All project updates
5 Ebrill 2024
A Decision Letter (PDF, 199KB) and Amendment Order (PDF, 78KB) have been issued by the Department of Energy Security and Net Zero to make a change that is not material to the Immingham Open Cycle Gas Turbine Order 2020.
21 Mawrth 2024
The Applicant has provided their Consultation and Publicity Statement (PDF, 165KB). The Secretary of State previously issued a letter (PDF, 158KB) to confirm those parties that the Applicant should consult.
12 Chwefror 2024
Representations received in response to the application for a non-material change to the Made VPI Immingham OCGT Development Consent Order VPI Immingham OCGT - Project Information have been published.
22 Rhagfyr 2023
The non-material change 2 documents have been published.
The deadline for receipt of representations is 1st February 2024.
If you wish to make a representation, this should be emailed to ImminghamOCGT@planninginspectorate.gov.uk or posted to:
Immingham OCGT Case Team - National Infrastructure
The Planning Inspectorate
Temple Quay House
2 The Square
Bristol BS1 6PN
8 Chwefror 2023
22 Rhagfyr 2022
30 Tachwedd 2022
14 Hydref 2022
If you wish to make a representation, this should be emailed to ImminghamOCGT@planninginspectorate.gov.uk or posted to:
National Infrastructure
The Planning Inspectorate
Temple Quay House
2 The Square
Bristol
BS1 6PN
The deadline for receipt of representations is 11:59pm on Thursday 17 November 2022
17 Mai 2021
Correction Notice (PDF, 160 KB); and Correction Order (PDF, 57 KB)
7 Awst 2020
Planning Inspectorate Notification of Consent Letter
Secretary of State Decision Letter
Examining Authority Recommendation Report
Development Consent Order as made by the Secretary of State
Habitats Regulation Assessment
Regulation 31 Notice
Post-Examination Submissions
7 Awst 2020
21 Gorffennaf 2020
6 Gorffennaf 2020
The deadline for the consultation responses is 23:59 on 20 July 2020.
30 Mehefin 2020
10 Mehefin 2020
The deadline for the consultation responses is 23:59 on 26 June 2020.
11 Mai 2020
The Examining Authority issued a Recommendation Report to the Secretary of State on 7 May 2020. The Secretary of State has three months in which to issue a decision. The decision letter and the Recommendation Report will be published on this project page once a decision has been made.
7 Mai 2020
10 Chwefror 2020
8 Chwefror 2020
7 Chwefror 2020
24 Ionawr 2020
10 Ionawr 2020
3 Ionawr 2020
13 Rhagfyr 2019
2 Rhagfyr 2019
26 Tachwedd 2019
19 Tachwedd 2019
5 Tachwedd 2019
24 Hydref 2019
11 Hydref 2019
7 Hydref 2019
25 Medi 2019
The Accompanied Site Inspection Itinerary has also been published.
16 Medi 2019
13 Medi 2019
30 Awst 2019
15 Awst 2019
Procedural decision following Preliminary Meeting.
8 Awst 2019
8 Awst 2019
10 Gorffennaf 2019
The letter also includes the draft Examination Timetable and Initial Assessment of Principal Issues.
8 Gorffennaf 2019
25 Mehefin 2019
16 Mai 2019
9 Mai 2019
18 Ebrill 2019
If the application is accepted for examination anyone interested in the application will be able to register and express their views during the relevant representation stage and the subsequent examination.
15 Ebrill 2019
The applicant has agreed that all application documents can be published as soon as practicable to help everyone become familiar with the detail of what is being proposed in this application. The Planning Inspectorate will therefore make the application documents available as soon as practicable.
This provision is solely for the purpose of allowing more time to all those who wish to become familiar with the detail of what is being proposed ahead of the relevant representation period without lengthening the overall time required for the application process. There will be no opportunity at this stage to make comments on the application. However, if the application is accepted anyone interested in the application will be able to register and express their views during the relevant representation stage and the subsequent examination