Amserlen yr archwiliad
Mae amserlen yr archwiliad yn dangos dyddiadau digwyddiadau a therfynau amser ar gyfer cyflwyniadau.
Os ydych wedi cofrestru i leisio'ch barn, gallwch wneud hyn yn ystod y cam archwilio.
Y cam archwilio
Agorodd yr archwiliad ar 6 February 2024
Caeodd yr archwiliad ar 6 August 2024
16 Ionawr 2024 - Pre-Exam Procedural Deadline
CaeedigPre-Exam Procedural Deadline
Deadline for receipt by the ExA of:
- Responses to the Rule 6 letter
- Responses to Relevant Representations (RRs)
- Responses (if applicable) to the Rule 9 letter of 20 September 2023
- Summaries of all RRs exceeding 1500 words
- Submission of Pre-examination Progress Tracker
- Applicant’s submission of the Land Rights Tracker
- Applicant’s submission of draft Statement of Commonality for Statements of Common Ground
- Requests to be heard orally at the Preliminary Meeting and under which part of the agenda
- Requests by Interested Parties to be heard orally at the Open Floor Hearing 1
- Notification of intention to attend the Issue Specific Hearing(s) under which part of the agenda
- Request by Interested Parties to attend Accompanied Site Inspection (ASI)
- Suggested locations for the ASI including justification, and whether such locations can be seen from public land or requires private access, for consideration by the ExA
6 Chwefror 2024 - Preliminary Meeting
CaeedigPreliminary Meeting (PM)
6 Chwefror 2024 - Open Floor Hearing
CaeedigOpen Floor Hearing (OFH)
7 Chwefror 2024 - Issue Specific Hearing 1 (ISH1)
CaeedigIssue Specific Hearing (ISH1)on Environmental Matters
8 Chwefror 2024 - Issue Specific Hearing (ISH1) (continued if required)
CaeedigIssue Specific Hearing (ISH1)on Environmental Matters (Continued if required)
8 Chwefror 2024 - Issue Specific Hearing (ISH1) (continued if required) AM only
CaeedigIssue Specific Hearing (ISH1)on Environmental Matters(continued if required)AM only
28 Chwefror 2024 - Deadline 1
CaeedigDeadline 1
Deadline for receipt by the ExA of:
- Comments on any updates to application documents submitted by the Applicant before or at the PM
- Written Representations (WRs) including summaries if exceeding 1500 words
- Local Impact Reports
- Comments on the Applicant’s draft Statement of Commonality of Statements of Common Ground
- Responses to ExA’s request for statement on the new National Policy Statement for Energy
- Notification by Statutory Parties of their wish to be considered as an IP by the ExA
- Requests from Affected Persons to be heard at any subsequent Compulsory Acquisition Hearing(CAH). Requests by Affected Persons (defined in section 59(4) of the Planning Act 2008) to be heard at a CAH
- Requests from Interested Parties to be heard at any subsequent Open Floor Hearing (OFH)
- Post-hearing submissions including written submissions of oral cases
- Notification of wish to have future correspondence received electronically
- Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010
- Comments on any further information/submissions accepted by the ExA
- Summaries of all RRs exceeding 1500 words (if not provided at the Pre-Examination
- Responses to RRs (if not provided at the Pre-Examination Procedural Deadline)
20 Mawrth 2024 - Deadline 2
CaeedigDeadline 2
Deadline for receipt by the ExA of:
- Responses to WRs
- Responses to LIRs
- Responses to any written questions arising from OFH1 and/or ISH1 (if required)
- Comments on any further information/submissions received by Deadline 1
- Applicant’s Mid-examination Progress Tracker
- Applicants National Policy Statement Tracker
- Applicant’s first update to the draft DCO
- Applicant’s first update to the Land Rights Tracker
- Applicant’s first update to the Guide to the Application
- Applicant’s first update to the Statements of Commonality of Statements of Common Ground
- Applicant’s draft itinerary for the ASI (if required)
- Any other updated documents and statements from the Applicant deemed necessary following its responses at Deadline 1
- Any further information requested by the ExA under Rule 17 of The Infrastructure Planning(Examination Procedure) Rules 2010
3 Ebrill 2024 - Publication of
CaeedigPublication of:
- Written Questions (ExQ1)
25 Ebrill 2024 - Deadline 3
CaeedigDeadline 3
Deadline for receipt by the ExA of:
- Responses to Written Questions (ExQ1)
- Comments on the Applicant’s first update to the draft DCO
- Comments on the Applicant’s first update to the Land Rights Tracker
- Comments on the first update to the Statements of Commonality of Statements of Common Ground
- Comments on the Applicant’s draft itinerary for the ASI (if required)
- Notification of wish to attend an Accompanied Site Inspection (ASI) (if required)
- Draft s106 Heads of Terms (if required)
- Any further information requested by the ExA under Rule 17 of The Infrastructure Planning(Examination Procedure) Rules 2010
- Comments on any further information/submissions received by Deadline 2
13 Mai 2024 - Open Floor Hearing 2 (OFH2) (if required)
CaeedigOpen Floor Hearing 2 (OFH2) (if required)
14 Mai 2024 - Accompanied Site Inspection (ASI)
CaeedigAccompanied Site Inspection (ASI)
15 Mai 2024 - Issue Specific Hearing 2 (ISH2)
CaeedigIssue Specific Hearing 2 (ISH2)
16 Mai 2024 - Issue Specific Hearing (ISH2) (continued if required)
CaeedigIssue Specific Hearing (ISH2) (continued if required)
17 Mai 2024 - Compulsory Acquisition Hearing 1 (CAH1) ( if required) AM only
CaeedigCompulsory Acquisition Hearing 1 (CAH1) (if required) AM only
21 Mai 2024 - Compulsory Acquisition Hearing 1 (CAH1) (Continued if required)
CaeedigCompulsory Acquisition Hearing 1 (CAH1) (Continued if required)
3 Mehefin 2024 - Deadine 4
CaeedigDeadline 4
Deadline for receipt by the ExA of:
- Post-hearing submissions including written submissions of oral cases (if required)
- Applicant’s Mid-examination Progress Tracker
- Applicant’s second update to the draft DCO
- Applicant’s second update to the Land Rights Tracker
- Applicant’s second update to the Guide to the Application
- Applicant’s second update to the Statements of Commonality of Statements of Common Ground
- Draft s106 Agreement(s) (if required)
- Any further information requested by the ExA under Rule 17 of The Infrastructure Planning(Examination Procedure) Rules 2010
- Comments on any further information/submissions received by Deadline 3
18 Mehefin 2024 - Publication by the ExA of
CaeedigPublication by the ExA of:
- Further Written Questions (ExQ2) (if required)
- Report on the Implications for European Sites (RIES)
- ExA’s commentary on, or schedule of changes to, the draft DCO (if required)
9 Gorffennaf 2024 - Deadline 5
CaeedigDeadline 5
Deadline for receipt by the ExA of:
- Responses to ExA’s Further Written Questions(ExQ2) (if required)
- Comments on the RIES
- Comments on the Applicant’s second update to the draft DCO
- Comments on the Applicant’s second update to the Land Rights Tracker
- Comments on ExA’s commentary on, or schedule of changes to, the draft DCO (if required)
- Completed and Signed Statements of Common Ground
- Final Statement of Commonality of Statements of Common Ground
- Any further information requested by the ExA under Rule 17 of The Infrastructure Planning(Examination Procedure) Rules 2010
- Comments on any further information/submissions received by Deadline 4
18 Gorffennaf 2024 - Reserve Date for ASI2 (NO LONGER REQUIRED)
CaeedigReserve Date for ASI2 (NO LONGER REQUIRED)
23 Gorffennaf 2024 - Reserve Date(s)
CaeedigDates reserved (NO LONGER REQUIRED) Monday 22 July 2024 and/or Tuesday 23 July for:
- ISH3 and/or CAH2 (NO LONGER REQUIRED)
1 Awst 2024 - Deadline 6
CaeedigDeadline 6
Deadline for receipt by the ExA of:
- Final Principal Areas of Disagreement Statements
- IPs Closing Statement(s) (if desired)
- Post-hearing submissions including written submissions of oral cases (if applicable)
- Applicant’s Closing Statement(s)
- Applicant’s Close of Examination Progress Tracker
- Applicants Final National Policy Statement Tracker
- Final draft DCO to be submitted by the Applicant in the SI template with the SI template validation report
- Final Book of Reference (BoR) and schedule of changes to BoR
- Completed s106 Agreements (if required)
- Final Land Rights Tracker
- Final Guide to the Application
- Any further information requested by the ExA under Rule 17 of The Infrastructure Planning(Examination Procedure) Rules 2010al Guide to the Application
- Comments on any further information/submissions received by Deadline 5
6 Awst 2024 - Close of Examination
CaeedigThe ExA is under a duty to complete the Examination of the application by the end of the period of six months.