Stonestreet Green Solar Examination timetable

The examination timetable shows the dates of events and deadlines for submissions.

If you have registered to have your say, you can do this in the examination stage.

The examination stage

The examination opened on 19 November 2024

The examination is expected to close on 19 May 2025

Have your say

Upcoming deadlines and events

7 January 2025 - Deadline 2

Open

Deadline 2

For receipt by the ExA of:

  • Comments on Written Representations
  • Comments on the Local Impact Reports
  • The Applicant’s revised dDCO
  • Status of Negotiations / Compulsory Acquisition Schedule
  • Draft Statements of Common Ground – see Annex D
  • Statement of Commonality on Statements of Common Ground
  • Comments on any further information/additional submissions received by Deadline 1
  • Any further information requested by the ExA

10 January 2025 - Publication by the ExA of

Publication by the ExA of:

  • The ExA’s First Written Questions (ExQ1)

31 January 2025 - Deadline 3

Deadline 3

For receipt by the ExA of:

  • Responses to ExQ1

  • Interested Parties are required to notify the Examining Authority (ExA) in writing of their wish to take part in an Open Floor Hearing (OFH) or Compulsory Acquisition Hearing (CAH)

21 February 2025 - Publication by the ExA of 2

Publication by the ExA of:

  • The ExA’s final itinerary for the ASI (if required)

24 February 2025 - Dates reserved for ASIs and hearings

ASI and Hearings

Dates reserved for ASIs and hearings wc 24 February 2024:

  • Further ISHs (if required)
  • CAH (if required)
  • Further OFHs (if required)
  • ASIs (if required)

11 March 2025 - Deadline 4

Deadline 4

For receipt by the ExA of:

  • Post-Hearing Submissions, including written summaries of oral submissions and any documents requested by the ExA
  • Comments on the Applicant’s revised dDCO at Deadline 3
  • Comments on any additional submissions received by Deadline 3
  • Any further information requested by ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010

25 March 2025 - Publication by the ExA of 3

Publication by the ExA of:

  • Report on the Implications for European Sites (RIES) and any associated questions (if required)

  • The ExA’s Second Written Questions (ExQ2) (if required)

15 April 2025 - Deadline 5

Deadline 5

For receipt by the ExA of:

  • Responses to ExQ2
  • Comments on the Applicant’s revised dDCO
  • Comments on any additional submissions received by Deadline 4
  • Any further information requested by ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010

22 April 2025 - Deadline 6

Deadline 6

For receipt by the ExA of:

  • Updated DCO
  • Updated BoR
  • Updated SoCG
  • Comments on the RIES (if required)
  • Comments on any additional submissions received by Deadline 5
  • Any further information requested by ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010

29 April 2025 - Deadline 7

Deadline 7

For receipt by the ExA of:

  • Comments on Deadline 6 submissions

6 May 2025 - Deadline 8

Deadline 8

For receipt by the ExA of:

  • Final DCO to be submitted by the Applicant in the SI MS Word template. Applicant to provide the email notification from https://publishing.legislation.gov.uk/validation confirming the document has successfully passed validation, and the PDF version of the SI validation report obtained from the link in the notification email. The Applicant should also provide a clean (all tracking removed) standalone MS Word version of the dDCO, with no header or cover page.

  • Final updated BoR and schedule of changes to BoR

  • Final SoCG

  • Final Statement of Commonality of SoCG

  • List of matters not agreed where SoCG could not be finalised

  • Final Navigation Document/Guide to the application

  • Final Status of Negotiations CA Schedule

  • Final Status of Negotiations with Statutory Undertakers

  • Final NPS tracker

  • Final signed and dated section 106 – if needed

  • Comments on any further information received

  • Comments on any additional information/submissions received by Deadline 5

  • Responses to ExQ2 and RIES (if issued)

  • Any further information requested by ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010

19 May 2025 - Close of Examination by the Examining Authority

Close of Examination by the Examining Authority

The ExA is under a duty to complete the Examination of the application by the end of the period of six months

Past deadlines and events

5 November 2024 - Procedural Deadline A

Closed

Procedural Deadline A

Deadline for receipt by ExA of:

  • Written submissions on Examination Procedure, including any submissions about the draft Examination Timetable and the use of virtual methods
  • Requests to be heard at the Preliminary Meeting
  • Requests to be heard at Issue Specific Hearing 1 (ISH1) regarding the draft Development Consent Order and general principles of the proposed development
  • Requests to be heard at Issue Specific Hearing 2 (ISH2) regarding Construction Traffic
  • Requests to be heard at an Open Floor Hearing 1 (OFH1)
  • Requests to be heard at a Compulsory Acquisition Hearing (CAH1) Requests by Affected Persons (defined in section 59(4) of the Planning Act 2008) to be heard at a Compulsory Acquisition Hearing (CAH)

19 November 2024 - Open Floor Hearing 1 (OFH1)

Closed

Open Floor Hearing 1 (OFH1)

19 November 2024 - Preliminary Meeting

Closed

Preliminary Meeting (PM)

20 November 2024 - Issue Specific Hearing 1 (ISH1)

Closed

Issue Specific Hearing 1 (ISH1) regarding the draft Development Consent Order and general principles of the proposed development

20 November 2024 - Compulsory Acquisition Hearing (CAH1)

Closed

Compulsory Acquisition Hearing (CAH1)

21 November 2024 - Issue Specific Hearing 2 (ISH2)

Closed

Issue Specific Hearing 2 (ISH2) regarding Construction Traffic

10 December 2024 - Deadline 1

Closed

Deadline 1

For receipt by the ExA of:

  • Comments on Relevant Representations (RRs)

  • Written Representations

  • Summaries of all RR exceeding 1500 words

  • Post-hearing submissions, including written submissions of oral cases

  • Notification of wish to have future correspondence received electronically

  • Suggestions for locations for the ASI (if any) together with reasoning

  • Any further information requested by the ExA Comments on any additional submissions accepted by the ExA

  • Local Impact Reports (LIRs)

  • Any further information requested by ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010

  • Comments on any further information/submissions accepted by the ExA