8 Ionawr 2025 - Deadline 7a
AgorDeadline 7a
- Requests to be heard orally at the Open Floor Hearing from additional affected persons or additional interested parties
- Requests to be heard orally at a Compulsory Acquisition Hearing) from additional affected persons or additional interested parties
- Written Representations (WRs) (in accordance with Regulation 13 of the CA Regulations)
- Comments on the CA Regulations RRs received by Deadline 6a
10 Ionawr 2025 - Deadline 7
AgorDeadline 7
For receipt by the ExA of:
- Response to Third Written Questions (if issued)
- Comments on the ExA’s commentary on, or schedule of changes to, the draft DCO
- Comments on any additional information/submissions received by Deadline 6
- Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010
14 Ionawr 2025 - Issue Specific Hearing 8 (ISH8)
Issue Specific Hearing 8 (ISH8)
15 Ionawr 2025 - Compulsory Acquisition Hearing 2 (CAH2), Issue Specific Hearing 9 (ISH9) and Open Floor Hearing 5 (OFH5)
- Compulsory Acquisition Hearing 2 (CAH2) held under Reg 15
- Issue Specific Hearing 9 (ISH9) held under Reg. 14
- Open Floor Hearing 5 (OFH5) held under Reg. 16
All the above hearings will be held for additional APs or IPs as a consequence of the additional land or rights sought arising from Change 1 (if required)
16 Ionawr 2025 - Time reserved for continuation of ISH8, CAH2, ISH9 and OFH5 (if required)
Time reserved for continuation of ISH8, CAH2, ISH9 and OFH5 (if required)
17 Ionawr 2025 - Deadline 8
Deadline 8
For receipt by the ExA of:
- Comments on the REIS (if issued)
- Comments on responses to Third Written Questions (if required)
- Final dDCO to be submitted by the Applicant in the SI template with the SI template validation report
- Final Schedule of Changes to the dDCO
- Final Explanatory Memorandum (EM) and schedule of changes to Explanatory Memorandum
- Final updated BoR and schedule of changes to BoR
- Final CA Schedule
- Final Status of Negotiations with Statutory Undertakers
- Final SoCG
- Final SoC
- List of matters not agreed where SoCG could not be finalised
- Final Guide to the Application
- Comments on any further information/submissions received by Deadline 7
- Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010
17 Ionawr 2025 - Deadline 8a
Deadline 8a
For receipt by the ExA of:
- Comments on WRs received at Deadline 7a
23 Ionawr 2025 - Deadline 9
Deadline 9
For receipt by the ExA of:
- Any further information requested by the ExA
23 Ionawr 2025 - Close of Examination
The ExA is under a duty to complete the Examination of the application by the end of the period of six months
23 Ionawr 2025 - Deadline 9a
Deadline 9a
For receipt by the ExA of:
- Post-hearing submissions including written submissions of oral cases as heard at the hearings held on the 15 – 16 Jan 2025