Amserlen yr archwiliad
Mae amserlen yr archwiliad yn dangos dyddiadau digwyddiadau a therfynau amser ar gyfer cyflwyniadau.
Os ydych wedi cofrestru i leisio'ch barn, gallwch wneud hyn yn ystod y cam archwilio.
Y cam archwilio
Agorodd yr archwiliad ar 24 April 2012
Caeodd yr archwiliad ar 24 October 2012
24 Ebrill 2012 - Deadline 1
CaeedigPreliminary Meeting
24 Ebrill 2012 - Preliminary Meeting
CaeedigThe purpose of the Preliminary Meeting is to enable views to be expressed about the way in which the application is to be examined.
2 Mai 2012 - Deadline 2
CaeedigNotice of procedural decision including confirmation of the examination timetable and first round of written questions from the Examining authority (ExA)
3 Mai 2012 - Deadline 3
CaeedigAccompanied site visit to the application site
3 Mai 2012 - Site Visit (Accompanied)
CaeedigThe initial site inspection in the company of any Interested Party or their representative.
6 Mehefin 2012 - Deadline 4
CaeedigDeadline for receipt of:
• Written representations • Responses to written questions • Local Impact Report (s) (LIRs) • Statements of common ground (SoCG)
4 Gorffennaf 2012 - Deadline 5
CaeedigDeadline for receipt of comments on:
• Relevant and written representations • Responses to the ExA’s questions • LIRs
18 Gorffennaf 2012 - Deadline 6
CaeedigIssue of the ExA’s second round of written questions
24 Gorffennaf 2012 - Deadline 7
CaeedigIssue specific (IS) hearing to consider the drafting aspects of the draft Development Consent Order, and the proposed agreement between the Applicant and local planning authorities under s106 of the Town and Country Planning Act 1990
24 Gorffennaf 2012 - Issue Specific Hearing 1
CaeedigIssue Specific Hearing to consider only the drafting aspects of the draft Development Consent Order, including proposed requirements, and the draft Section 106 Agreement. For the avoidance of doubt, this hearing is not to consider the underlying issues arising from the application or the representations which have been made about them, and will be done on an entirely without prejudice basis. The Panel's decision to hold the hearing should not be taken to imply that it has any view at this stage about whether the Order should be granted.
15 Awst 2012 - Deadline 8
CaeedigDeadline for (i) responses to the ExA’s second round of written questions and (ii) for interested parties to make representations to the ExA of the need for issue specific hearings
24 Awst 2012 - Deadline 9
CaeedigDeadline for i) interested parties to notify the ExA of their intention to be heard at an open floor (OF) hearing and ii) affected persons to notify the ExA of their wish to be heard at a compulsory acquisition (CA) hearing
24 Awst 2012 - Deadline 10
CaeedigLetter (Rule 17) from ExA to the Applicant and other specified IPs concerning the Conservation of Habitats and Species (Amendment) Regulations 2010
24 Awst 2012 - Deadline 11
CaeedigLetter (Rule 17(31)) from ExA to the Applicant and other specified interested parties concerning the Conservation of Habitats and Species (Amendment) Regulations 2010
24 Awst 2012 - Deadline 12
CaeedigExA notification of the programme for further IS hearings
24 Awst 2012 - Deadline 13
CaeedigDeadline for the receipt of comments on responses to the ExA’s second round of written questions
31 Awst 2012 - Deadline 14
CaeedigLetter from the ExA confirming dates and arrangements for the CA hearing
6 Medi 2012 - Deadline 15
CaeedigLetter from the ExA confirming dates and arrangements for the OF hearing
6 Medi 2012 - Deadline 16
CaeedigLetter from the ExA confirming the arrangements and agenda for the IS hearings on 18 and 19 September
18 Medi 2012 - Deadline 17
CaeedigIS hearing on drafting of the DCO and requirements, the draft deemed marine licence and proposed s106 agreement
18 Medi 2012 - Issue Specific Hearing 2
CaeedigIssue Specific Hearing into the draft Development Consent Order and requirements, the draft deemed Marine Licence and the proposed s106 agreement between the Applicant and other parties
19 Medi 2012 - Deadline 18
CaeedigIS hearing on the relationship between the Order and the COMAH Regulations
19 Medi 2012 - Issue Specific Hearing 3
Caeedigthe relationship between the provisions proposed to be granted by the Order and the subsequent detailed approvals to be obtained from the competent authority (HSE and the Environment Agency) within the COMAH Regulations 2 1999 as amended 2005, and any further amendments likely to be required as a consequence of Directive 2012/18/EU.
26 Medi 2012 - Deadline 19
CaeedigLetter (Rule 17) from the ExA to the Applicant concerning Crown Land
26 Medi 2012 - Deadline 20
CaeedigFurther letter from the ExA setting out the agenda and arrangements for the CA hearing
28 Medi 2012 - Deadline 21
CaeedigLetter (Rule 17) from the ExA to the Applicant and specified IPs inviting written representations about a proposed addition to Requirement 6 of the Order
2 Hydref 2012 - Deadline 22
CaeedigLetter from the ExA to the Applicant concerning proposed amendments to plans relating to the brine discharge outfall
3 Hydref 2012 - Deadline 23
CaeedigLetter (Rule 17) from ExA to the Applicant concerning Part 5 of the Book of Reference
3 Hydref 2012 - Deadline 24
CaeedigLetter (Rule 17) from the ExA to the Applicant concerning the draft Hazardous Substances Direction, preparation of the final draft DCO and a list of minor corrections to the Order
8 Hydref 2012 - Deadline 25
CaeedigDeadline for the submission of the final draft of the DCO and proposed s106 agreement
9 Hydref 2012 - Deadline 26
CaeedigCA hearing (one session only held on 9 October)
9 Hydref 2012 - Compulsory Acquisition Hearing 1
CaeedigCAH - Day 1
10 Hydref 2012 - Deadline 27
CaeedigCA hearing (one session only held on 9 October)
10 Hydref 2012 - Compulsory Acquisition Hearing 2
CaeedigCAH - Day 2
11 Hydref 2012 - Deadline 28
CaeedigLetter (Rule 17) from the ExA to the Applicant concerning information requested at the CA hearing on 9 October, and further to the final draft DCO
17 Hydref 2012 - Deadline 29
CaeedigOF hearing (six sessions held over two days)
17 Hydref 2012 - Open Floor Hearing 1
CaeedigOFH - Day 1
18 Hydref 2012 - Deadline 30
CaeedigOF hearing (six sessions held over two days)
18 Hydref 2012 - Open Floor Hearing 2
CaeedigOFH - Day 2
19 Hydref 2012 - Deadline 31
CaeedigAccompanied site visit to the application site
26 Hydref 2012 - Deadline 32
CaeedigNotification from the ExA of the completion of the examination.