13 January 2025 - Deadline 2 (D2)
OpenFor receipt by the ExA of:
- Comments on any additional information/submissions received by Deadline 1
- Comments on the Applicant’s draft suggestions for site inspections
- Local Impact Reports (LIR) from relevant local planning authorities
- Written Representations (WR) and Summaries of WRs exceeding 1500 words
- SoCGs requested by the ExA (see Annex F, section 3) and updated SoCGs submitted at Procedural Deadline A where any substantive updates have been made
- Statement of Commonality for all SoCGs
- PADs requested by the ExA (see Annex F section 4) which were not submitted at Procedural Deadline A or any updated PADs
- The Applicant’s updated documents (see Annex F, section 6 to the Rule 6 Letter (PD-001))
- Any further information requested by ExA. Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010
27 January 2025 - Deadline 3 (D3)
For receipt by the ExA of:
- The Applicant’s updated documents (see Annex F, section 6 to the Rule 6 Letter (PD-001))
- Updated PADs where any substantive changes have been made
- Comments on any information. requested/submissions received by Deadline 2
- Any further information requested by ExA. Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010
6 February 2025 - Publication of ExQ1
Publication by the ExA of:
- The ExA's First Written Questions (ExQ1)
26 February 2025 - Deadline 4 (D4)
For receipt by the ExA of:
- Responses to the ExA’s First Written Questions (ExQ1)
- Comments on any information requested/submissions received by Deadline 3
- The Applicant’s updated documents (see Annex F, section 6 to the Rule 6 Letter (PD-001))
- Updated PADs where any substantive changes have been made
- Any further information requested by ExA. Any further information requested by the ExA under Rule 17 of the Examination Rules
10 March 2025 - Hearings
Time reserved for hearings and Site Inspections w/c 10 March 2025
- Issue Specific Hearings (ISH) (if required)
- Compulsory Acquisition Hearing 2 (CAH2) (if required)
- Open Floor Hearing 2 (OFH2) (if required)
- Site Inspections (SI1) (if required)
20 March 2025 - Deadline 5 (D5)
For receipt by the ExA of:
- Post-Hearing Submissions, comprising written summaries of oral submissions made at the Hearings held on the week commencing 10 March 2025
- Comments on any information requested/submissions received by Deadline 4
- The Applicant’s updated documents (see Annex F, section 6 to the Rule 6 Letter (PD-001))
- Updated PADs where any substantive changes have been made.
- Any further information requested by ExA. Any further information requested by the ExA under Rule 17 of the Examination Rules
27 March 2025 - Publication of ExQ2
Publication by the ExA of:
- The ExA's Second Written Questions (ExQ2)
9 April 2025 - Deadline 6 (D6)
For receipt by the ExA of:
- Responses to the ExA’s Second Written Questions (ExQ2) (if these were issued)
- Comments on any information requested/submissions received by Deadline 5
- The Applicant’s updated documents (see Annex F, section 6 to the Rule 6 Letter (PD-001))
- Updated PADs where any substantive changes have been made
- Any further information requested by ExA. Any further information requested by the ExA under Rule 17 of the Examination Rules.
14 April 2025 - Hearings 2
Time reserved for hearings w/c 14 April 2025
- Issue Specific Hearings (ISH) (if required)
- Compulsory Acquisition Hearing 3 (CAH3) (if required)
24 April 2025 - Deadline 7 (D7)
For receipt by the ExA of:
- Post-Hearing Submissions, comprising written summaries of oral submissions made at the Hearings held on the w/c 14 April 2025 (if these hearings were held)
- Comments on any information requested/submissions received by Deadline 6
- The Applicant’s updated documents (see Annex F, section 6 to the Rule 6 Letter (PD-001))
- Updated PADs where any substantive changes have been made
- Any further information requested by ExA. Any further information requested by the ExA under Rule 17 of the Examination Rules
2 May 2025 - Publications by ExA
Publication by the ExA of:
- The ExA's Third Written Questions (ExQ3) (if required)
- The ExA's commentary n, or schedule of changes to, the dDCO (if required)
- Report on the Implications for European Sites (RIES) and any associated questions (if required)
16 May 2025 - Deadline 8 (D8)
For receipt by the ExA of:
- Responses to the ExA’s Third Written Questions (ExQ3) (if these were issued)
- Comments on the ExA’s commentary on, or schedule of changes to, the dDCO (if these were issued)
- Comments on Report on the Implications for European Sites (RIES) and any associated questions (if it were issued)
- Comments on any information requested/submissions received by Deadline 7
- The Applicant’s updated documents (see Annex F, section 6 to the Rule 6 Letter (PD-001))
- Updated PADs where any substantive changes have been made
- Any further information requested by ExA. Any further information requested by the ExA under Rule 17 of the Examination Rules
23 May 2025 - Deadline 9 (D9)
For receipt by the ExA of:
- Comments on any information requested/submissions received by Deadline 8
- Final DCO and Explanatory Memorandum. Final DCO to be submitted by the Applicant in the SI template. Applicant to provide the email notification from https://publishing.legislation.gov.uk/validation confirming the document has successfully passed validation, and the PDF version of the SI validation report obtained from the link in the notification email. The Applicant should also provide a clean (all tracking removed) standalone MS Word version of the dDCO, with no header or cover page
- Final updated BoR. Final BoR and schedule of changes to BoR
- Final Statement of Reasons
- Final SoCGs
- Final Statement of Commonality of SoCG
- List of matters not agreed where SoCG could not be finalised
- Final Guide to the application
- Final Status of Negotiations CA Schedule
- Final Status of Negotiations with Statutory Undertakers
- Final NPS tracker
- Final Consents and Licences Position Statement
- Final signed and dated section 106s
- Final versions of any other of the Applicant’s documents that have been updated
- Summary statement from the Applicant setting out any outstanding matters
- Final PADs submitted by the relevant IPs
- Any further information requested by ExA. Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010
2 June 2025 - Deadline 10 (D10)
For receipt by the ExA of:
- Any further information requested by ExA. Any further information requested by the ExA under Rule 17 of The Infrastructure Planning (Examination Procedure) Rules 2010.
3 June 2025 - Close of Examination
The ExA is under a duty to complete the Examination of the application by the end of the period of six months