statement (Rev 2)
(PDF, 3MB)
From Cory Riverside Energy
-
Deadline 8 Submission - 1.3 Guide to the Application (Rev 7)
(PDF, 583KB)
From Cory Riverside Energy
-
Deadline 8 Submission - Late Submission accepted at the discretion of the Examining Authority - Comments on any additional information/submissions received by previous deadline
(PDF, 217KB)
From Port of London Authority
-
Deadline 8 Submission - 8.02.81 Applicant's response to Thames Water Utilities Ltd Deadline 7 Submission
(PDF, 1MB)
From Cory Riverside Energy
-
Deadline 8 Submission - Written summary of oral submissions from Issue Specific Hearing 3 (ISH3) on the draft Development Consent Order (DCO)
(PDF, 112KB)
From London Borough of Bexley
-
Deadline 8 Submission - Comments on Doc 8.02.71 Environment Bank Site Selection for Biodiversity Offsetting Report
(PDF, 111KB)
From Bexley Natural Environment Forum
-
Deadline 8 Submission - Appendix 3 - DECC Approval Explanatory Memorandum
(PDF, 16KB)
From Greater London Authority
-
Deadline 8 Submission - 1.3 Guide to the Application (Rev 7) (with track changes).
(PDF, 608KB)
From Cory Riverside Energy
-
Deadline 8 Submission - 4.3 Book of Reference (Rev 3) (with track changes)
(PDF, 37KB)
From Cory Riverside Energy
-
Deadline 8 Submission - 8.02.80 Applicant's response to London Borough of Bexley Deadline 7 Submission
(PDF, 2MB)
From Cory Riverside Energy
-
Deadline 8 Submission - 6.3 ES Appendix L to B.1 Outline Construction Traffic Management Plan (CTMP (Rev 5)
(PDF, 3MB)
From Cory Riverside Energy
-
Deadline 8 Submission - 8.02.75 Deadline 8 Submission Letter
(PDF, 82KB)
From Cory Riverside Energy
-
Recording of Compulsory Acquisition Hearing 2 (CAH2) - 18th September 2019
(PDF, 32KB)
-
Recording of Issue Specific Hearing 3 (ISH3) - 19th September 2019
(PDF, 32KB)
-
Additional Submission – Letter of withdrawal - Accepted at the discretion of the Examining Authority - Submission withdrawn via email on 17 09 19
(PDF, 363KB)
From Creekside Developments (Kent) Limited
-
Additional Submission – Acceptance of Option Agreement and Withdrawal of Relevant Representation letter - Accepted at the discretion of the Examining Authority - Submission withdrawn via email on 17 09 19
(PDF, 5MB)
From Maz Mohammad
-
Additional Submission – Letter of withdrawal - Accepted at the discretion of the Examining Authority - Submission withdrawn via email on 17 09 19
(PDF, 498KB)
From SAS Depot Limited
-
Additional Submission – Withdrawal Letter - Accepted at the discretion of the Examining Authority - Submission Withdrawn via email on 16 09 19
(PDF, 248KB)
From Western Riverside Waste Authority
-
Additional Submission - Accepted at the discretion of the Examining Authority. Comments on the draft Development Consent Order (DCO)
(PDF, 70KB)
From Friends of Crossness Nature Reserve
-
Additional Submission – Accepted at the discretion of the Examining Authority. Letter to the Examining Authority concerning attendance at Issue Specific Hearing 3 (ISH3)
(PDF, 58KB)
From Thames Water Utilities Limited
-
Additional Submission – Accepted at the discretion of the Examining Authority. Annex A Protective Provisions
(PDF, 65KB)
From Thames Water Utilities Limited
-
Deadline 7a Submission - 8.2.74 Applicant's response to the ExA's rule 17 Letter on 30 August 2019
(PDF, 1MB)
From Cory Riverside Energy
-
Deadline 7a Submission - Cover Letter
(PDF, 334KB)
From Cory Riverside Energy
-
Deadline 7a Submission - Comments on any additional information/submissions received by previous deadline
(PDF, 588KB)
From Greater London Authority
-
Deadline 7a Submission - 8.02.70 Applicant's response to Air Quality Matters (this document supersedes the document submitted for Deadline 7 Submission REP7-018)
(PDF, 7MB)
From Cory Riverside Energy
-
Deadline 7a Submission - 8.02.70 Applicant's response to Air Quality Matters with track changes (this document supersedes the document submitted for Deadline 7 Submission REP7-018)
(PDF, 7MB)
From Cory Riverside Energy
-
Deadline 7a Submission - Responses to any further information requested by the ExA
(PDF, 125KB)
From London Borough of Bexley
-
Agenda for Compulsory Acquisition Hearing 2 (CAH2) and Issue Specific Hearing 3 (ISH3)
(PDF, 150KB)
-
Deadline 7 Submission - 8.02.72 Applicant's response to London Borough of Bromley Deadline 5 Submission
(PDF, 1MB)
From Cory Riverside Energy
-
Deadline 7 Submission - 8.02.42 Anaerobic Digestion Facility Emissions Mitigation Note (Rev 1)
(PDF, 7MB)
From Cory Riverside Energy
-
Deadline 7 Submission - 8.02.64 Applicant's response to Mrs Margaret J White Additional Submission (09 August 2019)
(PDF, 979KB)
From Cory Riverside Energy
-
Deadline 7 Submission - Comments on additional information/submissions received at Deadline 5 and 6
(PDF, 269KB)
From London Borough of Bexley
-
Deadline 7 Submission - 8.02.71 Environment Bank Site Selection for Biodiversity Offsetting Report
(PDF, 794KB)
From Cory Riverside Energy
-
Deadline 7 Submission - 7.6 Outline Biodiversity Landscape Mitigation Strategy (Rev 3) (with track changes)
(PDF, 1MB)
From Cory Riverside Energy
-
Deadline 7 Submission - Deadline 7 Covering Letter
(PDF, 186KB)
From Greater London Authority
-
Deadline 7 Submission - 8.02.65 Applicant's response to Thames Water Utilities Limited Deadline 5 Submission
(PDF, 1MB)
From Cory Riverside Energy
-
Deadline 7 Submission - Appendix A: Schedule 1 GLA response to Applicant's submissions at Deadline 5
(PDF, 289KB)
From Greater London Authority
-
Deadline 7 Submission - 8.02.68 Applicant's response to Countryside Properties and L&Q New Homes Deadline 5 Submission
(PDF, 1MB)
From Cory Riverside Energy
-
Deadline 7 Submission - 8.02.66 Applicant's response to London Borough of Bexley Deadline 5 Submission
(PDF, 1MB)
From Cory Riverside Energy
-
Deadline 7 Submission - Comments on any additional information/submissions received by previous deadline
(PDF, 522KB)
From Mrs Margaret J White
-
Deadline 7 Submission - 6.2 ES Figure 7.9 Predicted Annual Mean NOx Concentrations (Rev 2)
(PDF, 2MB)
From Cory Riverside Energy
-
Deadline 7 Submission - Responses to any further information requested by the Examining Authority
(PDF, 759KB)
From East London Waste Authority
-
Deadline 7 Submission - 1.3 Guide to the Application (Rev 6)
(PDF, 1MB)
From Cory Riverside Energy
-
Deadline 7 Submission - 6.2 ES Figure 7.10 Predicted Daily NOx Concentrations (Rev 2)
(PDF, 1MB)
From Cory Riverside Energy
-
Deadline 7 Submission - 8.02.69 Applicant's response to Arriva London Deadline 5 Submission
(PDF, 884KB)
From Cory Riverside Energy
-
Deadline 7 Submission - 7.6 Outline Biodiversity Landscape Mitigation Strategy (Rev 3)
(PDF, 1MB)
From Cory Riverside Energy
-
Deadline 7 Submission - Appendix A Draft DCO (Rev 3 with LBB track changes)
(PDF, 3MB)
From London Borough of Bexley
-
Deadline 7 Submission - 6.2 ES Figure 7.8 Predicted Hourly NO2 Concentrations (Rev 2)
(PDF, 3MB)
From Cory Riverside Energy
-
Deadline 7 Submission - 8.01.12 Statement of Common Ground Kent County Council (Rev 2)
(PDF, 493KB)
From Cory Riverside Energy
-
Deadline 7 Submission - 8.02.63 Deadline 7 Submission Letter
(PDF, 500KB)
From Cory Riverside Energy
-
Deadline 7 Submission - 8.02.42 Anaerobic Digestion Facility Emissions Mitigation Note (Rev 1) (with track changes)
(PDF, 7MB)
From Cory Riverside Energy
-
Deadline 7 Submission - 8.02.67 Applicant's response to Greater London Authority Deadline 5 and 6 Submissions
(PDF, 1MB)
From Cory Riverside Energy
-
Deadline 7 Submission - Appendix B Draft DCO Explanatory Memorandum (Rev 2 with LBB comments)
(PDF, 5MB)
From London Borough of Bexley
-
Deadline 7 Submission - 8.02.70 Applicant's response to Air Quality Matters
(PDF, 2MB)
From Cory Riverside Energy
-
Deadline 7 Submission - Responses to any further information requested by the Examining Authority - Submission withdrawn via email on 05 09 19
(PDF, 362KB)
From Western Riverside Waste Authority - WITHDRAWN
-
Deadline 7 Submission - 1.3 Guide to the Application (Rev 6) (with track changes)
(PDF, 1MB)
From Cory Riverside Energy
-
Deadline 7 Submission - Annex A - Protective Provisions
(PDF, 66KB)
From Thames Water Utitlities Limited
-
Deadline 7 Submission - Submission of Comments on behalf of Interested Party Thames Water Utilities Limited
(PDF, 391KB)
From Thames Water Utilities Limited
-
Variation to Timetable - Rule 8(3)
(PDF, 153KB)
-
Request for Further Information - Rule 17 - 30 August 2019
(PDF, 91KB)
-
Additional Submission – Accepted at the discretion of the Examining Authority. Summary of Consultation and Update on Statement of Common Ground between the Applicant and Greater London Authority
(PDF, 2MB)
From Cory Riverside Energy
-
Additional Submission – Accepted at the discretion of the Examining Authority
(PDF, 168KB)
From London Borough of Bromley
-
Deadline 5 Submission - Comments on any additional information/submissions received by previous deadline
(PDF, 222KB)
From Arriva London
-
Deadline 6 Submission - Outline Biodiversity Landscape Mitigation Strategy (OBLEMS) (Rev 2) - with Track Changes
(PDF, 1MB)
From Cory Riverside Energy
-
Deadline 6 Submission - Response to Examining Authority's Further Written Questions
(PDF, 109KB)
From London Borough of Havering
-
Deadline 6 Submission - 8.02.59 Submission Letter
(PDF, 240KB)
From Cory Riverside Energy
-
Deadline 6 Submission - 1.3 Guide to the Application (Rev 5) - Tracked Changes
(PDF, 1MB)
From Cory Riverside Energy
-
Deadline 6 Submission - Outline Biodiversity Landscape Mitigation Strategy (OBLEMS) (Rev2)
(PDF, 1MB)
From Cory Riverside Energy
-
Deadline 6 Submission - 1.3 Guide to the Application (Rev 5)
(PDF, 1MB)
From Cory Riverside Energy
-
Deadline 6 Submission - 8.02.61 Applicant's Response to the Examining Authority's Rule 17 letter on Changes to the Application
(PDF, 991KB)
From Cory Riverside Energy
-
Deadline 6 Submission - Response to Examining Authority's Further Written Questions
(PDF, 34KB)
From Greater London Authority
-
Deadline 6 Submission - 8.02.60 Applicant's Response to the Examining Authority's Further Written Questions
(PDF, 678KB)
From Cory Riverside Energy
-
Notification of Issue Specific Hearing 3 (ISH3) and Compulsory Acquisition Hearing 2 (CAH2)
(PDF, 98KB)
From Rule 13 - Notification of Hearings
-
Deadline 5 Submission - 6.3 Appendix L to B1 Outline Construction Traffic Management Plan (Rev 4)
(PDF, 15MB)
From Cory Riverside Energy
-
Deadline 5 Submission - Schedule 3 - GLA’s comments on London Borough of Bexley comments on the Applicant’s revised draft DCO submitted at Deadline 3
(PDF, 78KB)
From Greater London Authority
-
Deadline 5 Submission - 8.02.49 Applicant's response to Ralph Todd Deadline 4 Submission
(PDF, 521KB)
From Cory Riverside Energy
-
Deadline 5 Submission from non-IP – accepted at the discretion of the Examining Authority. Response to further information requested by the Examining Authority
(PDF, 235KB)
From Countryside Properties (UK) Ltd
-
Deadline 5 Submission - 8.02.51 Applicant's response to London Borough of Bexley Deadline 4 Submission
(PDF, 601KB)
From Cory Riverside Energy
-
Deadline 5 Submission - 8.02.46 Applicants response to GLA Deadline 4 Submisison
(PDF, 3MB)
From Cory Riverside Energy
-
Deadline 5 Submission - 8.02.50 Applicant's response to Thames Water Deadline 4 Submission
(PDF, 1MB)
From Cory Riverside Energy
-
Deadline 5 Submission - 8.02.55 Pre-Commencement Plan
(PDF, 979KB)
From Cory Riverside Energy
-
Deadline 5 Submission - 7.5 Outline Code of Construction Practice (Rev 3) (with track changes).
(PDF, 1MB)
From Cory Riverside Energy
-
Deadline 5 Submission - 8.02.44 Deadline 5 Submission Letter
(PDF, 503KB)
From Cory Riverside Energy