The list below includes a record of advice we have provided for this project.
-
Letter received, via e-mail, by the Planning Inspectorate from Cllr Richard Parker on behalf of Compton Bishop Parish Council attached.
-
E-mail and attachment received by the Planning Inspectorate on from Claire Talbot:
I strongly object to the Hinkley Point C connection project using pylons to distribute new energy supplies across...
Read more
-
Meeting between the Planning Inspectorate and National Grid regarding the Hinkley Point C Connection project on 17 October 2013.
-
E-mail received by the Planning Inspectorate from Jane & David Anderson below:
We wish to register our horror at the plan to stop the under grounding of power cables at Webbington and so erect eno...
Read more
-
E-mail and attachment received by the Planning Inspectorate from Mr John Hayes below:
National Grid Bridgwater Seabank Connection.
Consultation Stage 4
Biddisham Against Pylons Response
...
Read more
-
E-mail and attachment received by the Planning Inspectorate from Mr Jonathan Talbot:
I strongly object to the Hinkley Point C connection project using pylons to distribute new energy supplies acro...
Read more
-
Mr Richard Parker contacted the Planning Inspectorate regarding feedback given to the developer during non-statutory consultation.
-
Meeting held between the Planning Inspectorate and National Grid to discuss the proposed Hinkley Point C Connection Project.
-
A meeting hosted at the request of local authority officers to discuss principles of the examination process, logistics, and proposed public information activities, attended by National Grid, local au...
Read more
-
A meeting with National Grid and Local Authority Officers to discuss the principles of the examination process, logistics and public information activities.
-
A meeting with National Grid to discuss logistical arrangements and the venue requirements of the examination process.
-
Proposed Hinkley to Seabank Electricty Connection. E-mail received from Mark Parish Council regarding the applicant's pre-application consultation.
-
The correspondent wrote to express their views on the consultation being undertaken by the developer and on the merits of the case; and also to copy The Planning Inspectorate into correspondence with ...
Read more
-
The Planning Inspectorate met with National Grid for a project update and practical preparations for the submission of the application.
-
Query regarding Land Agents
-
The IPC met with NG for an update on the project, consultation process and EIA approach.
-
Update on the progress of the Hinkley ? Seabank Connection project, on-going pre-application process and joint working.
-
NG met with the IPC and several external partners to provide an update on the progress of the Hinkley ? Seabank Connection project, on-going pre-application process and joint working.
-
Review progress since last meeting October 2010? What does forward programme look like?
Understand IPC discussions with National Grid Update IPC on local community groups concerns
-
National Grid wished to update the IPC on arrangements for their upcoming announcement on the proposed Hinkley Point C Connection scheme.
-
Meeting with National Grid to discuss the proposed Hinkley Point C Connection project
-
Meeting between National Grid and the IPC to provide an update on consultation and project progress
-
Meeting between National Grid and their professional team and the IPC to provide an update on consultation and project progress.
-
Mr Paul Hipwell, of No Moor Pylons, asked us to clarify advice that we had given in the past. When the IPC and No Moor Pylons met in October 2010, we discussed who had to be consulted by the IPC on th...
Read more
-
On 22 October 2010 the IPC case team met with a group of elected representatives and representatives of local stakeholder groups to discuss progress on the proposed electrical line connection between ...
Read more