Project information
About the project
Type of application: Generating Stations
Name of applicant: RWE Generation UK plc
The project comprises the construction and operation of the Stallingborough CCGT generating plant and CCP which is anticipated to generate approximately 900 megawatts of electricity. Natural gas will be transported to the Main Site by a pipeline from the Ulceby and Habrough area in an easterly direction. Electricity will be supplied from the Main Site into the grid by a new electrical connection leading in a southerly direction to the existing West Grimsby substation. The Stallingborough CCGT generating plant and CCP is located within land owned by the Applicant’s Group, whereas the route for the natural gas pipeline and electricity connection, which is owned by a number of third parties, will be determined as part of the route selection and iterative environmental impact assessment processes. The potential cooling water infrastructure would be located within the Humber estuary where the foreshore is owned by the Crown Estate and the potential laydown area at the RWE CHP Grimsby site is under RWE ownership. The Main Site will be fitted with carbon capture equipment and carbon dioxide will be transported to offshore geological storage under the north sea and this transport and storage is expected to utilise the separate Viking CCS pipeline (PINS case reference EN070008). A connection between the Main Site and the Viking CCS pipeline will be delivered as a part of a separate project and consenting process.
View the developer's websiteProject stage
This project is at the pre-application stage.
The application is expected to be submitted between Oct and December 2025.
When we receive the application, we have 28 days to decide whether to accept it for examination.
If we accept the application, you will then be able to register to have your say and view all the application documents.
Pre-application
In progress
This is where the applicant starts to create their application. The applicant is required to consult with people and organisations in the area. They must also create detailed documents about the impact the project could have on the environment.
It is important to get involved at this stage to influence the application before the applicant sends it to the Planning Inspectorate.
Find out what you can do at this stage and check our detailed guides.
Acceptance
Not started
This is when the applicant sends us their application documents. We check if we can accept the application for examination. We have 28 days to make this decision.
How the acceptance stage works and what happens next.
Pre-examination
Not started
The Examining Authority is appointed and is made up of one or more inspectors. Anyone who wants to have their say needs to register at this stage.
The applicant must publish that the application has been accepted by us. They include when and how parties can register to get involved. The time period for registering is set by the applicant but must be no less than 28 days.
The pre-examination stage usually takes about 3 months.
What happens during the pre-examination stage.
Examination
Not started
The Examining Authority will ask questions about the proposed development. The applicant and anyone who has registered to have their say can get involved and submit comments at each deadline in the timetable. You can also attend hearings that may take place. This stage takes up to 6 months.
What happens at the examination stage?
Recommendation
Not started
The Examining Authority writes its recommendation report. This must be completed and sent to the relevant Secretary of State within 3 months of the end of examination stage.
Making a recommendation.
Decision
Not started
The decision stage is when the relevant Secretary of State then reviews the report and makes the final decision. They have 3 months to make a decision.
Who makes the final decision.
What happens after the decision is made
Not started
Once the Secretary of State has made a decision, challenges can be made to the High Court. All procedures must be followed when making a challenge. The High Court will decide if there are grounds for a judicial review.
This must happen within 6 weeks.
What you can do after the decision has been made.Project location
The main site for the CCGT generating plant and CCP is approximately 4km south east of Immingham.
Get updates
Enter your email address to receive:
- updates on project progress
- information on how to have your say
- notifications when key documents are published
Contact us
Telephone
If you have an interested party number, have it with you when you call.
Telephone: 0303 444 5000
Open Monday to Friday: 9am to 4pm.
Closed on weekends and bank holidays.
stallingboroughccgt@planninginspectorate.gov.uk.
When writing an email, quote the name of the project in the subject line.
We aim to respond within 10 working days.
Alternative formats
Call or email to ask for project documents in alternative formats such as PDF, large print, easy read, audio recording or braille.