Representation by Health and Safety Executive (Health and Safety Executive )
- Date submitted
- 16 January 2024
- Submitted by
- Members of the public/businesses
Based on the revised order limits ‘redline’, in drawing CR1/C2.1_A_CR December 2023 downloaded from infrastructure.planninginspectorate.gov.uk/wp-content/ipc/uploads/projects/EN010133/EN010133-000115-C2.1 Location Plan.pdf, this NSIP application falls into an additional consultation zone of an additional major accident hazard site. The major accident hazard site is EDF Energy Cottom Power Station, HSE reference #4154. The Applicant should make contact with the above site operator, to inform an assessment of whether or not the proposed development is vulnerable to a possible major accident.