11 December 2023 - CA Regulations Deadline 3 (CA Regs D3)
OpenCA Regulations Deadline 3 (CA Regs D3)
- Comments on any information received
- Comments or any additional information/submissions received by CA Regs D2.
14 December 2023 - Issue Specific Hearing 4 (ISH4)
Issue Specific Hearing 4 (ISH4)
under Regulation 14 of the CA Regulations
14 December 2023 - Compulsory Acquisition Hearing 2 (CAH2)
Compulsory Acquisition Hearing 2 (CAH2)
under Regulation 15 of the CA Regulations
14 December 2023 - Open Floor Hearing 3 (OFH3)
Open Floor Hearing 3 (OFH3)
under Regulation 15 of the CA Regulations
21 December 2023 - Deadline 6 (D6)
Deadline 6 (D6)
For receipt by the ExA of:
- Comments on ExA DCO (if required)
- Final DCO
- Final DCO to be submitted by the Applicant in the SI template with the SI template validation report (in clean and tracked changed versions)
- Final updated BoR
- Final BoR (in clean and tracked changed versions) and schedule of changes to BoR
- Final SoCGs (in clean and tracked changed versions)
- Final Statement of Commonality and Statements of Common Ground (in clean and tracked changed versions)
- List of matters not agreed where SoCG could not be finalised (in clean and tracked changed versions)
- Final Navigation Document/Guide to the application (in clean and tracked changed versions)
- Final Status of Negotiations CA Schedule (in clean and tracked changed versions)
- Final Status of Negotiations with Statutory Undertakers (in clean and tracked changed versions)
- Final NPS tracker (in clean and tracked changed versions)
- Final signed and dated section 106 (if required)
- Comments on any further information received
- Comments on any additional information/submissions received by Deadline 5
- Any further information requested by ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010
4 January 2024 - Deadline 7 (D7)
Deadline 7 (D7)
For receipt by the ExA of:
- Summary statements from parties regarding matters that they have previously raised during the examination that have not been resolved to their satisfaction.
- Comments on any further information received
- Comments on any additional information/submissions received by Deadline 6
- Any further information requested by ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010
5 January 2024 - Close of Examination
The Examining Authority is under a duty to complete the examination of the application by the end of the period of six months