Back

All project updates

30 September 2020

The Secretary of State has issued a Correction Order and Correction Notice for this Development Consent Order.

20 March 2020

The Secretary of State has granted development consent for this application. For further information please refer to the following decision documentation:

Notification of Decision Letter
Secretary of State Decision Letter
Development Consent Order as Made by the Secretary of State
Recommendation Report

20 March 2020

Decision made by the Secretary of State

20 December 2019

Recommendations given by the Planning Inspectorate

20 September 2019

The examination closed at 23:59 on Friday 20 September 2019.

19 September 2019

The Deadline 9 Submissions have been published.

29 August 2019

The Deadline 8 Submissions have been published.

6 August 2019

The Examining Authority has issued the Examination Timetable and Rule 17 Requests for further Information.

1 August 2019

The Deadline 7 Submissions have been published.

22 July 2019

The Deadline 6 Submissions have been published.

5 July 2019

28 June 2019

The Deadline 5 Submissions have been published.

6 June 2019

The Deadline 4 Submissions have been published.

15 May 2019

The Deadline 3 Submissions have been published.

26 April 2019

The Deadline 2 Submissions have been published.

4 April 2019

The Accompanied Site Inspection Itinerary has been published.

1 April 2019

The Deadline 1 Submissions have been published.

28 March 2019

Read the letter
The Examination Timetable (Rule 8 letter) has been sent to Interested Parties
The letter includes notification of an Accompanied Site Inspection on Thursday 11 April.
Procedural decision following Preliminary Meeting

27 March 2019

The Examination Timetable (Rule 8 letter) has been sent to Interested Parties.

Procedural decision following Preliminary Meeting.

20 March 2019

Preliminary Meeting takes place

20 March 2019

Examination begins

20 February 2019

The notification of Preliminary Meeting (Rule 6 letter) has been sent.

The letter also includes the draft Examination Timetable and Initial Assessment of Principal Issues.

7 February 2019

Relevant representations published on the website

1 February 2019

Registration of interested parties closes

13 December 2018

Registration of interested parties begins

10 December 2018

The application has been accepted for examination

13 November 2018

This application was received by the Planning Inspectorate on 12 November 2018.

The Applicant has agreed that all application documents can be published as soon as practicable upon submission to help everyone become familiar with the detail of what is being proposed in this application.

This provision is solely for the purpose of allowing more time to all those who wish to become familiar with the detail of what is being proposed ahead of the relevant representation period without lengthening the overall time required for the application process. There will be no opportunity at this stage to make comments on the application. However, if the application is accepted anyone interested in the application will be able to register and express their views during the relevant representation stage and the subsequent examination.

12 November 2018

Application received by the Planning Inspectorate