Richborough Connection Project Examination timetable

The examination timetable shows the dates of events and deadlines for submissions.

If you have registered to have your say, you can do this in the examination stage.

The examination stage

The examination opened on 8 June 2016

The examination closed on 8 December 2016

Upcoming deadlines and events

There are no deadlines and events

Past deadlines and events

21 June 2016 - Deadline 1

Closed

Deadline 1

Deadline for receipt of:

• Notification of wish by an Interested Party to be heard at an Open Floor Hearing (OFH)

• Notification of wish to make oral representations at the Issue Specific Hearing (ISH) on the draft Development Consent Order (DCO), and the ISH on Broad Oak reservoir proposal, to be held on 28 and 29 July 2016

• Submission of suggested locations/sites for the Panel to include as part of its Unaccompanied Site Inspections (USIs) and for the Accompanied Site Inspection (ASI), including the issues to be observed there, information on whether the site can be accessed on public land and reasoning for each nominated site

• Notification by an Interested Party of its wish to attend the ExA’s ASI

• Applicant’s updated HRA matrices to inform the Report on the Implications for European Sites (RIES) Notification from Statutory Parties, or a local authority without direct responsibility in the proposed development area, of a wish to be considered an Interested Party

29 June 2016 - Notification by the ExA (1)

Closed

Issue by the ExA of:

• Notification of the date, time and place of the ASI to be held on 25 and 26 July 2016

• Notification of date, time and place of the OFHs to be held on 27 July 2016

• Notification of the date, time and place of the first DCO ISH to be held on 28 July 2016

• Notification of the date, time and place of the ISH on the effect of the Broad Oak reservoir proposal to be held on 29 July 2016

14 July 2016 - Deadline 2

Closed

Deadline 2

Deadline for receipt of:

• Comments on Relevant Representations (RRs) including summaries of any RR over 1500 words

• Written Representations (WRs) by all Interested Parties including summaries of all WRs exceeding 1500 words

• Local Impact Report (LIR) from local authorities

• Submission by the Applicant of the Schedule requested by the ExA bringing together all mitigation needs (see Annex B of Rule 8 letter)

• Responses to ExA’s first written questions

• Revised draft DCO from the Applicant and any draft agreements

• Statements of Common Ground requested by ExA

• Additional photomontages by the Applicant (see Annex B of Rule 8 letter)

• Submission of the schedule requested by the ExA in relation to Crown Land and interests including how the Applicant intends to comply with section 135 PA2008

• Submission of the schedule requested by the ExA in relation to statutory undertakers’ land and special category land and extinguishment of rights and removal of apparatus of statutory undertakers etc. including how the Applicant intends to satisfy sections 127, 132 and 138 PA2008

• Comments on the information submitted by the Applicant dated 12 and 15 April 2016

Any other updated documents from Interested Parties (including corrections and omissions from the Applicant)

• Any other information requested by the ExA under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010 (the Exam Rules)

25 July 2016 - Accompanied Site Inspection Day 1

Closed

Dates reserved for ASI

26 July 2016 - Accompanied Site Inspection Day 2

Closed

Dates reserved for ASI

27 July 2016 - Open Floor Hearing

Closed

OFHs (if requested) which will potentially include an evening session

28 July 2016 - First ISH on DCO

Closed

ISH on the DCO including Schedule 9 deemed Marine Licence and any other agreements

29 July 2016 - ISH on the effect on Broad Oak Reservoir

Closed

ISH on the effect of the Broad Oak reservoir proposal on the Application

4 August 2016 - Deadline 3

Closed

Deadline 3

Deadline for receipt by the ExA of:

• Comments on WRs

• Responses to comments on RRs

• Comments on Local Impact Reports

• Comments on responses to ExA’s first written questions

• Comments on Applicant’s updated HRA matrices to inform the RIES

• Updates to Statements of Common Ground requested by ExA

• Comments on any submissions in relation to Crown Land and interests and compliance with section 135 PA2008 submitted for Deadline 2

• Comments on any submission in relation to statutory undertakers’ land and special category land and extinguishment of rights and removal of apparatus of statutory undertakers etc

• Comments on any other updated documents from Interested Parties (including corrections and omissions from the Applicant) submitted for Deadline 2

• Submission of post hearing documents including written summaries of the cases put orally at the OFHs held on Wednesday 27 July 2016, ISH on the DCO and ISH on the effect of the Broad Oak reservoir proposal on the application

• Notification by an affected person of wish for a Compulsory Acquisition Hearing to be held

• Any other information requested by the ExA under Rule 17 of the Exam Rules

• Additional photomontages by the Applicant (see Annex B of Rule 8 letter)

19 August 2016 - Notification by the ExA (2)

Closed

Issue by the ExA of:

• Notification of the date, time and place of the ISHs to be held on 27 to 30 September 2016 and 18 October 2016 (if required)

• Notification of the date, time and place of the Compulsory Acquisition Hearings (including statutory undertaker and special category land) to be held on 19 to 20 October 2016

• Notification of the date, time and place of any further ASI to be held on 18 October 2016 (if required)

Publication by the ExA of:

• Second round of written questions

8 September 2016 - Deadline 4

Closed

Deadline 4

Deadline for receipt of:

• Responses to ExA’s second written questions • The Applicant’s revised draft DCO

• Any written confirmation required from the Crown in relation to section 135 PA2008 providing documentary confirmation that no interests are engaged and/or the Crown authority consents

• Updated report on status of negotiations with affected persons in respect of compulsory acquisition for each plot and whether the objection has been withdrawn

• Notification of wish to make oral representations at the ISHs to be held on 27 to 30 September 2016 and 18 October 2016 (if required)

• Any other information requested by the ExA under Rule 17 of the Exam Rules

27 September 2016 - Second ISH on the DCO

Closed

ISH on the DCO including Schedule 9 deemed Marine Licence and any other agreements

28 September 2016 - Second ISH on the effect on Broad Oak Reservoir

Closed

ISH on the effect of the Application on the Broad Oak reservoir proposal

29 September 2016 - ISH on construction effects

Closed

ISH on construction effects including effects on agricultural practices

30 September 2016 - ISH on landscape, visual and biodiversity

Closed

ISH on landscape, visual and biodiversity effects including alternatives

7 October 2016 - Deadline 5

Closed

Deadline 5

Deadline for receipt of:

• Comments on responses to ExA’s second written questions

• Submission of post hearing documents including written summaries of the cases put orally at the hearings held on Tuesday 27 September to Friday 30 September 2016

• Applicant’s submission of how any changes to the design of the proposed development and/or the mitigation measures have (or have not) affected the HRA conclusions

• Any other information requested by the ExA under Rule 17 of the Exam Rules

11 October 2016 - Notification by the ExA (3)

Closed

Issue by the ExA of:

• Notification of the date, time and place of the ISHs to be held on 9 to 10 November 2016 (if required)

• Notification of date, time and place of the OFH to be held on 9 to 10 November 2016 (if required)

• Notification of the date, time and place of the Compulsory Acquisition Hearings (including statutory undertaker and special category land) to be held on 9 to 10 November 2016 (if required)

• Notification of the date, time and place of any further ASI to be held on 9 to 10 November 2016 (if required)

19 October 2016 - CAH Day 1

Closed

Compulsory Acquisition Hearings

20 October 2016 - CAH Day 2

Closed

Compulsory Acquisition Hearings

26 October 2016 - Deadline 6

Closed

Deadline 6

Deadline for receipt of:

• Submission of post hearing documents including written summaries of the cases put orally at the hearings held on Tuesday 18 October to Thursday 20 October 2016

• Notification of wish to make oral representations at the ISHs to be held on 9 to 10 November (if required)

• Comments on the Applicant’s submission of how any changes to the design of the proposed development and/or the mitigation measures have (or have not) affected the HRA conclusions

• Any other information requested by the ExA under Rule 17 of the Exam Rules

2 November 2016 - Notification by the ExA (4)

Closed

Issue by the ExA of:

• Any requests for further information by the ExA including request for comment on the published documentation (if required)

Publication by the ExA of:

• The Report on the Implications for European Sites (RIES)

9 November 2016 - Third ISH on the draft DCO and other matters

Closed

ISH on the draft DCO including Schedule 9 deemed Marine Licence and any other agreements

10 November 2016 - Day 2 of third ISH on the draft DCO and other matters (if required)

Closed

Second day of the third ISH on the draft DCO including Schedule 9 deemed Marine Licence and any other agreements(if required)

16 November 2016 - Deadline 7

Closed

Deadline 7

Deadline for receipt of:

• Submission of post hearing documents including written summaries of the cases put orally at the hearings held on Wednesday 9 November to Thursday 10 November 2016 should these hearings be considered necessary

• Applicant’s updated draft DCO in the final form the Applicant wishes it to be made

• Applicant’s Embedded Environmental Measures Schedule in its final form

• Any other information requested by the ExA under Item 19

24 November 2016 - Deadline 8

Closed

Deadline 8

Deadline for receipt of:

• Comments on the RIES

• Comments on the Applicant’s updated draft DCO

• Comments on the Applicant’s Embedded Environmental Measures Schedule

• Any final written submission by any Interested Party or Statutory Party

29 November 2016 - Notification by the ExA (5)

Closed

Issue by the ExA of:

• Examination timetable variation

• Request for further information

6 December 2016 - Deadline 9

Closed

Deadline 9

Deadline for receipt of:

• Information requested by the ExA under Rule 17 of the Examination Procedure Rules, as set out in its letter dated 29 November 2016

8 December 2016 - Close of Examination

Closed

The ExA is under a duty to complete the examination of the application by the end of the period of 6 months beginning with the day after the close of the Preliminary Meeting.