South Humber Bank Energy Centre Examination timetable

The examination timetable shows the dates of events and deadlines for submissions.

If you have registered to have your say, you can do this in the examination stage.

The examination stage

The examination opened on 10 November 2020

The examination closed on 10 May 2021

Upcoming deadlines and events

There are no deadlines and events

Past deadlines and events

8 October 2020 - Procedural Deadline A

Closed

Procedural Deadline A

Deadline for receipt by the ExA of:

• Written submissions, if required, from the Applicant and any Interested Party on Examination procedure, any changes that are considered necessary to the draft examination timetable, together with which agenda items you wish to speak on, points you wish to make, and why these need to be made orally rather than in writing; and • Requests to be heard orally at the Preliminary Meeting Part 1.

21 October 2020 - Preliminary Meeting Part 1

Closed

Preliminary Meeting Part 1

3 November 2020 - Procedural Deadline B

Closed

Procedural Deadline B

Deadline for receipt by the ExA of:

• Written submissions on Examination procedure responding to matters raised orally in the Preliminary Meeting Part 1; and • Requests to be heard orally at the Preliminary Meeting Part 2.

10 November 2020 - Preliminary Meeting Part 2

Closed

Preliminary Meeting Part 2

17 November 2020 - Issue by the ExA 1

Closed

Issue by the ExA of:

• Examination Timetable; • The ExA’s Written Questions (ExQ1).

8 December 2020 - Deadline 1

Closed

Deadline 1

Deadline for receipt by the ExA of:

• Local Impact Reports (LIRs) from Local Authorities; • Statements of Common Ground (SoCG) requested by the ExA; • Updated Guide to the Application, as requested by the ExA; • Notification of wish to speak at an Open Floor Hearing (OFH); • Submission by the Applicant and Interested Parties (IPs) of suggested locations for the ExA to include in any Accompanied Site Inspection (ASI), including the reason for nomination and issues to be observed, information about whether the location can be accessed using public rights of way or what access arrangements would need to be made, and the likely time requirement for the visit to that location (if not covered within Unaccompanied Site Inspection (USI); • Comments on Relevant Representations; and • Comments on any Additional Submissions accepted by the ExA.

22 December 2020 - Deadline 2

Closed

Deadline 2

Deadline for receipt by the ExA of:

• Comments on LIR(s); • Comments on any responses/ information submitted for Deadline 1; • Responses to the ExQ1; • Written Representations (WRs) with summaries of all WRs exceeding 1500 words; • Statement of Commonality of SoCG not submitted at Deadline 1; • Updated Guide to the Application, as requested by the ExA; • Any updated version of the draft Development Consent Order (dDCO) in clean, tracked and word versions; • Schedule of changes to the dDCO; and • Any further information requested by the ExA under Rule 17 of the EPR2.

11 January 2021 - Issue by the ExA 2

Closed

Issue by the ExA of:

• Notification of Hearings to be held during the week commencing 8 February 2021 (if required).

20 January 2021 - Deadline 3

Closed

Deadline 3

Deadline for receipt by the ExA of:

• Comments on Responses to ExQ1; • Comments on WRs; • Comments on any responses/ information submitted for Deadline 2; • Applicant’s draft itinerary for the ASI; • Progressed SoCG requested by the ExA; • Statement of Commonality of SoCG not submitted at Deadline 1; • Updated Guide to the Application, as requested by the ExA; • Any updated version of the dDCO in clean, tracked and word versions; and • Any further information requested by the ExA under Rule 17 of the EPR.

8 February 2021 - Open Floor Hearing

Closed

Open Floor Hearing (OFH1)

For any Interested Parties to make representations on the merits of the Proposed Development.

9 February 2021 - Issue Specific Hearing 1

Closed

Issue Specific Hearing into the Development Consent Order (DCO)(ISH1)

19 February 2021 - Deadline 4

Closed

Deadline 4

Deadline for receipt by the ExA of:

• Written summaries of oral submissions made at any Hearings held during the week commencing 8 February 2021; • Comments on any responses/ information submitted for Deadline 3; • Any updated version of the dDCO in clean, tracked and word versions; • Schedule of changes to the dDCO; • Statement of Commonality of SoCG not submitted at Deadline 1; • Updated Guide to the Application, as requested by the ExA; and • Any further information requested by the ExA under Rule 17 of the EPR.

23 February 2021 - Issue by the ExA 3

Closed

Issue by the ExA of:

• Notification of ASI to be held during the week commencing 8 March 2021 (if required).

5 March 2021 - Issue by the ExA 4

Closed

Issue by the ExA of:

• ExQ2 (if required).

8 March 2021 - Dates reserved 3

Closed

Dates reserved in week commencing 8 March 2021 for:

• Accompanied Site Inspection (if required).

19 March 2021 - Deadline 5

Closed

Deadline 5

Deadline for receipt by the ExA of:

• Responses to the ExA’s ExQ2; • Comments on any responses/ information submitted for Deadline 4; • Any updated version of the dDCO in clean, tracked and word versions; • Schedule of changes to the dDCO; • Statement of Commonality of SoCG not submitted at Deadline 1; • Updated Guide to the Application, as requested by the ExA; and • Any further information requested by the ExA under Rule 17 of the EPR.

31 March 2021 - Issue by the ExA 5

Closed

Issue by the ExA of:

• The Report on the Implications for European Sites (RIES) (if required); • The ExA’s proposed schedule of changes to the dDCO (if required); and • Any requests for information under Rule 17 of the EPR (if required).

23 April 2021 - Deadline 6

Closed

Deadline 6

Deadline for receipt by the ExA of:

• Finalised SoCG; • Final Guide to the Application; • Signed and dated s106 Agreement (if required); • Comments on the RIES (if required); and • Comments on the ExA’s proposed schedule of changes to the dDCO (if required); • Comments on any responses/ information submitted for Deadline 5; • The Applicant’s Final Preferred DCO in the SI template validation report; and • Responses to any further information requested by the ExA under Rule 17 of the EPR (if required).

5 May 2021 - Deadline 7

Closed

Deadline 7

Deadline for receipt by the ExA of: • Comments on any responses/ information submitted for Deadline 6 (23 April 2021); and • Responses to the further information requested by the ExA pursuant to his Rule 17 letter dated 28 April 2021. • The Applicant’s final preferred DCO in the SI template validation report (if required).

10 May 2021 - Deadline 8

Closed

Deadline 8

Deadline for receipt by the ExA of: • Comments on any responses/ information submitted to submissions made pursuant to the ExA’s Rule 17 Letter dated 28 April 2021; • Submission of a Section 106 agreement or a Deed of Variation that is entered into by all three parties, which expressly binds the mortgagees interest in the land to the obligations in the agreement and is compliant with all the requirements of s.106 (if required).