17 January 2025 - Deadline 3
OpenDeadline 3 (D3)
For receipt by the ExA of:
Responses to ExQ1
Comments on any further information or submissions received at Deadline 2
Updated Land Rights Tracker
Updated Examination Tracker
Updated Policy Tracker (if required)
Updated SoCG and Statement of Commonality (as required)
Notification of wish to attend ASI
Updated BoR and Schedule of Changes to the BoR, in clean and tracked versions (if required)
Updated dDCO in clean, tracked and Word versions, schedule of changes to the dDCO and updated Explanatory Memorandum (if required)
Updated Application Guide (Application Document Tracker) (if required) in clean and tracked versions
Any further information requested by ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010
10 February 2025 - Hearings
Week commencing Monday 10 February 2025 (if required) for:
Issue Specific Hearing 2 (ISH2) draft Development Consent Order (dDCO)
Any further Issue Specific Hearings (If required)
Compulsory Acquisition Hearing 2 (CAH2) (If required)
Open Floor Hearing (OFH2) (if required)
Accompanied Site Inspection (ASI)
25 February 2025 - Deadline 4
Deadline 4 (D4)
For receipt by the ExA of:
Post hearing submissions, including written summaries of oral submissions and any information requested by the ExA at the Hearings w/c 10 February 2025
Comments on any other information or submissions submitted at Deadline 3
Updated Land Rights Tracker
Updated Examination Tracker
Updated Policy Tracker (if required)
Updated SoCG and Statement of Commonality (if required)
Updated BoR and Schedule of Changes to the BoR, in clean and tracked versions (if required)
Updated dDCO in clean, tracked and Word versions, schedule of changes to the dDCO and updated Explanatory Memorandum (if required)
Updated Schedule of Changes to the dDCO (if required)
Updated Application Guide (Application Document Tracker) (if required) in clean and tracked versions
Any further information requested by ExA under Rule 17 of the Examination Rules
11 March 2025 - Publication by the ExA 2
Publication by the ExA of:
- Second Written Questions (ExQ2) (if required)
25 March 2025 - Deadline 5
Deadline 5 (D5)
For receipt by the ExA of:
Response to ExQ2 (if required)
Comments on any other information or submission submitted at D4
Updated Land Rights Tracker
Updated Examination Tracker
Updated Policy Tracker (if required)
Updated SoCG and Statement of Commonality (if required)
Updated BoR and Schedule of Changes to the BoR, in clean and tracked versions (if required)
Updated dDCO in clean, tracked and Word versions, schedule of changes to the dDCO and updated Explanatory Memorandum (if required)
Updated Schedule of Changes to the dDCO (if required)
Updated Application Guide (Application Document Tracker) (if required) in clean and tracked versions
Final draft of Planning Obligation
Any further information requested by ExA under Rule 17 of the Examination Rules
8 April 2025 - Publication by the ExA 3
Publication by the ExA of:
Report on the Implications for European Sites (RIES) and any associated questions (if required)
ExA’s commentary on, or schedule of changes to, the dDCO
29 April 2025 - Deadline 6
Deadline 6 (D6)
For receipt by the ExA of:
Comments on the RIES and responses to any associated questions (if issued)
Comments on any other information submitted at D5
Any further information requested by ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010
2 May 2025 - Deadline 7
Deadline 7
For receipt by the ExA of:
Final Land Rights Tracker
Final Examination Tracker
Final Policy Tracker (if required)
Final SoCG and Statement of Commonality
List of matters not agreed where SoCG could not be finalised
Final BoR and Schedule of Changes to the BoR, in clean and tracked versions
Final dDCO to be submitted by the Applicant in the SI template. Applicant to provide the email notification from https://publishing.legislation.gov.uk/validation confirming the document has successfully passed validation, and the PDF version of the SI validation report obtained from the link in the notification email. Final dDCO in clean, tracked and Word versions.
Final schedule of changes to the dDCO and updated Explanatory Memorandum
Final Application Guide (Application Document Tracker) in clean and tracked versions
Final Statement of Reasons in clean and tracked versions
Final Status of Negotiations with Statutory Undertakers
Completed section 106 agreement
Closing Statements
Any further information requested by ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010
5 May 2025 - Close of Examination
The ExA is under a duty to complete the Examination of the application by the end of the period of six months