All project updates
12 Mehefin 2024
On 11 June 2024, the Secretary of State issued a Correction Notice (PDF, 134KB) and Correction Order (PDF, 103KB) to make corrections to the National Grid (Yorkshire Green Energy Enablement
Project) Development Consent Order 2024.
The Correction Order will come into force on 12 June 2024.
14 Mawrth 2024
The Secretary of State has granted consent for this application.
Information can be found in these documents:
Planning Inspectorate's notification of decision letter (PDF, 148KB)
Secretary of State for Energy Decision Letter (PDF, 314KB)
Development Consent Order as Made by the Secretary of State (PDF, 2MB)
Examining Authority's Recommendation Report (PDF, 9MB)
Regulation 31 Notice (PDF, 65KB)
Habitats Regulations Assessment (PDF, 807KB)
Post Examination Submissions (PDF, 76.6 KB)
4 Mawrth 2024
The responses to the Secretary of State's invitation to Interested Parties to comment on the information provided in response to her letter of 16 January 2024 have been published.
2 Chwefror 2024
The Secretary of State has invited Interested Parties to comment on the information provided in response to her letter of 16 January 2024 (PDF, 143 KB).
Comments should be submitted by email to YorkshireGreen@planninginspectorate.gov.uk.
The deadline for comments is 23.59 on 1 March 2024.
17 Ionawr 2024
14 Rhagfyr 2023
15 Medi 2023
14 Medi 2023
The Examination Library (PDF, 747KB) has been updated.
11 Medi 2023
- Deadline 7 submissions
- The Rule 17 Request for Information for the attention of the Applicant (PDF, 185KB)
The Examination Library will be updated as soon as practicable.
Deadline 8 (Wednesday 13 September) is the final opportunity for submissions.
16 Awst 2023
The Examining Authority’s commentary and questions on the draft Development Consent Order (DCO) (PDF 361 KB).
The Report on the Implications for European Sites (RIES) (PDF 338 KB).
All parties are welcome to comment by Deadline 7: Wednesday 6 September 2023.
Parties are reminded that the ExA may close the Examination before the end of the statutory six month period if it is satisfied that all relevant matters have been addressed. Deadline 8 is the final opportunity for submissions.
7 Awst 2023
The Examination Library (PDF, 697 KB) has been updated.
1 Awst 2023
The Examination Library (PDF, 696KB) has been updated.
20 Gorffennaf 2023
- The recordings and transcripts for Compulsory Acquisition Hearing 2 (CAH2)
- The recordings, transcripts and action points for Issue Specific Hearing 4 (ISH4)
- The Rule 17 Request for Information for the attention of Stephensons Rural LLP (PDF, 167 KB)
The Examination Library (PDF, 603 KB) has been updated.
19 Gorffennaf 2023
The following documents have now been published:
Additional Submission from Yorkshire Wildlife Trust, accepted at the discretion of the Examining Authority (PDF, 304 KB).
Action points for Compulsory Acquisition Hearing 2 (CAH2) (PDF, 104 KB).
The Examination Library (PDF, 1 MB) has been updated.
Recordings, transcripts and remaining action points for the events during the week commencing 17 July 2023 will be published as soon as practicable.
19 Gorffennaf 2023
Anyone wishing to attend the hearing who has not yet registered to attend should contact the Case Team by emailing YorkshireGreen@planninginspectorate.gov.uk.
Anyone who wishes to observe the hearings in real time should use the livestream link. Please note that the events will start broadcasting LIVE when opened by the Examining Authority. If the Livestream does not initially work it may be resolved by refreshing the webpage.
Recordings, transcripts and action points for the events during the week commencing 17 July 2023 will be published as soon as practicable.
18 Gorffennaf 2023
14 Gorffennaf 2023
- Compulsory Acquisition Hearing 2 (CAH2) on Compulsory Acquisition and Temporary Possession Matters (PDF, 209KB).
- Issue Specific Hearing 4 (ISH4) on the Draft Development Consent Order and Environmental Matters (PDF, 191 KB).
Anyone wishing to attend the hearings who has not yet registered to attend should contact the Case Team by emailing YorkshireGreen@planninginspectorate.gov.uk.
Anyone who wishes to observe the hearings in real time should use the livestream link. Please note that the events will start broadcasting LIVE when opened by the Examining Authority. If the Livestream does not initially work it may be resolved by refreshing the webpage.
13 Gorffennaf 2023
The Examination Library (PDF, 533KB) and Examination Timetable have been updated.
13 Gorffennaf 2023
The Examination Library will be updated as soon as practicable.
5 Gorffennaf 2023
- The agenda for Compulsory Acquisition Hearing 2 (CAH2) on Compulsory Acquisition and Temporary Possession Matters (PDF, 209KB).
- The agenda for Issue Specific Hearing 4 (ISH4) on the Draft Development Consent Order and Environmental Matters (PDF, 191 KB).
Should any parties wish to register to attend the hearings, please contact the case team via email: yorkshiregreen@planninginspectorate.gov.uk
4 Gorffennaf 2023
The agenda for Compulsory Acquisition Hearing 2 (CAH2) on Compulsory Acquisition and Temporary Possession Matters (PDF, 209 KB).
Should any parties wish to register to attend the hearing, please contact the case team via email: yorkshiregreen@planninginspectorate.gov.uk
27 Mehefin 2023
22 Mehefin 2023
20 Mehefin 2023
The Applicant has submitted a Notification of Request for Proposed Changes (PDF, 3MB)
20 Mehefin 2023
The Examination Library (PDF, 528 KB) has been updated.
13 Mehefin 2023
8 Mehefin 2023
The Examination Library will be updated as soon as practicable.
31 Mai 2023
- Note of the Accompanied Site Inspection (ASI) on 23 May 2023 (PDF, 209 KB)
- Action points for Issue Specific Hearing 3 (ISH3) (PDF, 122 KB)
The Examination Library (PDF 478 KB) has been updated.
30 Mai 2023
- Recordings and transcripts of Compulsory Acquisition Hearing 1 (CAH1)
- Recordings and transcripts of Issue Specific Hearing 3 (ISH3) on the draft Development Consent Order
The Examination Library will be updated shortly.
The remaining action points for hearings during the week commencing 22 May 2023 will be published as soon as possible.
30 Mai 2023
- Recordings and transcripts of Issue Specific Hearing 2 (ISH2) on Green Belt, Environmental Effects and Construction Matters
- Action points for Issue Specific Hearing 2 (ISH2) (PDF, 142 KB)
- Action points for Compulsory Acquisition Hearing 1 (CAH1) (PDF, 98 KB)
The Examination Library will be updated shortly.
The remaining recordings, transcripts and action points for hearings during the week commencing 22 May 2023 will be published as soon as possible.
26 Mai 2023
- Action points for Issue Specific Hearing 2 (ISH2) (PDF, 142 KB)
- Action points for Compulsory Acquisition Hearing 1 (CAH1) (PDF, 98 KB)
The Examination Library will be updated shortly.
The remaining recordings, transcripts and action points for hearings during the week commencing 22 May 2023 will be published as soon as possible.
22 Mai 2023
- Issue Specific Hearing 2 (ISH2) on Green Belt, Environmental Effects and Construction Matters (PDF, 280KB)
- Compulsory Acquisition Hearing 1 (CAH1) – Compulsory Acquisition, Temporary Possession and Related Matters (PDF, 210KB)
- Issue Specific Hearing 3 (ISH3) on the draft Development Consent Order and related matters (PDF, 183KB)
Anyone wishing to attend the hearings who has not yet registered to attend should contact the Case Team by emailing YorkshireGreen@planninginspectorate.gov.uk.
Anyone who wishes to observe the hearings in real time should use the livestream link: https://www.liveeventstream.online/planning-inspectorate-hearings/yorkshire-green. Please note that the events will start broadcasting LIVE when opened by the Examining Authority. If the Livestream does not initially work it may be resolved by refreshing the webpage.
15 Mai 2023
The agenda for Issue Specific Hearing 2 (ISH2) on Green Belt, Environmental Effects and Construction Matters (PDF, 280KB)
The agenda for Compulsory Acquisition Hearing 1 (CAH1) - Compulsory Acquisition, Temporary Possession and Related Matters (PDF, 210KB)
The agenda for Issue Specific Hearing 3 (ISH3) on the draft Development Consent Order and related matters (PDF, 183KB)
Should any parties wish to register to attend any of the hearings, please contact the case team via email: yorkshiregreen@planninginspectorate.gov.uk.
12 Mai 2023
The Examination Library will be updated as soon as practicable.
4 Mai 2023
The Examination Library (PDF, 429KB) has been updated.
2 Mai 2023
25 Ebrill 2023
The Examination Library (PDF, 347 KB) has been updated.
17 Ebrill 2023
The Examination Library (PDF, 347KB) has been updated.
6 Ebrill 2023
The Examination Library will be updated as soon as practicable.
29 Mawrth 2023
- The Examination Timetable (Rule 8 letter) (PDF, 303KB).
- The Examining Authority’s First Written Questions (PDF, 746KB). The Deadline for responses is 26 April 2023 (Deadline 2).
The Examination Library (PDF, 285KB) has been updated.
29 Mawrth 2023
Procedural decision following Preliminary Meeting.
28 Mawrth 2023
- The note of the Preliminary Meeting (PDF, 161 KB)
- Recordings and transcripts for Issue Specific Hearing 1 (ISH1)
The Examination Library (PDF, 294 KB) is updated.
24 Mawrth 2023
The following have now been published:
- Recording and transcript of the Preliminary Meeting
- Recording and transcript of the OFH1
- Action points for Open Floor Hearing 1 (OFH1) (PDF, 109 KB)
- Action points for Issue Specific Hearing 1 (ISH1) (PDF, 131 KB)
Recordings and transcripts for Issue Specific Hearing 1 will be published as soon as possible.
The Planning Inspectorate has also published s51 advice to the Applicant, in response to new environmental information received on 16 March 2023.
22 Mawrth 2023
Anyone wishing to attend the hearing who has not yet registered to attend should contact the Case Team by emailing YorkshireGreen@planninginspectorate.gov.uk
Anyone who wishes to observe the PM in real time should use the livestream link. Please note that the event will start broadcasting LIVE when opened by the Examining Authority. If the Livestream does not initially work it may be resolved by refreshing the webpage.
A Notification of an amendment to the appointment of the Examining Authority (PDF, 186 KB) has been published and the Examination Library (PDF, 281 KB) has been updated.
22 Mawrth 2023
22 Mawrth 2023
17 Mawrth 2023
Anyone wishing to attend the hearing who has not yet registered to attend should contact the Case Team by emailing YorkshireGreen@planninginspectorate.gov.uk
Anyone who wishes to observe the PM in real time should use the livestream link. Please note that the event will start broadcasting LIVE when opened by the Examining Authority. If the Livestream does not initially work it may be resolved by refreshing the webpage.
A Notification of an amendment to the appointment of the Examining Authority (PDF, 186 KB) has been published and the Examination Library (PDF, 281 KB) has been updated.
10 Mawrth 2023
- Procedural Deadline A submissions
- The Examining Authority's Agenda for Open Floor Hearing 1 (OFH1) on Wednesday 22 March 2023 (PDF, 127 KB)
Anyone wishing to attend the hearing should contact the Case Team by emailing YorkshireGreen@planninginspectorate.gov.uk
2 Mawrth 2023
The Agenda includes a list of the documents that may be referred to during the hearing. Parties should confirm attendance by Procedural Deadline A, Wednesday 8 March 2023.
The Examination Library (PDF, 235 KB) has been updated.
22 Chwefror 2023
22 Chwefror 2023
The letter also includes the draft Examination Timetable and Initial Assessment of Principal Issues.
21 Chwefror 2023
14 Chwefror 2023
The Examination Library (PDF, 215 KB) has been updated.
13 Chwefror 2023
19 Ionawr 2023
You can now register as an Interested Party
If you are unable to complete a registration form online and would like to register your interest, please call the helpline on: 0303 444 5000 to request a paper form.
The Applicant has informed the Planning Inspectorate that some persons with a legal interest in the land affected by the Proposed Development had not received the notification of the accepted application, due to various reasons, and were therefore not made aware of the period within which they could make a Relevant Representation. The Applicant has now notified the omitted persons who have been allowed further time to make Relevant Representations. If you are a person that has received the Applicant's notification dated 17 January 2023 (PDF, 3699 KB) and need assistance making a Relevant Representation, please contact us at YorkshireGreen@planninginspectorate.gov.uk or 0303 444 5000.
For further advice please see Advice Note 8.2: How to register to participate in an Examination.
You can check our step by step guide to find out more about having your say about a national infrastructure project