13 January 2025 - Examining Authority's Further Written Questions (ExQ2)
Publication of the Examining Authority's Further Written Questions (ExQ2) (if required)
3 February 2025 - Deadline 4
OpenDeadline 4
Deadline for receipt by the ExA of:
- Responses to ExQ2 (if published)
- Comments on the Applicant’s update to the draft DCO
- Comments on the Applicant’s update to the Land Rights Tracker
- Applicant’s update to the draft DCO
- Applicant’s update to the Land Rights Tracker
- Applicant’s update to the Guide to the Application
- Applicant’s update to the Statements of Commonality of Statements of Common Ground
- Comments on any other submissions received at Deadline 3
- Updated report on the inter-relationship with other infrastructure projects (as described in Annex B)
- Any further information requested by the ExA under Rule 17 of the Examination Procedure Rules
11 February 2025 - Hearing Dates
Tuesday 11 - Friday 14 February 2025
Dates reserved (if required) for:
- Any Compulsory Acquisition Hearing
- A further Open Floor Hearing (if requested)
- Any Issue Specific Hearing
- Accompanied Site Inspection
17 February 2025 - Publication of RIES and Examining Authority's preferred draft DCO
Issue by the ExA of:
- The Report into the Implications for European Sites (RIES) (if required)
- The ExA’s preferred draft DCO, proposed schedule of changes, or commentary on the draft DCO (if required)
13 March 2025 - Deadline 5
Deadline 5
Deadline for receipt by the ExA of:
- Post-hearing submissions including written summaries of oral case put at hearings during w/c 10 February 2025 (if held)
- Comments on the Applicant’s third update to the draft DCO
- Comments on the Applicant’s third update to the Land Rights Tracker
- Comments on the Report into the Implications for European Sites (RIES) (if required)
- Comments on ExA’s commentary on, or schedule of changes to, the draft DCO (if required)
- Completed, signed and dated Statements of Common Ground
- Final Statement of Commonality of Statements of Common Ground
- Comments on any other submissions received at Deadline 4
- Any further information requested by the ExA under Rule 17 of the Examination Procedure Rules
21 March 2025 - Dates reserved for hearings
Tuesday 18 - Friday 21 March 2025
Dates reserved (if required) for:
- Any Compulsory Acquisition Hearing
- Any Issue Specific Hearing
- Accompanied Site Inspection
4 April 2025 - Deadline 6
Deadline 6
Deadline for receipt by the ExA of:
- Post-hearing submissions including written summaries of oral case put at hearings during w/c 18 March 2025 (if held)
- Final Principal Areas of Disagreement Statements
- IP’s Closing Statement(s)
- Post-hearing submissions including written submissions of oral cases (if applicable)
- Applicant’s Closing Statement(s)
- Applicant’s Close of Examination Progress Tracker
- Final draft DCO to be submitted by the Applicant in the SI template with the SI template validation report
- Final Explanatory Memorandum in clean and tracked versions
- Final Book of Reference (BoR) and schedule of changes to BoR
- Applicant’s final Schedule of Negotiations and Powers Sought in clean and tracked versions
- Completed s106 Agreements (if required)
- Final Land Rights Tracker
- Final planning obligations and commercial side agreements tracker
- Final Guide to the Application
- Final schedule of changes to the draft DCO (if required)
- Comments on any other submissions received at Deadline 5
- Final report on the inter-relationship with other infrastructure projects (as described in Annex B)
- Any further information requested by the ExA under Rule 17 of the Examination Procedure Rules
10 April 2025 - End of Examination
The ExA is under a duty to complete the examination of the application by the end of the period of six months. Please note that the ExA may close the Examination before the end of the six-month period if it is satisfied that all relevant matters have been addressed and discussed.