8 October 2024 - Pre-Exam Procedural Deadline
OpenPre-Exam Procedural Deadline
Deadline for receipt by the Examining Authority (ExA) of:
- Responses to the Rule 6 letter including any written submissions on the Examination Procedure and Examination Timetable, including any submissions about the use of virtual methods
- Requests to be heard orally at the Preliminary Meeting including which agenda items you wish to speak on, points you want to make and why these need to be made orally rather than in writing
- Responses to Relevant Representations (RRs) (please read PD7 of Annex F of this letter)
- Summaries of all RR exceeding 1500 words
- Request to participate in the Compulsory Acquisition Hearing on 22 October 2024 (please see Annex E of this letter)
- Request to participate in Issue Specific Hearing 1 on 23 October 2024 (please see Annex E of this letter)
- Suggested locations for an Accompanied Site Inspection, including the reason for the nomination, issues to be observed there and whether the locations require access to private land (please read PD6 of Annex F of this letter)
- Other
22 October 2024 - Preliminary Meeting (PM)
The Preliminary Meeting for the Dogger Bank South Offshore Wind Farms Development Consent Order Application is to be held by virtual means using Microsoft Teams. This meeting will commence at 10:00 on Tuesday 22 October 2024.
A livestream will be available for this event.
22 October 2024 - Compulsory Acquisition Hearing 1 (CAH1)
A Compulsory Acquisition Hearing for the Dogger Bank South Offshore Wind Farms Development Consent Order Application is to be held by virtual means using Microsoft Teams. This meeting will commence at 14:00 on Tuesday 22 October 2024.
A livestream will be available for this event.
23 October 2024 - Issue Specific Hearing 1 (ISH1)
Issue Specific Hearing (ISH1) on the scope of the Proposed Development, including construction activities and the principles of the Applicant’s draft Development Consent Order (DCO). This Issue Specific Hearing for the Dogger Bank South Offshore Wind Farms Development Consent Order Application is to be held by virtual means using Microsoft Teams. This meeting will commence at 09:30 on Wednesday 23 October 2024.
A livestream will be available for this event.