Nid oes unrhyw derfynau amser neu ddigwyddiadau
Amserlen yr archwiliad
Mae amserlen yr archwiliad yn dangos dyddiadau digwyddiadau a therfynau amser ar gyfer cyflwyniadau.
Os ydych wedi cofrestru i leisio'ch barn, gallwch wneud hyn yn ystod y cam archwilio.
Y cam archwilio
Agorodd yr archwiliad ar 7 December 2021
Caeodd yr archwiliad ar 7 June 2022
26 Tachwedd 2021 - Procedural Deadline A
CaeedigProcedural Deadline A
Deadline for receipt by the ExA of:
- Written submissions on the Examination procedure including any submissions about the use of virtual procedures; and
- Requests to be heard orally at the Preliminary Meeting
7 Rhagfyr 2021 - Preliminary Meeting
CaeedigPreliminary Meeting
21 Rhagfyr 2021 - Deadline 1
CaeedigDeadline 1
Deadline for receipt by the ExA of:
- Local Impact Reports (LIRs) from the Local Authorities
- Statements of Common Ground (SoCG)
- Updated Guide to the Application
- Notification of wish to speak at an Open Floor Hearing
- Notification of wish to speak at a Compulsory Acquisition Hearing
- Submission of suggested locations to be included in any Accompanied Site Inspection (ASI)
- Notification of wish to attend ASI
- Comments on Relevant Representations
- Comments on Additional Submissions
- Any further information requested by the ExA
1 Chwefror 2022 - Deadline 2
CaeedigDeadline 2
Deadline for receipt by the ExA of:
- Comments on any information submitted for Deadline 1
- Written Representations (WRs) with summaries of all WRs exceeding 1500 words
- Comments on LIR(s)
- Responses to the ExA's Written Questions (ExQ1)
- An updated Statement of Commonality of SoCG
- Updated Guide to the Application
- Updated Compulsory Acquisition Schedule
- Updated Book of Reference;
- Update on the progress that has been made with Affected Persons in respect of Compulsory Acquisition and Temporary Possession
- An updated version of the draft Development Consent Order (dDCO) in clean, tracked and word versions
- Schedule of changes to the dDCO
- Applicant’s draft itinerary for the ASI
- Any further information requested by the ExA
14 Chwefror 2022 - Notification of Hearings
CaeedigNotification of Hearings
Issue by the ExA of:
- Notification of Hearings to be held during the week commencing 14 and/ or 21 March 2022 (if required)
15 Chwefror 2022 - Deadline 3
CaeedigDeadline 3
Deadline for receipt by the ExA of:
- Comments on Responses to ExQ1
- Comments on WRs;
- Comments on Applicant’s draft itinerary for the ASI
- Comments on any information submitted for Deadline 2
- Any updated SoCG requested by the ExA
- An updated Statement of Commonality of SoCG
- Updated Guide to the Application
- An updated Book of Reference
- An update on the progress that has been made with Affected Persons in respect of Compulsory Acquisition and Temporary Possession
- An updated Compulsory Acquisition/ Temporary Possession Schedule, including s127 Statutory Undertakers’ Land and Rights Schedule and s138 Statutory Undertakers’ Apparatus Schedule
- An updated version of the dDCO in clean, tracked and word versions
- Any further information requested by the ExA
1 Mawrth 2022 - Deadline 4
CaeedigDeadline 4
Deadline for receipt by the ExA of:
- Comments on any information submitted for Deadline 3
- An updated version of the dDCO in clean, tracked and word versions
- Schedule of changes to the dDCO
- An updated Statement of Commonality of SoCG
- Updated Guide to the Application
- An updated Compulsory Acquisition Schedule
- An updated Book of Reference
- An update on the progress that has been made with Affected Persons in respect of Compulsory Acquisition and Temporary Possession
- Any further information requested by the ExA
14 Mawrth 2022 - Open Floor Hearing (OFH)
Caeedig.
15 Mawrth 2022 - Issue Specific Hearing 1 (ISH1)
CaeedigIssue Specific Hearing on Environmental Matters
16 Mawrth 2022 - Compulsory Acquisition Hearing (CAH)
Caeedig.
17 Mawrth 2022 - Issue Specific Hearing 2 (ISH2)
CaeedigIssue Specific Hearing on the draft Development Consent Order
22 Mawrth 2022 - Reserved for OFH / ISH1 / CAH (NOT REQUIRED)
Caeedig.
24 Mawrth 2022 - Reserved for CAH / ISH2 (if required)
Caeedig.
5 Ebrill 2022 - Deadline 5
CaeedigDeadline 5
Deadline for receipt by the ExA of:
- Written summaries of oral submissions made at any Hearings held during the week commencing 14 March 2022 and 21 March 2022
- Comments on any information submitted for Deadline 4
- An updated version of the dDCO in clean, tracked and word versions
- Schedule of changes to the dDCO
- An updated Statement of Commonality of SoCG
- Updated Guide to the Application
- An updated Compulsory Acquisition Schedule
- An updated Book of Reference
- An update on the progress that has been made with Affected Persons in respect of Compulsory Acquisition and Temporary Possession
- Any further information requested by the ExA
12 Ebrill 2022 - Accompanied Site Inspection (if required)
Caeedig.
12 Ebrill 2022 - Publication by the ExA
Caeedig- Further Written Questions (ExQ2) (if required)
- Proposed schedule of changes to the dDCO (if required)
26 Ebrill 2022 - Deadline 6
CaeedigDeadline 6
Deadline for receipt by the ExA of:
- Responses to ExQ2 (if required)
- Comments on the ExA’s proposed schedule of changes to the dDCO (if required)
- Final SoCG
- Final Statement of Commonality of the SoCG
- Updated Guide to the Application (if required)
- Update regarding progress that has been made with Affected Persons in respect of Compulsory Acquisition and Temporary Possession
- Comments on any information submitted for Deadline 5
- Responses to any further information requested by the ExA
3 Mai 2022 - Issue by the ExA
Caeedig- The Report on the Implications for European Sites (RIES) (if required)
10 Mai 2022 - Deadline 6a
CaeedigDeadline 6a
Deadline for receipt by the ExA of:
- Comments on Responses submitted at Deadline 6
- Final Guide to the Application
- Final update regarding progress that has been made with Affected Persons in respect of Compulsory Acquisition (CA) and Temporary Possession (TP)
- Final Book of Reference
- Final CA/ TP schedule
- Signed and dated s106 Agreement (if required)
- Applicant’s preferred DCO in the SI template validation report and a validated copy of the DCO
- Applicant’s preferred DCO in word format
- Responses to any further information requested by the ExA
24 Mai 2022 - Deadline 7
CaeedigDeadline 7
Deadline for receipt by the ExA of:
- The submission of final and completed (signed and dated) versions of the Statements of Common Ground (SoCG) between the Applicant and Natural England, Northern Powergrid, the United Kingdom Health Security Agency, the Canal and River Trust, Network Rail, and Keadby with Althorpe Parish Council; or submission of a detailed explanation from both the Applicant and relevant Interested Party(ies) as to why it has not been possible to submit the final and completed (signed and dated) versions of the relevant SoCG(s);
- Comments on responses submitted for Deadline 6a;
- Responses to any further information requested by the ExA;
- Comments on the RIES (if required).
6 Mehefin 2022 - Deadline 7a
CaeedigDeadline 7a
Deadline for receipt by the ExA of:
- Comments on responses submitted for Deadline 7;
- Response to any further information requested by the ExA;
- A final update regarding progress that has been made with Affected Persons in respect of Compulsory Acquisition (CA) and Temporary Possession (TP) (or confirmation that no changes have been made since Deadline 6a);
- The final Book of Reference (or confirmation that no changes have been made since Deadline 6a);
- The final CA/ TP schedule (or confirmation that no changes have been made since Deadline 6a);
- The final Guide to the Application (or confirmation that no changes have been made since Deadline 6a);
- Final preferred version of the Applicant’s DCO in the SI template validation report and validated copy of the DCO (or confirmation that no changes have been made since Deadline 6a);
- Final preferred version of the Applicant's DCO in word format (or confirmation that no changes have been made since Deadline 6a).
7 Mehefin 2022 - End of Examination
CaeedigThe ExA is under a duty to complete the Examination of the application by the end of the period of 6 months. Please note that the ExA may close the Examination before the end of the six month period if he is satisfied that all relevant matters have been addressed and discussed.