5 June 2023 - Hearings (if required)
Hearings (if required)
W/c 5 June 2023 is reserved for any:
- Issue Specific Hearing(s) (if required)
- Open Floor Hearing(s) (if required)
- Compulsory Acquisition Hearing(s) (if required)
13 June 2023 - Deadline 8
OpenDeadline 8
For receipt by the Examining Authority of:
- Post-hearing submissions, including written summaries of oral submissions to the hearings (if held)
- Comments on progressed Statements of Common Ground (if any)
- Comments on any other responses received by Deadline 7
- Applicant’s updated Application Guide in clean and tracked versions
- Applicant’s updated Application Document Tracker in clean and tracked versions
- Applicant’s updated draft Development Consent Order in clean and tracked versions
- Applicant’s Schedule of Changes to the draft Development Consent Order
- Applicant’s updated Schedule of Negotiations and Powers Sought in clean and tracked versions
- Applicant’s updated National Policy Statement tracker (if required) in clean and tracked versions
- Applicant’s updated Book of Reference (BoR) and Schedule of Changes to the BoR (if required) in clean and tracked versions
- Any further information requested by the Examining Authority under Rule 17
14 June 2023 - Publication of the RIES (if required)
Publication by the Examining Authority of:
- The Report on the Implications for European Sites (if required) and any associated questions
21 June 2023 - Publication of the ExA's proposed schedule of changes to the dDCO (if required)
Publication by the Examining Authority of:
- The Examining Authority’s proposed schedule of changes to the draft Development Consent Order (if required)
5 July 2023 - Deadline 9
Deadline 9
For receipt by the Examining Authority of:
- Responses to the Report on the Implications for European Sites (if issued)
- Responses to the Examining Authority’s proposed schedule of changes to the draft Development Consent Order (if issued)
- Comments on responses received by Deadline 8
- Signed and dated s106 Agreement(s) (if required)
- Finalised Statements of Common Ground
- Finalised Statement of Commonality for Statements of Common Ground
- List of matters not agreed where any Statement of Common Ground could not be finalised
- Applicant’s final Application Guide in clean and tracked versions
- Applicant’s final Application Document Tracker in clean and tracked versions
- Applicant’s final Schedule of Negotiations and Powers Sought in clean and tracked versions
- Applicant’s final National Policy Statement tracker in clean and tracked versions
- Applicant’s final draft Development Consent Order (Microsoft Word) in clean and tracked versions
- Applicant’s final draft Development Consent Order (PDF) in clean and tracked versions
- Applicant’s final draft Development Consent Order (dDCO) to be submitted in the SI template with the SI template validation report
- Applicant’s finalised Schedule of Changes to the draft Development Consent Order
- Applicant’s final Book of Reference (BoR) and Schedule of Changes to the BoR in clean and tracked versions
- Any further information requested by the Examining Authority under Rule 17
17 July 2023 - Deadline 10
Deadline 10
For receipt by the Examining Authority of:
- Any further information requested by the Examining Authority under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010
17 July 2023 - Close of Examination
The Examining Authority is under a duty to complete the examination of the application by the end of the period of six months